Home / Browse projects / Mumbai Suburban, Maharashtra / Astrum

Registered Litigation declared Residential / Group Housing project

Astrum

By Upvan Developers

RG-MH-29549 · RERA P51800029353 · Last updated on MahaRERA portal: 20 Jul 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 2 cases
  • 1 complaint at MahaRERA
  • Completion date moved by 24 months
  • 3 extensions taken
  • Rs 40.00 crore secured on the land, in favour of Aditya Birla Sun Life AMC Limited

Clear

  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 24 months from the original
5 of 11Construction stages donefurthest along: Staircases, 73%
15 of 68Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 188 documents Report an error

Astrum is a Residential / Group Housing project by Upvan Developers in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800029353 on 18 May 2021. Possession is promised by 31 Dec 2026. The completion date has moved by 24 months from the original filing. 53 of the 68 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameAstrum
  • TypeResidential / Group Housing
  • Location
    • Upper Govind Nagar
    • Malad (East)
    • Borivali
    • Mumbai Suburban
    • 400097
  • Pincode400097
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800029353
  • ReraGenie IDRG-MH-29549

Builder

  • NameUpvan Developers
  • Entity typePartnership
  • Other registrations1 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredMay 2021First promiseDec 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on18 May 2021
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed188 files

Current status

78%53 of 68 units booked
78.1%Work done, per cost certificate

Figures as on 20 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AstrumNA272168068

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 73%.

Astrum: 65% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises55%
Sanitary Fittings within the flats / premises4%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks73%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.42%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.45%

Progress on shared amenities15

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes75%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes40%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes40%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes30%
Electrical meter room, sub-station, receiving stationYes10%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed176

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots176
Closed/Covered176

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,800 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofAditya Birla Sun Life AMC Limited
Secured amountRs 40.00 crore
CERSAI search filedYes
Declared on9 Jul 2025

Approvals and building plan

Sanctioning authorityMunicipal Corporation of Greater Mumbai
Permissible FSI11929.88
Proposed, not sanctioned6,881 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor Conwood House Yashodham Gen A K Vaidya Marg Goregaon East Mumbai 400 063
Estimated costRs 91.60 cr
Cost incurredRs 71.57 cr
Work done78.12%
BuildingWingEstimatedIncurred
AstrumNARs 67.89 crRs 52.01 cr
-NARs 23.71 crRs 19.56 cr

Certifying professionals and partners9

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUday Dhawan
ArchitectUday V Dhawan
EngineerZakirhusain Chaugule
EngineerVP Consultants
EngineerRECI Engineering
Chartered AccountantM A Parikh Shah Associates
Chartered AccountantN. A. Shah Associates LLP
Chartered AccountantNehali & Co.
Chartered AccountantNehali & Co
PartnerRole in project
Upvan Developers-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800016996Dec 2024 → Dec 2025

Reason as filed by the promoterFollowing are the reasons for delay in construction works of the captioned Project: a. Immediately as we commenced the works of shore piling and excavation in November, 2021, the residents of the adjoining buildings with ulterior motives and desires, started to complain on frivolous and completely untrue grounds, including alleged noise/ sound that was generated in the process of such works. Although we had procured appropriate approvals, adhered to the law prescribed parameters of noise and also conducted further tests from accredited labs and implemented strong sound dampening measures to co

EA12032620193Dec 2024 → Jun 2026

Reason as filed by the promoterFollowing are the reasons for delay in construction works of Astrum (“Project”): a. Immediately as we commenced the works of shore piling and excavation,we realized that the rock under the ground was much harder than shown in the tests,which left us with no choice but to explore more options like controlled blasting, diamond cutting, etc. which were much higher in cost and time consuming than the regular methods b. Although we had appropriate approvals for the above,the residents of the adjoining buildings with ulterior motives and desires,started to complaint on frivolous and completely untru

EA11062621314Dec 2024 → Dec 2026

Reason as filed by the promoterFollowing are the reasons for delay in construction works of Astrum (“Project”): a. Extreme Climatic Conditions & Labour Shortages (March-May 2026): During the severe summer months of 2026, acute heat conditions impacted labour productivity due to dehydration and health risks, while reverse migration led to shortages of skilled and unskilled labour. Consequently, approximately two additional months of effective working time were lost despite efforts to maintain a fully mobilized site b. Ongoing Elections in states and the SIR process conducted there: During the months of March & April 2026 the

Litigation declared2

CaseCourtStatus
25461/2016High Court of Judicature at BombayPending
2144/2016High Court of Judicature at BombayPending

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12602768Sunnil S KurupUpvan Developers12/05/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Nov 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Apr 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Dec 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed188

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 188 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Astrum - Form 1 - 30-06-2026.pdf20 Jul 2026
Withdrawal Update Form 2File: Astrum - Form 2 - 30-06-2026.pdf20 Jul 2026
Withdrawal Update Form 3File: Astrum - Form 3 - 30-06-2026.pdf20 Jul 2026
Form 2A (FY 2023-2024)File: Astrum - Form 2A - 31-03-2024.pdf1 Jul 2026
Form 2A (FY 2024-2025)File: Astrum Form 2A - 31-03-2025.pdf1 Jul 2026
Form 2A (FY 2025-2026)File: Astrum - Form 2A - 31-03-2026.pdf1 Jul 2026
Form 2A (FY 2021-2022)File: Astrum - Form 2A - 31-03-2022.pdf16 Jun 2026
Form 2A (FY 2022-2023)File: Form 2A - Astrum - 31-03-2023.pdf16 Jun 2026
Form 5 (FY 2021-2022)File: Astrum-Form-5-2021-2022.pdf16 Jun 2026
Withdrawal Update Form 1File: Astrum - Form 1 - 20-04-2026.pdf20 Apr 2026
Withdrawal Update Form 2File: Astrum - Form 2 - 31-03-2026.pdf20 Apr 2026
Withdrawal Update Form 3File: Astrum - Form 3 - 31-03-2026.pdf20 Apr 2026
Form 2A (FY 2025-2026)File: Astrum - Form 2A - 31-03-2026.pdf20 Apr 2026
Form 1File: Form 1 - Astrum -30-09-2023.pdf10 Mar 2026
Form 2File: Form 2 - Astrum - 30-09-2023.pdf10 Mar 2026
Form 3File: Form 3 - Astrum - 30-09-2023.pdf10 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold - Booked Inventory -Astrum - 30-09-2023.pdf10 Mar 2026
Form 1File: Form 1 - Astrum - 30-06-2023.pdf10 Mar 2026
Form 2File: Form 2 - Astrum - 30-06-2023.pdf10 Mar 2026
Form 3File: Form 3 - Astrum - 30-06-2023.pdf10 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold - Booked Inventory - 30-06-2023.pdf10 Mar 2026
Form 1File: Form 1 - Astrum - 31-03-2023.pdf10 Mar 2026
Form 2File: Form 2 - Astrum - 31-03-2023.pdf10 Mar 2026
Form 3File: Form 3 - Astrum - 31-03-2023.pdf10 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - Astrum - 31-03-2023.pdf10 Mar 2026
Form 1File: Form 1 - Astrum - 31-12-2022.pdf10 Mar 2026
Form 2File: Form 2 - Astrum - 31-12-2022.pdf10 Mar 2026
Form 3File: Form 3 - Astrum - 31-12-2022.pdf10 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold - Booked Inventory - 31-12-2022.pdf10 Mar 2026
Form 1File: Form 1 - Astrum - 30-09-2022.pdf10 Mar 2026
Form 2File: Form 2 - Astrum - 30-09-2022.pdf10 Mar 2026
Form 3File: Form 3 - Asrtrum - 30-09-2022.pdf10 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold - Booked Inventory - 30-09-2022.pdf10 Mar 2026
Form 1File: Form 1 - Astrum - 30-06-2022.pdf10 Mar 2026
Form 2File: Form 2 - Astrum - 30-06-2022.pdf10 Mar 2026
Form 3File: Form 3 - Astrum - 30-06-2022.pdf10 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold - Booked Inventory - 30-06-2022.pdf10 Mar 2026
Form 1File: Form 1 - Astrum - 31-03-2022.pdf10 Mar 2026
Form 2File: Form 2 - Astrum - 31-03-2022.pdf10 Mar 2026
Form 3File: Form 3 - Astrum - 31-03-2022.pdf10 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - Astrum - 31-03-2022.pdf10 Mar 2026
Form 1File: Form 1 - Astrum - 31-12-2021.pdf10 Mar 2026
Form 2File: Form 2 - Astrum - 31-12-21.pdf10 Mar 2026
Form 3File: Form 3 - Astrum - 31-12-2021.pdf10 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold - Booked Inventory - 31-12-2021.pdf10 Mar 2026
Form 1File: Form 1 - Astrum - 30-09-2021.pdf10 Mar 2026
Form 2File: Form 2 - Astrum - 30-09-2021.pdf10 Mar 2026
Form 3File: Form 3 - Astrum - 30-09-2021.pdf10 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold - Booked Inventory - 30-09-2021.pdf10 Mar 2026
Form 1File: Form 1 - Astrum - 30-06-2021.pdf10 Mar 2026
Form 2File: Form 2 - Astrum -30-06-2021.pdf10 Mar 2026
Form 3File: Form 3 - Astrum - 30-06-2021.pdf10 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold - Booked Inventory - Astrum - 30-06-2021.pdf10 Mar 2026
Form 5 (FY 2023-2024)File: Form 5 - Astrum - 2023-2024.pdf10 Mar 2026
Form 5 (FY 2022-2023)File: Form 5 - Astrum - 2022-2023.pdf10 Mar 2026
Form 1File: Form 1 - Astrum - 31-03-2025.pdf2 Mar 2026
Form 2File: Form 2 - Astrum - 31-03-2025.pdf2 Mar 2026
Form 3File: Form 3 - Astrum - 31-03-2025.pdf2 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - Astrum - 31-03-2025.pdf2 Mar 2026
Form 1File: Form 1 - Astrum - 31-12-2024.pdf2 Mar 2026
Form 2File: Form 2 - Astrum - 31-12-2024.pdf2 Mar 2026
Form 3File: Form 3 - Astrum - 31-12-2024.pdf2 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - Astrum - 31-12-2024.pdf2 Mar 2026
Form 1File: Form 1 - Astrum - 30-09-2024.pdf2 Mar 2026
Form 2File: Form 2 - Astrum - 30-09-24.pdf2 Mar 2026
Form 3File: Form 3 - Astrum - 30-09-2024.pdf2 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - Astrum - 30-09-2024.pdf2 Mar 2026
Form 1File: Form 1 - Astrum - 30-06-2024.pdf2 Mar 2026
Form 2File: Form 2 - Astrum - 30-06-2024.pdf2 Mar 2026
Form 3File: Form 3 - Astrum - 30-06-2024.pdf2 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - Astrum - 30-06-2024.pdf2 Mar 2026
Form 1File: Form 1 - Astrum - 31-03-2024.pdf2 Mar 2026
Form 2File: Form 2 - Astrum - 31-03-2024.pdf2 Mar 2026
Form 3File: Form 3 - Astrum - 31-03-2024.pdf2 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Booked Inventory - Astrum - 31-03-2024.pdf2 Mar 2026
Form 1File: Form 1 - Astrum - 31-12-2023.pdf2 Mar 2026
Form 2File: Form 2 - Astrum - 31-12-2023.pdf2 Mar 2026
Form 3File: Form 3 - Astrum - 31-12-2023.pdf2 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold - Booked Inventory - Astrum - 31-12-2023.pdf2 Mar 2026
Withdrawal Update Form 1File: Astrum - Form 1 - 31-12-2025.pdf20 Jan 2026

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
WoodlandsMSD Upper Govind Nagar Malad East Mumbai 400 09743CompletedDec 2016Late, May 2017

How this compares with Mumbai Suburban

78%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 24 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Astrum on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Malad (East)6,700+ in Mumbai Suburban

2 kmAstrumCompleted 187Lapsed / revoked 111Other 180Dot size: filed unitsN

Filed coordinates, straight-line distance. 478 registered projects within 2 km.

Builder: Upvan Developers

Upvan Developers has 2 registrations on MahaRERA, including Astrum and Woodlands Reserve. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 1 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Astrum is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Astrum?

The registered promoter entity is Upvan Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Astrum?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Astrum?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Astrum?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Astrum?

The professionals named in the filing: Architect: Uday Dhawan; Architect: Uday V Dhawan; Engineer: Zakirhusain Chaugule; Engineer: VP Consultants; Engineer: RECI Engineering; Chartered Accountant: M A Parikh Shah Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Astrum?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Astrum. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Astrum to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.