Home / Browse projects / Thane, Maharashtra / ASHWATHI HEIGHTS

Registered No litigation declared Others project

ASHWATHI HEIGHTS

By PRACHITI CONSTRUCTIONS

RG-MH-19318 · RERA P51700078444 · Last updated on MahaRERA portal: 30 Jun 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 2 completed earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 12 months from the original
4 of 11Construction stages donefurthest along: Internal walls, 50%
42 of 52Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 56 documents Report an error

ASHWATHI HEIGHTS is a Others project by PRACHITI CONSTRUCTIONS in Thane, Maharashtra, registered with MahaRERA as P51700078444 on 12 Dec 2024. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 10 of the 52 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameASHWATHI HEIGHTS
  • TypeOthers
  • Location
    • MAHARASHTRA
    • KALYAN
    • KATEMANEVALI
    • Thane
    • 421306
  • Pincode421306
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700078444
  • ReraGenie IDRG-MH-19318

Builder

  • NamePRACHITI CONSTRUCTIONS
  • Entity typePartnership
  • GSTIN27ABDFP3487E1Z3
  • PartnersPrachiti Kailas Pawshe, Pradip chandrakant Misar, MAYUR PRADIP MISAR, PRAMOD CHANDRAKANT MISAR, SHRUTI ABHISHEK DIXIT
  • Declared earlier projects4 →

Key dates

this monthRegisteredDec 2024First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on12 Dec 2024
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed56 files

Current status

19%10 of 52 units booked
73.3%Work done, per cost certificate

Figures as on 30 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ASHWATHI HEIGHTSNA77361652

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 30 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 50%.

ASHWATHI HEIGHTS: 48% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 30 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed76

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots76
Closed/Covered8
Open Space68

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area597 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
ASHWATHI CO OPERATIVE HOUSING SOCIETYKATEMANEVALIThane

Approvals and building plan

Sanctioning authorityKalyan Dombivli Municipal corporation
Permissible FSI3698.23
Proposed, not sanctioned1,401 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO.106, SHRADHA MAHAL,NEAR SAKET COLLEGE,CHINCHPADA,KALYAN (E)-421306
Estimated costRs 6.40 cr
Cost incurredRs 4.69 cr
Work done73.35%
BuildingWingEstimatedIncurred
ASHWATHI HEIGHTSNARs 6.30 crRs 4.69 cr
-NARs 10.00 lakh-

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDe con consultants
EngineerAARNA STRUCTURAL CONSULTANTS
Chartered AccountantRoshan Gawde and Co.
Chartered AccountantJ. K. SONEE & ASSOCIATES
Chartered AccountantJK SONEE AND ASSOCIATES
Chartered AccountantSHAH MEET AND CO
PartnerRole in project
PRACHITI CONSTRUCTIONS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA30082502476Dec 2025 → Dec 2026

Reason as filed by the promoterDue to the on going heavy rains and monsoon of July and August 2025, we expect some delay in completion of internal works and hence there will be some delay in obtaining the completion certificate from KDMC, hence we are applying for maximum of 6 months of extension u/s 6 from MahaRERA. Thank you

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Aug 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 May 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Jan 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed56

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 march 2026 prachiti.pdf30 Jun 2026
Withdrawal Update Form 2File: PRACHITI FORM 2 Q4.pdf30 Jun 2026
Withdrawal Update Form 3File: Form-3 Q4 FY 2025-26_compressed.pdf30 Jun 2026
Withdrawal Update Form 1File: FORM 1 Dec 2025.pdf24 Mar 2026
Withdrawal Update Form 2File: Form 2 Sep 2025.pdf24 Mar 2026
Withdrawal Update Form 3File: Form 3 Q3 2025.pdf24 Mar 2026
Withdrawal Update Form 1File: Form 1 Sep 2025.pdf23 Mar 2026
Withdrawal Update Form 2File: Form 2 Sep 2025.pdf23 Mar 2026
Withdrawal Update Form 3File: Form-3 Sep 2025.pdf23 Mar 2026
Form 5 (FY 2024-2025)File: Form 5 Prachiti (1)-1-3.pdf16 Mar 2026
Withdrawal Update Form 1File: Architect’s Certificate.pdf30 Aug 2025
Withdrawal Update Form 2File: ascon form 2.pdf30 Aug 2025
Withdrawal Update Form 3File: PRACHITI CONSTRUCTION (2).pdf30 Aug 2025
Form 1File: PRACHITI FORM 1 MAR 2025 (1).pdf30 Jun 2025
Form 2File: form 2 prachiti.pdf30 Jun 2025
Form 3File: PRACHITI CONSTRUCTION (1).pdf30 Jun 2025
Disclosure of Sold and Booked InventoryFile: ilovepdf_merged (3).pdf30 Jun 2025
Form 1File: 20250104041305.pdf28 Jun 2025
Form 2File: form 2.pdf28 Jun 2025
Form 3File: d237eda3-1137-4551-9de0-ae49276b9bba.pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: ilovepdf_merged (3).pdf28 Jun 2025
Building plan approvalFile: Plan.pdf8 Jan 2025
Building plan approvalFile: Plan.pdf8 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf8 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: Plan.pdf8 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf8 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: Plan.pdf8 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Revised.pdf10 Dec 2024
Other - FinanceFile: Declaration About Land Cost.pdf3 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form-2 prachiti constuction_0001.pdf25 Nov 2024
Details of encumbrances concerned to FinanceFile: Legal Encumbrances.pdf22 Nov 2024
CERSAI detailsFile: Cersai Report.pdf22 Nov 2024
Details of encumbrances concerned to LegalFile: Legal Encumbrances.pdf22 Nov 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 1 Other - Legal.pdf21 Nov 2024
Proforma of Agreement for saleFile: FLAT SALE - T 421.pdf9 Nov 2024
Details of encumbrances concerned to FinanceFile: Self Declaration Regarding Encumbrances final.pdf21 Oct 2024
Details of encumbrances concerned to LegalFile: Self Declaration Regarding Encumbrances final.pdf21 Oct 2024
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for secured unsecured finance availed for the proje.pdf21 Oct 2024
Declaration in FORM BFile: Prachiti Form B.pdf15 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: plinth certificate.PDF15 Oct 2024
Other - TechnicalFile: ANNEXURE ‘A’.pdf15 Oct 2024
Proforma of Allotment letterFile: Rera Allotment Letter.pdf11 Oct 2024
Copy of the legal title reportFile: Title Cetificate.pdf20 Aug 2024
Status of ConveyanceFile: Develoment Agreement Index.pdf14 Aug 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations.pdf14 Aug 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format-B.pdf13 Aug 2024
Building plan approvalFile: Commencement Certificates.pdf22 May 2024
Building Plan Approval / NA Order for plotted developmentFile: Commencement Certificates.pdf22 May 2024
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMNT CERTIFICATE.pdf22 May 2024
Deviation Report with respect to Allotment letterFile: DEVIATION REPORT WITH RESPECT TO ALLOTMENT LETTER.pdf22 May 2024
Deviation Report with respect to model copy of AgreementFile: DEVIATION REPORT WITH RESPECT TO MODEL COPY OF AGREEMENT.pdf22 May 2024
Layout approvalFile: Copy of Layout_compressed.pdf4 May 2024
Copy of Layout Approval (in case of layout)File: Copy of Layout_compressed.pdf4 May 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificates.pdf4 May 2024
PAN CardFile: PAN CARD.pdf26 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect’s Certificate.pdf26 Mar 2024

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise2 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
SAIDATTA PARADISE WING CP52100050847NEAR UNICARE HOSPITAL CHAKAN, Pune56May 2023OngoingDec 2028Not due yet
DWARKADHISH PARK BUILDING DP52100054421TRISHUL CHOWK, Pune40Jan 2024OngoingDec 2028Not due yet
SAIDATTA PARADISE WING AP52100014071Chakan, Pune77Nov 2017CompletedDec 2022Registered original: Jun 2021Oct 2022
SAIDATTA PARADISE WING BP52100014072Nanekarwadi (CT), Pune48Nov 2017CompletedMay 2019May 2018

How this compares with Thane

19%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 12 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ASHWATHI HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KALYAN7,600+ in Thane

2 kmASHWATHI HEIGHTSCompleted 43Lapsed / revoked 40Other 91Dot size: filed unitsN

Filed coordinates, straight-line distance. 174 registered projects within 2 km.

Builder: PRACHITI CONSTRUCTIONS

PRACHITI CONSTRUCTIONS has 1 registration on MahaRERA, including ASHWATHI HEIGHTS. Its filings disclose 4 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if ASHWATHI HEIGHTS is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ASHWATHI HEIGHTS?

The registered promoter entity is PRACHITI CONSTRUCTIONS, a partnership as per the filing. Its GSTIN 27ABDFP3487E1Z3 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ASHWATHI HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ASHWATHI HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ASHWATHI HEIGHTS?

The professionals named in the filing: Architect: De con consultants; Engineer: AARNA STRUCTURAL CONSULTANTS; Chartered Accountant: Roshan Gawde and Co.; Chartered Accountant: J. K. SONEE & ASSOCIATES; Chartered Accountant: JK SONEE AND ASSOCIATES; Chartered Accountant: SHAH MEET AND CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ASHWATHI HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ASHWATHI HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ASHWATHI HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.