ANANTA

By K AJMERA DEVELOPERS

RG-MH-06897 · RERA P51800053780 · Last updated on MahaRERA portal: 6 May 2026

Source: official MahaRERA filing

Red flags

  • Possession 2 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Aug 2026Possession promised2 months past this date
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 80%
62 of 77Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 58 documents Report an error

ANANTA is a Others project by K AJMERA DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800053780 on 28 Nov 2023. Possession was promised by 31 Aug 2026 and is now 2 months past that date. The completion date has moved by 12 months from the original filing. 15 of the 77 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameANANTA
  • TypeOthers
  • Location
    • SITUATED ON PLOT NO. 14
    • VISHWAKARMA MARG
    • NAHUR MULUND (W)
    • Nahur
    • Kurla
    • Mumbai Suburban
    • 400080
  • Pincode400080
  • RERA no.P51800053780
  • ReraGenie IDRG-MH-06897

Builder

  • NameK AJMERA DEVELOPERS
  • Entity typePartnership
  • PartnersPUNEET HARIBHAI SHAH, KIRTI RASIKLAL AJMERA

Key dates

2 months past promisethis monthRegisteredNov 2023First promiseAug 2025Revised toAug 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on28 Nov 2023
  • Promised completion31 Aug 2026
  • Revised completionRevised to 31 Aug 2026 (originally 31 Aug 2025)
  • Buildings1 building record
  • Documents filed58 files

Current status

19%15 of 77 units booked
77.0%Work done, per cost certificate

Figures as on 6 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANANTANA212075277

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 80%.

ANANTA: 53% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 6 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes30%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed84

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots84
Closed/Covered84

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,583 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on18 Jul 2025
LandownerVillageDistrict
NAVYOG APARTMENTS CO-OPERATIVE HOUSING SOCIETY LTDMulundMumbai Suburban
Shree Prithvi Estates (I) Pvt Ltd-Mumbai City

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI5125.27
Proposed, not sanctioned5,069 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDADAR WEST
Estimated costRs 25.78 cr
Cost incurredRs 19.85 cr
Work done77.0%
BuildingWingEstimatedIncurred
ANANTANARs 25.78 crRs 19.85 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTANVI dedhia
EngineerVISHAL NIKAM
EngineerSVPATILAND ASSOCIATES
Chartered AccountantNEHALI AND CO
Chartered AccountantJIGAR ZAVERI
PartnerRole in project
K AJMERA DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA18072502103Aug 2025 → Aug 2026

Reason as filed by the promoterWe Would like to request you that the Project Estella which is located at Plot Bearing CTS no.551/51 of Village Nahur, at Vishwakarma Marg, Mulund West, Mumbai 400 080. having its Registration No P518000053780 was mentioned to be completed on 31 August 2025. Due to delay from contractor in completing work the project was not able to complete in time. We would like to request you to further grant us extension for 12 Months We request you kindly grant us the certificate at the earliest. Thanking You,

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12602370Suryanarayan Ramsunder SharmaK AJMERA DEVELOPERS22/04/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Jan 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Oct 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Oct 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed58

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: NAVYOG Form 1.pdf6 May 2026
Withdrawal Update Form 2File: Form ---2.pdf6 May 2026
Withdrawal Update Form 3File: CA Certificate (1).pdf6 May 2026
Withdrawal Update Form 1File: NAVYOG Form 1 Architect Certificate 08012026.pdf25 Feb 2026
Withdrawal Update Form 2File: Signed Form 2 Navyog 08012026.pdf25 Feb 2026
Withdrawal Update Form 3File: Signed CA Certificate- Ananta Navyog_Dec 25.pdf25 Feb 2026
Withdrawal Update Form 1File: NAVYOG Form 1 Architect Certificate 14102025.pdf13 Jan 2026
Withdrawal Update Form 2File: Form 2 Navyog 15102025.pdf13 Jan 2026
Withdrawal Update Form 3File: CA Certificate- Ananta Navyog_Sept25 Updated.pdf13 Jan 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf11 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf11 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Ananta 30 Sep 2024.pdf8 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Ananta 31 Dec 2024.pdf8 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Navyog_Architect Certificate.pdf21 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Navyog_Engineer Certificate.pdf21 Feb 2025
Building plan approvalFile: IOA.pdf9 Oct 2024
Layout approvalFile: Plans 1.pdf9 Oct 2024
Layout approvalFile: Plans 2.pdf9 Oct 2024
Layout approvalFile: Plans 1.pdf9 Oct 2024
Layout approvalFile: Plans 2.pdf9 Oct 2024
Building plan approvalFile: IOA.pdf9 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: IOA.pdf9 Oct 2024
Copy of Layout Approval (in case of layout)File: Plans 1.pdf9 Oct 2024
Copy of Layout Approval (in case of layout)File: Plans 2.pdf9 Oct 2024
Copy of Layout Approval (in case of layout)File: Plans 1.pdf9 Oct 2024
Copy of Layout Approval (in case of layout)File: Plans 2.pdf9 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: IOA.pdf9 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed CA Certificate- Ananta Navyog_june'24.pdf20 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Signed Form 1 Navyog Architect Certificate June 2024.pdf15 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Signed FORM - 2 Navyog Apartment June 2024.pdf15 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Signed Navyog Form -2A march 2024.pdf2 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf18 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf13 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf13 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: further CC.pdf9 Feb 2024
Copy of the legal title reportFile: Title Report RERA Navyog- 15012024.pdf22 Jan 2024
Proforma of Agreement for saleFile: Final AFS for Navyog-Ananta-15012024R.pdf22 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Signed Form 1 Ananta Architect Certificate 31 Dec 2023.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Signed Form 2 Ananta 31 December 2023.pdf20 Jan 2024
Proforma of Allotment letterFile: 1 Proforma of Allotment letter.pdf17 Nov 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Letter RERA 01112023.pdf1 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: output.pdf27 Oct 2023
Building plan approvalFile: IOD.pdf14 Oct 2023
Layout approvalFile: PLANS (17).pdf14 Oct 2023
PAN CardFile: PAN FIRM.pdf14 Oct 2023
Copy of the legal title reportFile: Title Report RERA Navyog 091123.pdf14 Oct 2023
Details of encumbrances concerned to FinanceFile: NO ENCUMBRANCE SELF DECLARATION (6).pdf14 Oct 2023
Details of encumbrances concerned to LegalFile: NO ENCUMBRANCE SELF DECLARATION (6).pdf14 Oct 2023
Copy of Layout Approval (in case of layout)File: PLANS (17).pdf14 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: IOD.pdf14 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: Navyog Plinth CC 05102023.pdf14 Oct 2023
Declaration about Commencement CertificateFile: CC COVERING LETTER.pdf14 Oct 2023
Declaration in FORM BFile: FORM B (11).pdf14 Oct 2023
CERSAI detailsFile: CERSAI DECLARATION (10).pdf14 Oct 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNEXURE A DOI (19).pdf14 Oct 2023
Proforma of Agreement for saleFile: Final AFS for Navyog-Ananta-09102023 (1).pdf14 Oct 2023
Deviation Report with respect to Allotment letterFile: deviation report allotment letter.pdf14 Oct 2023
Deviation Report with respect to model copy of AgreementFile: Deviation report for AFS.pdf14 Oct 2023

How this compares with Mumbai Suburban

19%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ANANTA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NAHUR MULUND (W)6,700+ in Mumbai Suburban

Builder: K AJMERA DEVELOPERS

K AJMERA DEVELOPERS has 1 registration on MahaRERA, including ANANTA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if ANANTA is delayed beyond 31 Aug 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ANANTA?

The registered promoter entity is K AJMERA DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ANANTA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ANANTA?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for ANANTA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ANANTA?

The professionals named in the filing: Architect: TANVI dedhia; Engineer: VISHAL NIKAM; Engineer: SVPATILAND ASSOCIATES; Chartered Accountant: NEHALI AND CO; Chartered Accountant: JIGAR ZAVERI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ANANTA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ANANTA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ANANTA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.