ASHWA PLATINUM
By ASHWAMEDH BUILDERS AND DEVELOPERS MUMBAI
RG-MH-23964 · RERA P51800005636 · Last updated on MahaRERA portal: 7 Sep 2023
Source: official MahaRERA filing
Red flags
- 9 complaints at MahaRERA
- Completion date moved by 37 months
- 4 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ASHWA PLATINUM is a Residential / Group Housing project by ASHWAMEDH BUILDERS AND DEVELOPERS MUMBAI in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800005636 on 11 Aug 2017. The registration is recorded completed; possession was promised by 31 Dec 2023. The completion date has moved by 37 months from the original filing. 9 complaints are on record with the regulator.
At a glance
Project
- NameASHWA PLATINUM
- TypeResidential / Group Housing
- Location
- Dindayal Upadhyaya Marg
- Mulund
- Kurla
- Mumbai Suburban
- 400080
- Pincode400080
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800005636
- ReraGenie IDRG-MH-23964
Builder
- NameASHWAMEDH BUILDERS AND DEVELOPERS MUMBAI
- Entity typePartnership
- PartnerSANJAY RAMDAS THAKKAR
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on11 Aug 2017
- Promised completion31 Dec 2023
- Revised completionRevised to 31 Dec 2023 (originally 30 Nov 2020)
- Buildings2 building records
- Documents filed69 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SALE WING A | NA | 56 | 0 | 0 | 0 | 0 |
| SALE WING B | NA | 10 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 7 Sep 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
16 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 80%.
SALE WING A100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
SALE WING B68%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 60% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 40% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 7 Sep 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 70% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 80% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 90% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
Parking filed60
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| SALE WING A | 32 | 27 | 59 |
| SALE WING B | 1 | 0 | 1 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | NILESH SAWANT |
| Engineer | AJAY MAHALE |
| Chartered Accountant | S C BHATE AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| ASHWAMEDH BUILDERS AND DEVELOPERS MUMBAI | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterTo, Hon.Secreatary, Maharera. Sub.:-Request for Extension of Handing over of Possession Date.Rera-No. P5180000563 Dear Sir With reference to above mentioned subject we have to submit as under 1) We are developing residential project under the building name as "Ashwa Platinum" at CTS No 755PT, Kurla, Mumbai Suburban - 400080 in our above mentioned partnership firm i.e. M/s Ashwamedh Builders & Developers Mumbai. 2) Our project consist of two wings viz 'Wing A' & 'Wing B' & the possession handing over date of the said wings was 31/05/2020. 3) But now considering the COVID 19 pandemic & lockdown
Reason as filed by the promoterTo, Maharashtra Real Estate Regulatory Authority Reg.:-Project Registration No P51800005636 of M/s Ashwamedh Builders & Developers Mumbai. Sub.:-Request for Extension of Handing over of Possession Date. Dear Sir / Madam With reference to above mentioned subject we have to state & submit as under 1) We are developing a residential project under the building name as "Ashwa Platinum" at CTS No 755PT, Kurla, Mumbai Suburban - 400080 in our above mentioned partnership firm i.e. M/s Ashwamedh Builders & Developers Mumbai. 2) Our project consist of two wings viz 'Wing A' & 'Wing B' & the possession h
Reason as filed by the promoterThe Occupancy certificate for WIng A has been received and nearby all the allottees of Wing A" have been given possession and accordingly, we have put zero against the total number of the apartment and sold apartment or Wing A since no consent is required as a possession has been duly handed over to the allottees.
Reason as filed by the promoterThe Project is nearby at completion stage we seek extension till 31.12.23 since due to labor migration trend during the monsoon season resulted in a substantial reduction in available workers, causing a shortage of hands to carry out the necessary tasks. As they tend to go on vacation during the season because of heavy rainfall causing delay in project completion.
