ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / ARKADE PEARL 2

Registered Litigation declared Residential / Group Housing project

ARKADE PEARL 2

By ARKADE DEVELOPERS LIMITED

RG-MH-18316 · RERA P51800077017 · Last updated on MahaRERA portal: 20 May 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case

Clear

  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 10 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
6 of 11Construction stages donefurthest along: Installation of Lifts, 76%
19 of 32Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 55 documents Report an error

ARKADE PEARL 2 is a Residential / Group Housing project by ARKADE DEVELOPERS LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800077017 on 16 Jul 2024. Possession is promised by 31 Dec 2026. 13 of the 32 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.

At a glance

Project

  • NameARKADE PEARL 2
  • TypeResidential / Group Housing
  • Location
    • AT SHAHAJI RAJE ROAD
    • VILE PARLE (EAST)
    • Vileparle
    • Andheri
    • Mumbai Suburban
    • 400057
  • Pincode400057
  • RERA no.P51800077017
  • ReraGenie IDRG-MH-18316

Builder

  • NameARKADE DEVELOPERS LIMITED
  • Entity typeCompany
  • DirectorARPIT VIKRAM JAIN
  • Managing DirectorAMIT MANGILAL JAIN
  • Other registrations8 more →
  • Declared earlier projects19 →

Key dates

this monthRegisteredJul 2024PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on16 Jul 2024
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed55 files

Current status

41%13 of 32 units booked
95.1%Work done, per cost certificate

Figures as on 20 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WINGNA9032032

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 76%.

A WING: 65% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises38%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.76%

Progress on shared amenities15

As on 20 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes75%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes75%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes75%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes80%
Water conservation /Rain water harvestingYes75%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes85%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,153 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on2 Jul 2025
LandownerVillageDistrict
PRACHI CO-OPERATIVE HOUSING SOCIETY LIMITEDVileparleMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI2444.26
Proposed, not sanctioned2,444 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 54 AND 55 ,SARAF CHOUDHARY NAGAR , KANDIVALI THAKUR COMPLEX COMPLEX, MUMBAI - 400101
Estimated costRs 16.87 cr
Cost incurredRs 16.04 cr
Work done95.07%
BuildingWingEstimatedIncurred
A WINGNARs 14.16 crRs 14.09 cr
-NARs 2.71 crRs 1.95 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKalakruti Architects and Planners Kalakruti Architects and Planners
EngineerJignesh Mohan Patel
Chartered AccountantAMIT T JAIN AND CO
Chartered AccountantMittal & Associates
PartnerRole in project
ARKADE DEVELOPERS LIMITED-

Litigation declared1

CaseCourtStatus
SHORT CAUSE SUIT NO 2079 /2023COURT OF CITY CIVIL DINDOSHI GOREGAONOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Jun 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 May 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 May 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed55

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A Arkade Pearl 2 Mar 26.pdf20 May 2026
Withdrawal Update Form 1File: FORM-1-Pearl 2-Mar 26.pdf7 May 2026
Withdrawal Update Form 2File: Form 2 Pearl 2 mar 26.pdf7 May 2026
Withdrawal Update Form 3File: Form 3 Arkade Pearl 2 mar 26.pdf7 May 2026
Withdrawal Update Form 1File: Form 1 Pearl 2 Dec 25.pdf6 Feb 2026
Withdrawal Update Form 2File: Form 2 Pearl 2 Dec 25.pdf6 Feb 2026
Withdrawal Update Form 3File: Pearl 2 dec 25 (1)-compressed.pdf6 Feb 2026
Form 5 (FY 2024-2025)File: Form 5 Arkade Pearl 2 24-25.pdf17 Dec 2025
Withdrawal Update Form 1File: Form 1 Pearl 2 Sep 25.pdf29 Oct 2025
Withdrawal Update Form 2File: Arkade Pearl 2 Sept 25.pdf29 Oct 2025
Withdrawal Update Form 3File: Arkade Pearl 2 sep 25.pdf29 Oct 2025
Withdrawal Update Form 1File: Form 1 Pearl 2_Wing A.pdf5 Aug 2025
Withdrawal Update Form 2File: Arkade Pearl 2 Form 2 Jun 25.pdf5 Aug 2025
Withdrawal Update Form 3File: Arkade Pearl 2.pdf5 Aug 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Arkade Pearl 2 Mar 25_compressed.pdf24 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Arkade Pearl 2 Mar 25.pdf19 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold and unsold Pearl 2 mar 25.pdf11 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form_2A_Pearl A wing Mar 25.pdf11 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Pearl A wing Mar 25.pdf5 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Pearl2 dec 24_compressed.pdf29 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 1 Arkade Pearl 2 Dec 2024.pdf17 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Pearl 2 Dec 24.pdf14 Jan 2025
Disclosure of sold/ booked inventoryFile: Pearl 2 Inventory declaration dec 24.pdf14 Jan 2025
Disclosure of sold/ booked inventoryFile: Pearl 2 Sep 24.pdf7 Nov 2024
Declaration about Commencement CertificateFile: CC revalidation Pearl.pdf5 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Pearl 2 Form 3 S_compressed.pdf22 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Pearl 2 Sep 24.pdf22 Oct 2024
Declaration about Commencement CertificateFile: 2439592Amendletter_signed.pdf22 Oct 2024
Other - TechnicalFile: Corrigendum letter 418A TO 418D.pdf25 Jul 2024
Other - TechnicalFile: Annexure A pearl 2 R.PDF4 Jul 2024
Other - TechnicalFile: Declaration cum undertaking for CTS issue R1_11zon.pdf4 Jul 2024
Copy of the legal title reportFile: Pearl Title Certificate June 24.pdf21 Jun 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate Pearl 2.pdf21 Jun 2024
Declaration about Commencement CertificateFile: Format D - CC declaration.pdf21 Jun 2024
Proforma of Agreement for saleFile: Agreement for Sale.pdf21 Jun 2024
Deviation Report with respect to model copy of AgreementFile: Deviation for Agr - R.pdf21 Jun 2024
Other - LegalFile: INC-27_Certificate of Incorporation_AA3166257 new.pdf13 May 2024
Layout approvalFile: 1-4 - highlighted.pdf11 May 2024
Layout approvalFile: 9-10 highlighted.pdf11 May 2024
Building plan approvalFile: Amend Issue Letter (1).pdf11 May 2024
Copy of Layout Approval (in case of layout)File: 1-4 - highlighted.pdf11 May 2024
Copy of Layout Approval (in case of layout)File: 9-10 highlighted.pdf11 May 2024
Building Plan Approval / NA Order for plotted developmentFile: Amend Issue Letter (1).pdf11 May 2024
CERSAI detailsFile: Cersai Declaration Pearl 2 (1).pdf11 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 (11).pdf11 May 2024
Proforma of Allotment letterFile: Clean Allotment Letter - Pearl 2 (Wing A)- after making changes as per circular (1).pdf11 May 2024
Deviation Report with respect to Allotment letterFile: Arkade Developers Ltd Allotment letter-s.pdf11 May 2024
PAN CardFile: pan card.pdf10 May 2024
Details of encumbrances concerned to FinanceFile: legal encumbrance.pdf10 May 2024
Details of encumbrances concerned to FinanceFile: no financial encumbrance.pdf10 May 2024
Details of encumbrances concerned to LegalFile: legal encumbrance.pdf10 May 2024
Details of encumbrances concerned to LegalFile: no financial encumbrance.pdf10 May 2024
Declaration in FORM BFile: Form B pramoter signed (1).pdf10 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A DOI.pdf10 May 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A -seperate bank account.pdf10 May 2024

Promoter's earlier projects10

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

10 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Arkade SereneP51800029961Sunder Nagar Malad West, Mumbai Suburban-Jul 2021CompletedJun 2024Feb 2023
ARKADE EARTH-CARNATIONP51800014422Kanjurmarg East, Mumbai Suburban-Nov 2017CompletedDec 2023Apr 2021
ARKADE EARTH-ASPENP51800006579Kanjurmarg East, Mumbai Suburban-Aug 2017CompletedDec 2023Apr 2021
ARKADE EARTH- BLUEBELLP51800011586Kanjurmarg East, Mumbai Suburban-Aug 2017CompletedDec 2023Apr 2021
DarshanDarshan Vile Parle East Mumbai 5710-CompletedJun 2023Nov 2022
ARKADE EARTH-DAFFODILP51800004440Kanjurmarg East, Mumbai Suburban-Aug 2017CompletedDec 2022Feb 2020
ARKADE EARTH - HAZELP51800022666KANJURMARG EAST, Mumbai Suburban-Oct 2019CompletedDec 2022Apr 2022
ARKADE EARTH - GARDENIAP51800010074Kanjurmarg East, Mumbai Suburban-Aug 2017CompletedDec 2022Feb 2020
ARKADE EARTH - FERNP51800004750Kanjurmarg East, Mumbai Suburban-Aug 2017CompletedDec 2022Feb 2020
ARKADE EARTH - EBONYP51800008953Kanjurmarg East, Mumbai Suburban-Aug 2017CompletedDec 2022Feb 2020

How this compares with Mumbai Suburban

41%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ARKADE PEARL 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VILE PARLE (EAST)6,700+ in Mumbai Suburban

Builder: ARKADE DEVELOPERS LIMITED

ARKADE DEVELOPERS LIMITED has 9 registrations on MahaRERA, including ARKADE PEARL 1 and Arkade Eden. Its filings disclose 19 earlier MahaRERA projects: declares 19 of 19 past projects completed on time. Litigation is declared on 7 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if ARKADE PEARL 2 is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ARKADE PEARL 2?

The registered promoter entity is ARKADE DEVELOPERS LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ARKADE PEARL 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ARKADE PEARL 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ARKADE PEARL 2?

The professionals named in the filing: Architect: Kalakruti Architects and Planners Kalakruti Architects and Planners; Engineer: Jignesh Mohan Patel; Chartered Accountant: AMIT T JAIN AND CO; Chartered Accountant: Mittal & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ARKADE PEARL 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ARKADE PEARL 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ARKADE PEARL 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.