Home / Browse projects / ARIHANT HERITAGE - OLD LAXMI BUILDING
ARIHANT HERITAGE - OLD LAXMI BUILDING
RG-MH-62004 · RERA P51900015921 · Last updated on MahaRERA portal: 26 Mar 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 89 months
- 3 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ARIHANT HERITAGE - OLD LAXMI BUILDING is a Residential / Group Housing project by ARIHANT DEVLOPERS in PAREL, 400012, registered with MahaRERA as P51900015921 on 9 Apr 2018. Possession was promised by 25 Dec 2025 and is now 10 months past that date. The completion date has moved by 89 months from the original filing. 9 of the 9 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameARIHANT HERITAGE - OLD LAXMI BUILDING
- TypeResidential / Group Housing
- Location
- AAI MAI MERVANJI
- PAREL
- 400012
- Pincode400012
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900015921
- ReraGenie IDRG-MH-62004
Builder
- NameARIHANT DEVLOPERS
- Entity typePartnership
- PartnerJITENDERKUMAR MOHANLAL JAIN
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on9 Apr 2018
- Promised completion25 Dec 2025
- Revised completionRevised to 25 Dec 2025 (originally 31 Jul 2018)
- Buildings1 building record
- Documents filed49 files
Current status
Figures as on 26 Mar 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| ARIHANT HERITAGE- OLD LAXMI BUILDING | NA | 21 | 21 | 9 | 0 | 9 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 26 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.
ARIHANT HERITAGE- OLD LAXMI BUILDING: 78% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 26 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed12
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SACHIN V GAIKWAD |
| Architect | SACHIN WAIRKAR |
| Engineer | PRAKASH BAJAJ |
| Engineer | COMPUTER HELP |
| Chartered Accountant | MANOJ PAL |
| Chartered Accountant | DEEPAK PRAKASK GAGE |
| Partner | Role in project |
|---|---|
| ARIHANT DEVLOPERS | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterNEW CC IS OBTAINED AND 2 FLOOR IS INCREASED
Reason as filed by the promoterPROJECT HAS NOT RECEIVED THE COMPLETION CERTIFICATE FOR THE 7TH FLOOR AND ALSO THE MCGM HAS NOT GIVEN THE WATER CONNECTION PERMISSION
Reason as filed by the promoternew CC is applied and flat sale in process
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000196659 | Nandkumar S. Bhat | M/S Arihant Developers | 15/04/2021 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 3 Apr 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 3 Apr 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 3 Apr 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 4 May 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 24 Feb 2025
Documents filed49
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Declaration in FORM BFile: Form B Final.pdf | 26 Mar 2025 |
| Declaration in FORM BFile: bb.pdf | 18 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: File.PDF | 5 Mar 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Architect Certificate.pdf | 24 Feb 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Adobe Scan 24 Feb 2025 (1).pdf | 24 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf | 24 Feb 2025 |
| Declaration in FORM BFile: Adobe Scan 21-Feb-2025.pdf | 21 Feb 2025 |
| Declaration in FORM BFile: Form B_FINAL.pdf | 10 Feb 2025 |
| Certificates of CA (Form 3)File: Form 3 Final_compressed.pdf | 10 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Final.pdf | 10 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Qualtiy Final.pdf | 10 Feb 2025 |
| Declaration in FORM BFile: Form B.pdf | 17 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Information of sold-Booked Inventory.pdf | 17 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality Assurance Certificate Sandeep Rathod.pdf | 17 Jan 2025 |
| Declaration about Commencement CertificateFile: Commencement Declaration.pdf | 11 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate final.pdf | 11 Jun 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Final.pdf | 11 Jun 2023 |
| Certificates of CA (Form 3)File: Form 3 Arihant Final_compressed.pdf | 11 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Arihant 21-22 Final.pdf | 11 Jun 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: 2373907_FurtherCC_signed laxmi.pdf | 4 May 2023 |
| Declaration in FORM BFile: form B RERA.pdf | 4 May 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality assurance.pdf | 4 May 2023 |
| Disclosure of sold/ booked inventoryFile: sold and unsold inventory rera.pdf | 4 May 2023 |
| Certificates of CA (Form 5)File: Arihant Heritage - old Laxmi Building Form 5.pdf | 12 Mar 2019 |
| Layout approvalFile: planfinal.pdf | 3 Apr 2018 |
| Building plan approvalFile: iod1.pdf | 3 Apr 2018 |
| Building plan approvalFile: iod2.pdf | 3 Apr 2018 |
| Building plan approvalFile: iod 3.pdf | 3 Apr 2018 |
| Building plan approvalFile: iod 4.pdf | 3 Apr 2018 |
| Copy of the legal title reportFile: Title report.pdf | 3 Apr 2018 |
| Details of encumbrancesFile: Encumberance Certificate1.pdf | 3 Apr 2018 |
| Copy of Layout Approval (in case of layout)File: planfinal.pdf | 3 Apr 2018 |
| Building Plan Approval (IOD)File: iod1.pdf | 3 Apr 2018 |
| Building Plan Approval (IOD)File: iod2.pdf | 3 Apr 2018 |
| Building Plan Approval (IOD)File: iod 3.pdf | 3 Apr 2018 |
| Building Plan Approval (IOD)File: iod 4.pdf | 3 Apr 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 3 Apr 2018 |
| Declaration in FORM BFile: Form B.pdf | 3 Apr 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Artichet certificate.pdf | 3 Apr 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf | 3 Apr 2018 |
| Certificates of CA (Form 3)File: CA CERTIFICATE1.pdf | 3 Apr 2018 |
| Proforma of Allotment letterFile: sa1.pdf | 3 Apr 2018 |
| Proforma of Allotment letterFile: SA3.pdf | 3 Apr 2018 |
| Proforma of Allotment letterFile: sa2.pdf | 3 Apr 2018 |
| Proforma of Allotment letterFile: SA4.pdf | 3 Apr 2018 |
| Proforma of Allotment letterFile: SA5.pdf | 3 Apr 2018 |
| OtherFile: rd.pdf | 3 Apr 2018 |
| OtherFile: rd1.pdf | 3 Apr 2018 |
| OtherFile: dec.pdf | 3 Apr 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 49 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep ARIHANT HERITAGE - OLD LAXMI BUILDING on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near PAREL
Filed coordinates, straight-line distance. 57 registered projects within 2 km.
SATTVA SUMERA
ALPERTON DEVELOPERS AND CONTRACTORS PRIVAT
THE EDGE
TEJUKAYA CORP PRIVATE LIMITED
THE PINNACLE
RATNARAJ BLESSING MILESTONE LLP
Ruparel Millennia
Renuka Realtors
Ruparel Jewel
Renuka Realtors
Ruparel NOVA
SHREE SUKHAKARTA DEVELOPERS PVT.LTD.
Builder: ARIHANT DEVLOPERS
ARIHANT DEVLOPERS has 1 registration on MahaRERA, including ARIHANT HERITAGE - OLD LAXMI BUILDING. Its filings disclose no earlier MahaRERA projects. Read the full track record.
Frequently asked questions
What does it mean that ARIHANT HERITAGE - OLD LAXMI BUILDING shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if ARIHANT HERITAGE - OLD LAXMI BUILDING is delayed beyond 25 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ARIHANT HERITAGE - OLD LAXMI BUILDING?
The registered promoter entity is ARIHANT DEVLOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ARIHANT HERITAGE - OLD LAXMI BUILDING?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against ARIHANT HERITAGE - OLD LAXMI BUILDING?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for ARIHANT HERITAGE - OLD LAXMI BUILDING?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ARIHANT HERITAGE - OLD LAXMI BUILDING?
The professionals named in the filing: Architect: SACHIN V GAIKWAD; Architect: SACHIN WAIRKAR; Engineer: PRAKASH BAJAJ; Engineer: COMPUTER HELP; Chartered Accountant: MANOJ PAL; Chartered Accountant: DEEPAK PRAKASK GAGE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ARIHANT HERITAGE - OLD LAXMI BUILDING?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback