Home / Browse projects / Thane, Maharashtra / ATHENA

Registered No litigation declared Residential / Group Housing project

ATHENA

By IMPRESSIONS NXT

RG-MH-21692 · RERA P51700023695 · Last updated on MahaRERA portal: 27 Jun 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 24 months from the original
0 of 11Construction stages donefurthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 78 documents Report an error

ATHENA is a Residential / Group Housing project by IMPRESSIONS NXT in Thane, Maharashtra, registered with MahaRERA as P51700023695 on 2 Jan 2020. Possession is promised by 31 Dec 2026. The completion date has moved by 24 months from the original filing.

At a glance

Project

  • NameATHENA
  • TypeResidential / Group Housing
  • Location
    • DNC ROAD
    • OPPOSITE DNC COLLEGE DOMBIVLI EAST
    • DOMBIVLI
    • Kalyan
    • Thane
    • 421201
  • Pincode421201
  • RERA no.P51700023695
  • ReraGenie IDRG-MH-21692

Builder

  • NameIMPRESSIONS NXT
  • Entity typePartnership
  • GSTIN27AAGFI7396M1ZK
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersMILIND VASANT JOSHI, ARCHIT ABHAY KAMAT, MAHESH SHARAD DESAI, SACHIN RAMESH CHITNIS
  • Other registrations3 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredJan 2020First promiseDec 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on2 Jan 2020
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2024)
  • Buildings1 building record
  • Documents filed78 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ATHENANA160000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 27 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

ATHENA: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 27 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed46

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots46
Closed/Covered40
Open Space6

Land and ownership7

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,736 sq m
Land owned byThe promoter, with other names on the file
Named landowners7
LandownerVillageDistrict
ATMARAM PUNDLIK MHATREDOMBIVLIThane
DEEPAK PUNDLIK MHATREDOMBIVLIThane
MADHUKAR PUNDLIK MHATREDOMBIVLIThane
PRAMOD PUNDLIK MHATREDOMBIVLIThane
SUNANDA PRABHAKAR MHATREDOMBIVLIThane
SHUBHANGI CHARUHAS GHARATDOMBIVLIThane
SUSHMA SUHAS MISALDOMBIVLIThane

Approvals and building plan

Permissible FSI3180.74
Proposed, not sanctioned1,810 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRAMNAGAR DOMBIVLI

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUDAY MANSUKHLAL CHOPDA
EngineerARVIND PATEL
Chartered AccountantRISHI DESHMUKH
PartnerRole in project
IMPRESSIONS NXT-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700025908Dec 2024 → Dec 2026

Reason as filed by the promoterDUE TO SHORTAGE OF MATERIAL AND LABOUR

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Dec 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Sep 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Sep 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Sep 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed78

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: athena 1.pdf27 Jun 2026
Form 2File: athena 2.pdf27 Jun 2026
Form 3File: athena -3.pdf27 Jun 2026
Disclosure of Sold and Booked InventoryFile: sold -44.pdf27 Jun 2026
Form 1File: RERA ARCHITECT CERTIFICATE - 31-12-2025.pdf13 Feb 2026
Form 2File: Athena Form 2.pdf13 Feb 2026
Form 3File: athena fom 3.pdf13 Feb 2026
Disclosure of Sold and Booked InventoryFile: saold unsold athena.pdf13 Feb 2026
Form 1File: RERA ARCHITECT CERTIFICATE - 30-09-2025 (3).pdf22 Nov 2025
Form 2File: Athena Form 2 Engineer certificate 30-6-25_0001 (1).pdf22 Nov 2025
Form 3File: Athena Form 3 CA certificate 30-6-25_0001 (1).pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: sold unsold athena.pdf22 Nov 2025
Form 1File: Athena Form 1 Architect certificate 30-6-25_0001.pdf21 Jul 2025
Form 2File: Athena Form 2 Engineer certificate 30-6-25_0001.pdf21 Jul 2025
Form 3File: Athena Form 3 CA certificate 30-6-25_0001.pdf21 Jul 2025
Disclosure of Sold and Booked InventoryFile: athena sold.pdf21 Jul 2025
Form 1File: Form No 01 31-03-2025.pdf17 Jul 2025
Form 2File: Form No 02 31-03-2025.pdf17 Jul 2025
Form 3File: Form No 03 31-03-2025.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD 31-03-2025.pdf17 Jul 2025
Details of encumbrances concerned to FinanceFile: Athena Legal Litigation Encumbrance_0001.pdf14 Apr 2025
Details of encumbrancesFile: Athena self declaration regarding Encumbrance to finance_0001.pdf14 Apr 2025
Proforma of Allotment letterFile: Athena Rera allotment letter_0001 - converted.pdf14 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Athena Architect certificate Form 1_0001.pdf14 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Athena Engineer certificate Form 2_0001.pdf14 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Athena Engineer certificate quality assurance Form 2A_0001 - converted.pdf14 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Athena Engineer certificate quality assurance Form 2A_0001 - converted.pdf14 Apr 2025
Disclosure of sold/ booked inventoryFile: Athena disclosure of sold-unsold inventory_0001.pdf14 Apr 2025
Declaration about Commencement CertificateFile: Athena declaration about commencement certificate format D_0001.pdf14 Apr 2025
Declaration about Commencement CertificateFile: Athena declaration about commencement certificate format D_0001_1.pdf14 Apr 2025
Declaration about Commencement CertificateFile: Athena declaration about commencement certificate format D_0001_2.pdf14 Apr 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Athena Format A Declaration about rera designated bank account_0001.pdf14 Apr 2025
Deviation Report with respect to Allotment letterFile: Athena Deviation report copy of allotment letter_0001.pdf14 Apr 2025
Details of encumbrances concerned to LegalFile: Athena Legal Litigation Encumbrance_0001.pdf14 Apr 2025
Other - FinanceFile: Athena disclosure for secured - unsecured finace_0001.pdf14 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Athena Engineer certificate quality assurance Form 2A_0001 - converted.pdf14 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Athena Engineer certificate quality assurance Form 2A_0001 - converted.pdf14 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22) (3).pdf14 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Athena Engineer certificate quality assurance Form 2A_0001 - converted.pdf14 Apr 2025
Disclosure for secured/unsecured finance availed for the projectFile: Athena disclosure for secured - unsecured finace_0001.pdf14 Apr 2025
CERSAI detailsFile: Athena Cersai letter_0001.pdf12 Apr 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Athena declaration about separate bank account for project _0001.pdf12 Apr 2025
Deviation Report with respect to model copy of AgreementFile: Athena Deviation report copy of Agreement _0001.pdf12 Apr 2025
Details of encumbrances concerned to FinanceFile: 1 Details of encumbrances.pdf24 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Athena Architect Certificate Form 1 30-9-24_0001.pdf24 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Athena Architect Certificate Form 1 30-6-24.pdf24 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Athena Engineers certificate form 2 30-9-24.pdf24 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Athena Engineers certificate form 2 30-6-24_0001.pdf24 Dec 2024
Details of encumbrances concerned to LegalFile: 1 Details of encumbrances.pdf24 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Athena 1-4-2023 to 31-3-2024_0001.pdf24 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Impre NXT Athena CA form 5 Annual report on statement 20-21.pdf19 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Impre NXT Athena CA form 5 Annual report on statement 19-20.pdf9 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Impre NXT Athena CA form 5 Annual report on statement 21-22_0001.pdf9 Feb 2024
Disclosure of sold/ booked inventoryFile: Athena rera update sold booked disclosure inventory_0001.pdf2 Jan 2024
Layout approvalFile: Athena Blue 12 (1).pdf9 Sep 2023
Layout approvalFile: Athena blue 22 (1).pdf9 Sep 2023
Building plan approvalFile: Athena blue 22 (1).pdf9 Sep 2023
Building plan approvalFile: Athena blue 22 (1).pdf9 Sep 2023
Building plan approvalFile: Athena Blue 12 (1).pdf9 Sep 2023
Copy of Layout Approval (in case of layout)File: Athena Blue 12 (1).pdf9 Sep 2023
Copy of Layout Approval (in case of layout)File: Athena blue 22 (1).pdf9 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: Athena blue 22 (1).pdf9 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: Athena blue 22 (1).pdf9 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: Athena Blue 12 (1).pdf9 Sep 2023
Commencement Certificates / NA Order for plotted developmentFile: REVISED SANCTION PLAN LETER.pdf9 Sep 2023
Declaration in FORM BFile: ATHENA FORM B.pdf19 Dec 2019
Proforma of Allotment letterFile: PS MHATRE AGREEMENT.pdf19 Dec 2019
Layout approvalFile: PS MHATRE PLAN.pdf11 Dec 2019
Building plan approvalFile: PS MHATRE PLAN.pdf11 Dec 2019
PAN CardFile: impressions NXT pancard .pdf11 Dec 2019
Copy of the legal title reportFile: TITLE SEARCH REPORT.pdf11 Dec 2019
Details of encumbrancesFile: PS MHATRE ENCU CERTIFICATE.pdf11 Dec 2019
Copy of Layout Approval (in case of layout)File: PS MHATRE PLAN.pdf11 Dec 2019
Building Plan Approval / NA Order for plotted developmentFile: PS MHATRE PLAN.pdf11 Dec 2019
Commencement Certificates / NA Order for plotted developmentFile: PS MHATRE CC.pdf11 Dec 2019
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA ARCHITECT CERTIFICATE.pdf11 Dec 2019
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERTIFICATE REVISED.pdf11 Dec 2019
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: P S Mhatre_ Form 3.pdf2 Dec 2019

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 24 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ATHENA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near OPPOSITE DNC COLLEGE DOMBIVLI EAST7,600+ in Thane

Builder: IMPRESSIONS NXT

IMPRESSIONS NXT has 4 registrations on MahaRERA, including ATHENA and SILVIA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if ATHENA is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ATHENA?

The registered promoter entity is IMPRESSIONS NXT, a partnership as per the filing. Its GSTIN 27AAGFI7396M1ZK can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ATHENA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ATHENA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ATHENA?

The professionals named in the filing: Architect: UDAY MANSUKHLAL CHOPDA; Engineer: ARVIND PATEL; Chartered Accountant: RISHI DESHMUKH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ATHENA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ATHENA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ATHENA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.