Complaints filed with MahaRERA9
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000054570 | Puneet N Shah | Nilesh Sawant and Darshana Sawant | 19/05/2018 |
| CC006000000439657 | Hiren Nagaria | ASHWAMEDH BUILDERS AND DEVELOPERS MUMBAI | 17/03/2024 |
| CC12400726 | VINIT PARSHURAM MANE | ASHWAMEDH BUILDERS AND DEVELOPERS MUMBAI | 11/11/2024 |
| CC12500306 | VINIT PARSHURAM MANE | ASHWAMEDH BUILDERS AND DEVELOPERS MUMBAI | 28/01/2025 |
| CC12502118 | Kamal Gobindram Sangtani | ASHWAMEDH BUILDERS AND DEVELOPERS MUMBAI | 27/06/2025 |
| CC12502163 | Nilesh Mahendra Thakkar | ASHWAMEDH BUILDERS AND DEVELOPERS MUMBAI | 30/06/2025 |
| CC12502318 | Pradeep Hari Salvi | ASHWAMEDH BUILDERS AND DEVELOPERS MUMBAI | 09/07/2025 |
| CC12503294 | Darshana Nilesh Sawant | ASHWAMEDH BUILDERS AND DEVELOPERS MUMBAI | 15/09/2025 |
| CC12503295 | Darshana Nilesh Sawant | ASHWAMEDH BUILDERS AND DEVELOPERS | 15/09/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 7 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 19 Feb 2022
Documents filed69
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 7 Sep 2023 |
| Declaration in FORM BFile: affidavit cum declaration.pdf | 6 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 6 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer Certificate for Quality Assurance.pdf | 6 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: Disclsure of sold Booked inventory.pdf | 6 Sep 2023 |
| Certificates of CA (Form 3)File: Undertaking to submit From no 3.pdf | 6 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Undertaking to submit From no 5.pdf | 6 Sep 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC-B Wing up to 7th Floor.pdf | 7 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer’s Certificate for quality Assurance.pdf | 25 Mar 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Declaration Of Interest Of Other Real Estate- DNS.pdf | 25 Mar 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Declaration Of Interest Of Other Real Estate-SRT.pdf | 25 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Undertaking to submit form no 5.pdf | 25 Mar 2023 |
| Proforma of Agreement for saleFile: Agreement for sale.pdf | 25 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold - Unsold - A Wing NEW.pdf | 23 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold - Unsold - B Wing NEW.pdf | 23 Jul 2022 |
| Deviation Report with respect to Allotment letterFile: No Deviation for Allotment Letter.pdf | 23 Jul 2022 |
| Deviation Report with respect to model copy of AgreementFile: Deviation for Agreement for sale_compressed.pdf | 23 Jul 2022 |
| Deviation Report with respect to model copy of AgreementFile: Deviation for Agreement for sale 2_compressed-1-5.pdf | 23 Jul 2022 |
| Deviation Report with respect to model copy of AgreementFile: Deviation for Agreement for sale 2_compressed-6-11.pdf | 23 Jul 2022 |
| Deviation Report with respect to model copy of AgreementFile: Deviation for Agreement for sale 2_compressed-12-17.pdf | 23 Jul 2022 |
| Deviation Report with respect to model copy of AgreementFile: Deviation for Agreement for sale 2_compressed-18-22.pdf | 23 Jul 2022 |
| Deviation Report with respect to model copy of AgreementFile: Deviation for Agreement for sale 2_compressed-23-29.pdf | 23 Jul 2022 |
| Details of encumbrances concerned to LegalFile: Declaration of No Encumbrances legal.pdf | 21 Jul 2022 |
| Declaration about Commencement CertificateFile: Declaration about CC.pdf | 21 Jul 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A.pdf | 21 Jul 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A (1).pdf | 21 Jul 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200242707662_For_Asset_Based_Search_21_07_2022_12_11_01_818.pdf | 21 Jul 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200242707684_For_Asset_Based_Search_21_07_2022_12_11_09_056.pdf | 21 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold - Unsold - A Wing.pdf | 21 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold - Unsold - B Wing.pdf | 21 Jul 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 2017-18.pdf | 21 Jul 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 2018-19.pdf | 21 Jul 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2019-20.pdf | 21 Jul 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2020-21.pdf | 21 Jul 2022 |
| Proforma of Allotment letterFile: Proforma allotment letter_compressed.pdf | 21 Jul 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: No Encumberance for Bank Account.pdf | 21 Jul 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Formation of Society.pdf | 16 Jul 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: commencement certificate.pdf | 15 Jul 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form -1.pdf | 15 Jul 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: commencement certificate.pdf | 19 Feb 2022 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: occupation certificate.pdf | 19 Feb 2022 |
| Architect’s Certificate on Completion of Project (Form 4)File: Architect Certificate Form -4.pdf | 19 Feb 2022 |
| Certificates of CA (Form 3)File: CA CERTIFICATE.pdf | 25 Nov 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf | 24 Nov 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS CERTIFICATE.pdf | 24 Nov 2020 |
| Details of Restarting of Construction work post lockdownFile: Maharashtra Real Estate Authority.pdf | 24 Nov 2020 |
| OtherFile: Maharashtra Real Estate Authority.pdf | 24 Nov 2020 |
| OtherFile: Scan 7 Jul 2020.pdf | 7 Jul 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE.pdf | 23 Feb 2018 |
| Building plan approvalFile: Rehab Sale bldg IOD.pdf | 26 Jul 2017 |
| Building plan approvalFile: Amended IOA Sale building.pdf | 26 Jul 2017 |
| Building plan approvalFile: LOI Revised LOI.pdf | 26 Jul 2017 |
| Building plan approvalFile: Oc of Rehab bldg.pdf | 26 Jul 2017 |
| Layout approvalFile: Amended IOA Sale building.pdf | 26 Jul 2017 |
| PAN CardFile: new pan card.pdf | 26 Jul 2017 |
| Copy of the legal title reportFile: Revise title certificate.pdf | 26 Jul 2017 |
| Details of encumbrancesFile: Declaration encumbrances.pdf | 26 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Amended IOA Sale building.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: Amended IOA Sale building.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: LOI Revised LOI.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: Oc of Rehab bldg.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: Rehab Sale bldg IOD.pdf | 26 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Rehab Sale building CC.pdf | 26 Jul 2017 |
| Declaration in FORM BFile: Affidavit cum declaration.pdf | 26 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTURE CERTIFICATE.pdf | 26 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE.pdf | 26 Jul 2017 |
| Certificates of CA (Form 3)File: CA CERTIFICATE new.pdf | 26 Jul 2017 |
| Certificates of CA (Form 3)File: CA CERTIFICATE new.pdf | 26 Jul 2017 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER AGREEMENT.pdf | 26 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 69 filed documents as one ZIP, foldered, with a manifest
Keep ASHWA PLATINUM on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mulund6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 330 registered projects within 2 km.
Eternia Towers A to D
Oberoi Constructions Limited
Bellanza Phase 1 - Wing A, B, C at The Prestig
PRESTIGE MULUND REALTY PRIVATE LIMITED
Atmosphere O2
Atmosphere Realty Pvt Ltd
Bellanza Phase 2 - Wing D, E, F at The Prestig
PRESTIGE MULUND REALTY PRIVATE LIMITED
Forest Hills Ph 1 at The Prestige City
PRESTIGE MULUND REALTY PRIVATE LIMITED
Kalpataru Elitus
Arimas Real Estate Private Limited
See every Mumbai Suburban project, with the district possession charts
Builder: ASHWAMEDH BUILDERS AND DEVELOPERS MUMBAI
ASHWAMEDH BUILDERS AND DEVELOPERS MUMBAI has 1 registration on MahaRERA, including ASHWA PLATINUM. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if ASHWA PLATINUM is delayed beyond 31 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ASHWA PLATINUM?
The registered promoter entity is ASHWAMEDH BUILDERS AND DEVELOPERS MUMBAI, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ASHWA PLATINUM?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against ASHWA PLATINUM?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for ASHWA PLATINUM?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ASHWA PLATINUM?
The professionals named in the filing: Architect: NILESH SAWANT; Engineer: AJAY MAHALE; Chartered Accountant: S C BHATE AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ASHWA PLATINUM?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback