Home / Browse projects / Mumbai Suburban, Maharashtra / Anmol Fortune - III
Anmol Fortune - III
RG-MH-09468 · RERA P51800001912 · Last updated on MahaRERA portal: 27 Sep 2021
Source: official MahaRERA filing
Red flags
- 4 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Anmol Fortune - III is a Residential / Group Housing project by Wadhwa Realty Pvt Ltd. in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800001912 on 29 Jul 2017. The registration is recorded completed; possession was promised by 30 Dec 2022. 4 complaints are on record with the regulator.
At a glance
Project
- NameAnmol Fortune - III
- TypeResidential / Group Housing
- Location
- Borivali
- Mumbai Suburban
- 400062
- Pincode400062
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800001912
- ReraGenie IDRG-MH-09468
Builder
- NameWadhwa Realty Pvt Ltd.
- Entity typeCompany
- DirectorNavin Amarlal Makhija
- Other registrations1 more →
- Completed2 of 2
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on29 Jul 2017
- Promised completion30 Dec 2022
- Revised completionNone
- Buildings1 building record
- Documents filed59 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| E Wing | NA | 38 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 27 Sep 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 90%.
E Wing: 90% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities17
As on 27 Sep 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 90% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
| Society Office | Yes | 100% |
| Swimming pool | Yes | 100% |
Parking filed286
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Abhijit A Mehta |
| Engineer | S R Estimation |
| Chartered Accountant | Gmj & Co. |
| Partner | Role in project |
|---|---|
| Wadhwa Realty Pvt Ltd. | - |
Complaints filed with MahaRERA4
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000012339 | Vinay Bhat | Wadhwa Realty Ltd | 08/12/2017 |
| CC006000000057233 | Heramb Namshikar | Wadhwa Realty Pvt Ltd | 09/12/2018 |
| CC006000000078976 | Wadhwa Realty Pvt. Ltd | The Vice President MHADA | 24/04/2019 |
| CC006000000090108 | Heena Iqbal | M/S. Wadhwa Realty PVT. LTD. | 13/07/2019 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 17 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Nov 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Nov 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 17 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 25 Jun 2020
Documents filed59
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 WING E Sep2021.pdf | 27 Sep 2021 |
| Details of Restarting of Construction work post lockdownFile: Post-Covid-Anmol Fortune.pdf | 20 Jul 2020 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Final Wadhwa_OCC_signed.pdf | 25 Jun 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA CERTIFICATE-FORM 1 - 1_compressed.pdf | 22 Nov 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA CERTIFICATE-FORM 1 - 3_compressed.pdf | 22 Nov 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA CERTIFICATE-FORM 1 - 2_compressed.pdf | 22 Nov 2019 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Anmol Foutune III Signed.pdf | 11 Nov 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch certificate_compressed.pdf | 7 Nov 2019 |
| Certificates of CA (Form 3)File: CA Certificate Anmol Fortune E - June-19.pdf | 11 Sep 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate_E_Anmol Fortune_31-12-2018.pdf | 5 Sep 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate_E_Anmol Fortune_31-03-2019.pdf | 5 Sep 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate_E_Anmol Fortune_30-06-2019.pdf | 5 Sep 2019 |
| Certificates of CA (Form 3)File: CA Certificate Anmol Fortune E - march19.pdf | 5 Sep 2019 |
| Certificates of CA (Form 3)File: CA Certificate Anmol Fortune E 311218_compressed.pdf | 29 Aug 2019 |
| Certificates of CA (Form 3)File: Anmol Fortune-Tower E-30-6-18-ilovepdf-compressed.pdf | 4 Dec 2018 |
| Building plan approvalFile: 1st Floor E.pdf | 29 Nov 2018 |
| Building plan approvalFile: Basement.pdf | 29 Nov 2018 |
| Building plan approvalFile: Build up E.pdf | 29 Nov 2018 |
| Building plan approvalFile: Floor plan E.pdf | 29 Nov 2018 |
| Building plan approvalFile: Part basement E.pdf | 29 Nov 2018 |
| Building plan approvalFile: Section.pdf | 29 Nov 2018 |
| Building plan approvalFile: still E.pdf | 29 Nov 2018 |
| Building plan approvalFile: Typical floor plan.pdf | 29 Nov 2018 |
| Building plan approvalFile: fire check.pdf | 29 Nov 2018 |
| Layout approvalFile: plotplan.pdf | 29 Nov 2018 |
| Copy of Layout Approval (in case of layout)File: plotplan.pdf | 29 Nov 2018 |
| Building Plan Approval (IOD)File: 1st Floor E.pdf | 29 Nov 2018 |
| Building Plan Approval (IOD)File: Basement.pdf | 29 Nov 2018 |
| Building Plan Approval (IOD)File: Build up E.pdf | 29 Nov 2018 |
| Building Plan Approval (IOD)File: Floor plan E.pdf | 29 Nov 2018 |
| Building Plan Approval (IOD)File: Part basement E.pdf | 29 Nov 2018 |
| Building Plan Approval (IOD)File: Section.pdf | 29 Nov 2018 |
| Building Plan Approval (IOD)File: still E.pdf | 29 Nov 2018 |
| Building Plan Approval (IOD)File: Typical floor plan.pdf | 29 Nov 2018 |
| Building Plan Approval (IOD)File: fire check.pdf | 29 Nov 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Signed Engg Cert_E_Anmol Fortune_31-03-2018.pdf | 27 Nov 2018 |
| Certificates of CA (Form 3)File: Signed CA Cert_E_Anmol Fortune_31-03-2018-ilovepdf-compressed.pdf | 27 Nov 2018 |
| Certificates of CA (Form 5)File: Wadhwa Realty Anmol Fortune III.pdf | 30 Sep 2018 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Ltr-SocietyRegistration.pdf | 31 Mar 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Cert_E_Anmol Fortune_31-07-2017.pdf | 24 Oct 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Cert_E_Anmol Fortune_31-07-2017.pdf | 24 Oct 2017 |
| Certificates of CA (Form 3)File: CA Cert_E_Anmol Fortune_31-07-2017.pdf | 24 Oct 2017 |
| Declaration in FORM BFile: DEVELOPMENT AGREEMENT V1.pdf | 24 Jul 2017 |
| Declaration in FORM BFile: SupplementalAgr.pdf | 24 Jul 2017 |
| Declaration in FORM BFile: SupplementalAgr1V1.pdf | 24 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Tower E.pdf | 24 Jul 2017 |
| Proforma of Allotment letterFile: AgreementForSale-Building-E-RERA-Final.pdf | 24 Jul 2017 |
| OtherFile: AdditionalInformation-EWing.pdf | 24 Jul 2017 |
| Layout approvalFile: NoLayout1.pdf | 18 Jul 2017 |
| Details of encumbrancesFile: EncumbranceCertificate-E.pdf | 18 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: NoLayout1.pdf | 18 Jul 2017 |
| Declaration in FORM BFile: Form-B-EWing.pdf | 18 Jul 2017 |
| Building plan approvalFile: IOD.pdf | 17 Jul 2017 |
| PAN CardFile: Wadhwa Realty Pan card copy.pdf | 17 Jul 2017 |
| Copy of the legal title reportFile: TITLE CERTIFICATE FROM SHIRALKAR CO-updated (2013 Dec).pdf | 17 Jul 2017 |
| Building Plan Approval (IOD)File: IOD.pdf | 17 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 17 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate_E_Anmol Fortune_30-04-2017.pdf | 17 Jul 2017 |
| Certificates of CA (Form 3)File: CA Certificate_E_Anmol Fortune_30-04-2017.pdf | 17 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 59 filed documents as one ZIP, foldered, with a manifest
Keep Anmol Fortune - III on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Borivali6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 364 registered projects within 2 km.
NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY L
SHIVAM PARIVAR DEVELOPERS PVT LTD
GUNDECHA REXON SUITES PHASE 1
ANAYA INFRASTRUCTURE PVT LTD
PALAI TOWERS
N D DEVELOPERS
AGARWAL FLORENCE
PARAM ANAND BUILDERS LLP
KRISHNA KUNJ PHASE 1
PRINCE HOUSING AND HOSPITALITY PRIVATE LIM
NIRLON EMPLOYEES CHS LTD BUILDING NO. 10
Shivam Parivar Developers Private Limited
See every Mumbai Suburban project, with the district possession charts
Builder: Wadhwa Realty Pvt Ltd.
Wadhwa Realty Pvt Ltd. has 2 registrations on MahaRERA, including Anmol Fortune - II and Anmol Fortune - III. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if Anmol Fortune - III is delayed beyond 30 Dec 2022?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Anmol Fortune - III?
The registered promoter entity is Wadhwa Realty Pvt Ltd., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Anmol Fortune - III?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Anmol Fortune - III?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Anmol Fortune - III?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Anmol Fortune - III?
The professionals named in the filing: Architect: Abhijit A Mehta; Engineer: S R Estimation; Chartered Accountant: Gmj & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Anmol Fortune - III?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback