ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / ASR CAPITAL

Registered No litigation declared Commercial project

ASR CAPITAL

By ACEPRIME DEVELOPERS LLP

RG-MH-75720 · RERA P52100077121 · Last updated on MahaRERA portal: 14 Jul 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
3 of 11Construction stages donefurthest along: Staircases, 57%
0Complaints at MahaRERAon this registration
Jump to the 67 documents Report an error

ASR CAPITAL is a Commercial project by ACEPRIME DEVELOPERS LLP in Pune, Maharashtra, registered with MahaRERA as P52100077121 on 23 Jul 2024. Possession is promised by 31 Dec 2026.

At a glance

Project

  • NameASR CAPITAL
  • TypeCommercial
  • Location
    • Pimpale Gurav
    • Pune City
    • Pune
    • 411027
  • Pincode411027
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100077121
  • ReraGenie IDRG-MH-75720

Builder

  • NameACEPRIME DEVELOPERS LLP
  • Entity typePartnership
  • PartnersRAJENDRA POPAT GHANWAT, AMIT SHIVAJIRAO JADHAV

Key dates

this monthRegisteredJul 2024PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on23 Jul 2024
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed67 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ASR CAPITALNA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 57%.

ASR CAPITAL: 35% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure33%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks57%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 14 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed88

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots88
Closed/Covered88

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area886 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI946.09
Proposed, not sanctioned946 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPOUD ROAD, PUNE

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectM B ARCHITECTS
EngineerVikas Uttam Gaikwad
Chartered AccountantJENIL SHAH & ASSOCIATES
PartnerRole in project
ACEPRIME DEVELOPERS LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 May 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Jun 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Mar 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed67

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 Architecture Certifficate.pdf14 Jul 2026
Form 2File: FORM 2 Engineers certificate.pdf14 Jul 2026
Form 3File: Form 3 CA.pdf14 Jul 2026
Disclosure of Sold and Booked InventoryFile: sold inventory details.pdf14 Jul 2026
Form 1File: Form 1Aceprime.pdf16 Apr 2026
Form 2File: Form 2Engineers certificate 31-03-26.pdf16 Apr 2026
Form 3File: Form 3 Aceprime.pdf16 Apr 2026
Disclosure of Sold and Booked InventoryFile: Sold Inventory Certificate 31-3-26.pdf16 Apr 2026
Form 1File: FORM 1 Architectur Certificate MB Architech 31-12-25.pdf21 Jan 2026
Form 2File: Form 2 Engineers certificate 31-12-25.pdf21 Jan 2026
Form 3File: FORM 3 CA certificate.pdf21 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold Inventory Certificate 31-12-25.pdf21 Jan 2026
Form 1File: Form 1Architetch certificate MB Arce prime 30-5-25.pdf11 Oct 2025
Form 2File: Form2 Engineers certificate 30-9-25.pdf11 Oct 2025
Form 3File: Form 3ACEPRIME CA 30 Sept 25.pdf11 Oct 2025
Disclosure of Sold and Booked InventoryFile: disclosure of sold and book inventory.pdf11 Oct 2025
Form 1File: Architecture certificate.pdf16 Jul 2025
Form 2File: Engineers certificate12-7-25.pdf16 Jul 2025
Form 3File: Form 3 for CA Certification-signed 12-7-25.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: sold inventory.pdf16 Jul 2025
Form 1File: Architech certificate.pdf16 Jul 2025
Form 2File: Engineers certificate 12-10-24.pdf16 Jul 2025
Form 3File: Form 3 (1)-CA.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Inventory Certificate.pdf16 Jul 2025
Form 1File: aRCHITECH CERTIFICATE.pdf16 Jul 2025
Form 2File: Engineers certificate 18-01-25 (1).pdf16 Jul 2025
Form 3File: Form 3 for CA Certification.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Inventory Certificate.pdf16 Jul 2025
Form 1File: aRCHITECH CERTIFICATE.pdf16 Jul 2025
Form 2File: Engineers certificate 18-01-25 (1).pdf16 Jul 2025
Form 3File: Form 3 for CA Certification.pdf16 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Inventory Certificate.pdf16 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf28 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 for CA Certification.pdf28 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate 18-01-25.pdf28 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech certificate.pdf12 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 (1)-CA.pdf12 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate 12-10-24.pdf12 Dec 2024
Layout approvalFile: Unit Declaration.pdf26 Jun 2024
Copy of Layout Approval (in case of layout)File: Unit Declaration.pdf26 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Final.pdf18 Jun 2024
Details of encumbrances concerned to FinanceFile: Encumbrance Letter - Finance and Legal.pdf20 May 2024
Details of encumbrances concerned to LegalFile: Encumbrance Letter - Finance and Legal.pdf20 May 2024
Copy of the legal title reportFile: Titel Report .pdf3 May 2024
Proforma of Agreement for saleFile: Draft of Agreement.pdf3 May 2024
Other - LegalFile: Sale Deed.pdf3 May 2024
Other - LegalFile: Sat Bara.pdf3 May 2024
Other - LegalFile: Supplymentory Deed -Admmission of Partner.pdf3 May 2024
Other - LegalFile: Suuplymentory Deed-Resignation.pdf3 May 2024
CERSAI detailsFile: CERSAI certificate.pdf25 Apr 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate Bank Ac_.pdf25 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: CC Updated.pdf18 Apr 2024
Other - TechnicalFile: Annexure A.pdf8 Apr 2024
Layout approvalFile: REVISE SANCTION PLAN 2_11zon.pdf28 Mar 2024
Building plan approvalFile: REVISE SANCTION PLAN_11zon.pdf28 Mar 2024
Copy of Layout Approval (in case of layout)File: REVISE SANCTION PLAN 2_11zon.pdf28 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: REVISE SANCTION PLAN_11zon.pdf28 Mar 2024
Declaration about Commencement CertificateFile: Declaration About Commencement Certificate.pdf28 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate.pdf28 Mar 2024
PAN CardFile: PAN Cards.pdf8 Feb 2024
Copy of the legal title reportFile: Titel Report .pdf8 Feb 2024
Declaration in FORM BFile: Form B.pdf8 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Form 1 .pdf8 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Other Real Estate Organizations .pdf8 Feb 2024
Proforma of Allotment letterFile: Allotment Letter.pdf8 Feb 2024
Deviation Report with respect to Allotment letterFile: Deviation Report For Allotment Letter.pdf8 Feb 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report For Agreement To sale .pdf8 Feb 2024

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ASR CAPITAL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pimpale Gurav13,700+ in Pune

2 kmASR CAPITALCompleted 41Lapsed / revoked 24Other 44Dot size: filed unitsN

Filed coordinates, straight-line distance. 109 registered projects within 2 km.

Builder: ACEPRIME DEVELOPERS LLP

ACEPRIME DEVELOPERS LLP has 1 registration on MahaRERA, including ASR CAPITAL. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if ASR CAPITAL is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ASR CAPITAL?

The registered promoter entity is ACEPRIME DEVELOPERS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ASR CAPITAL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ASR CAPITAL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ASR CAPITAL?

The professionals named in the filing: Architect: M B ARCHITECTS; Engineer: Vikas Uttam Gaikwad; Chartered Accountant: JENIL SHAH & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ASR CAPITAL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ASR CAPITAL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ASR CAPITAL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.