ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / Anandi Height

Registration lapsed No litigation declared Others project

Anandi Height

By Prathmesh Developers

RG-MH-28913 · RERA P51700027975 · Last updated on MahaRERA portal: 3 Oct 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 28 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jun 2024Possession promised28 months past this date
2 of 11Construction stages donefurthest along: Basement (if any), 95%
33 of 51Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 48 documents Report an error

Anandi Height is a Others project by Prathmesh Developers in Thane, Maharashtra, registered with MahaRERA as P51700027975 on 21 Jan 2021. Possession was promised by 29 Jun 2024 and is now 28 months past that date. The completion date has moved by 12 months from the original filing. 18 of the 51 units on this registration are recorded sold or booked, and 2 of 11 construction stages are filed complete.

At a glance

Project

  • NameAnandi Height
  • TypeOthers
  • Location
    • Navagaon
    • Subhash Road
    • nagaon
    • Kalyan
    • Thane
    • 421202
  • Pincode421202
  • RERA no.P51700027975
  • ReraGenie IDRG-MH-28913

Builder

  • NamePrathmesh Developers
  • Entity typePartnership
  • PartnersHarish Dungaram Ji Choudhary, Sanjesh Gopal Patkar
  • Other registrations5 more →
  • No longer live3 lapsed, de-registered or revoked

Key dates

28 months past promisethis monthRegisteredJan 2021First promiseJun 2023Revised toJun 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on21 Jan 2021
  • Promised completion29 Jun 2024
  • Revised completionRevised to 29 Jun 2024 (originally 30 Jun 2023)
  • Buildings1 building record
  • Documents filed48 files

Current status

35%18 of 51 units booked

Figures as on 3 Oct 2023, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Anandi HeightsNA9842951

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 Oct 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 95%.

Anandi Heights: 75% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)95%
Podiums (if any)0%
Plinth95%
Stilt Floor95%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Progress on shared amenities15

As on 3 Oct 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed15

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots15
Closed/Covered1
Open Space14

Land and ownership5

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area906 sq m
Land owned byThe promoter, with other names on the file
Named landowners5
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on10 Oct 2025
LandownerVillageDistrict
SHREE DEVELOPERSBadlapur (M Cl)Thane
BHAVIN PATELAmbarnath (R)Thane
MAHADEV PATELAmbarnath (R)Thane
NARAYAL PATILAmravati (M Corp.)Amravati
KANJIThane (M Corp.)Thane

Approvals and building plan

Sanctioning authorityKalyan-Dombivli Municipal Corporation
Permissible FSI1279.74
Proposed, not sanctioned1,280 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchOld DP Road Katrap Badlapur East

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSTHAPATYA NIRMAAN SHIRISH NACHANE
EngineerRAJESH THAKRE RAJESH THAKARE
Chartered AccountantNarendra Mangilal Barfa MANGILAL BARFA
Chartered AccountantKRISHNA PAL ASHOK SINGH
Chartered AccountantVIKRAM CHOUDHARY
PartnerRole in project
Prathmesh Developers-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700017295Jun 2023 → Jun 2024

Reason as filed by the promoterWe hereby submit that our above project is almost 95% complete, and only some interior finishing work is pending. We have already applied for a Part Occupation Certificate. we believe that the part O.C. may get delayed, so we need the project extension up to 29th June 2024.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Dec 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Aug 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Jan 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed48

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: Form B Declaration - new (1).pdf3 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance Certificate -new (1).pdf3 Oct 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Flat list New.pdf3 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: C A Letter - new.pdf3 Oct 2023
Declaration in FORM BFile: Form B Declaration Builders (1).pdf15 Sep 2023
Declaration in FORM BFile: Form B Declaration Landowner_compressed.pdf15 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Letter New Upload.pdf15 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Letter New Upload.pdf15 Sep 2023
Layout approvalFile: MYSCAN_20220816_0001 1.pdf4 Aug 2023
Layout approvalFile: MYSCAN_20220816_0002 2.pdf4 Aug 2023
Layout approvalFile: MYSCAN_20220816_0003 3.pdf4 Aug 2023
Copy of Layout Approval (in case of layout)File: MYSCAN_20220816_0001 1.pdf4 Aug 2023
Copy of Layout Approval (in case of layout)File: MYSCAN_20220816_0002 2.pdf4 Aug 2023
Copy of Layout Approval (in case of layout)File: MYSCAN_20220816_0003 3.pdf4 Aug 2023
Commencement Certificates / NA Order for plotted developmentFile: CC Revised Plan.pdf20 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate.pdf19 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Certificate.pdf19 Feb 2023
Layout approvalFile: MYSCAN_20220816_0001.pdf17 Feb 2023
Layout approvalFile: MYSCAN_20220816_0002.pdf17 Feb 2023
Layout approvalFile: MYSCAN_20220816_0003.pdf17 Feb 2023
Copy of Layout Approval (in case of layout)File: MYSCAN_20220816_0001.pdf17 Feb 2023
Copy of Layout Approval (in case of layout)File: MYSCAN_20220816_0002.pdf17 Feb 2023
Copy of Layout Approval (in case of layout)File: MYSCAN_20220816_0003.pdf17 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5.pdf17 Feb 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Seprate Bank.pdf17 Feb 2023
OtherFile: RPM_MCHI_517000_KD_646.pdf7 Jan 2021
Building plan approvalFile: 01.pdf1 Jan 2021
Building plan approvalFile: 02.pdf1 Jan 2021
Building plan approvalFile: 03.pdf1 Jan 2021
Building Plan Approval / NA Order for plotted developmentFile: 01.pdf1 Jan 2021
Building Plan Approval / NA Order for plotted developmentFile: 02.pdf1 Jan 2021
Building Plan Approval / NA Order for plotted developmentFile: 03.pdf1 Jan 2021
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf1 Jan 2021
Declaration in FORM BFile: Form B.pdf1 Jan 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech certificate.pdf1 Jan 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf1 Jan 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE_compressed (3).pdf1 Jan 2021
Proforma of Allotment letterFile: Allotment Letter.pdf1 Jan 2021
Layout approvalFile: 01.pdf31 Dec 2020
Layout approvalFile: 02.pdf31 Dec 2020
Layout approvalFile: 03.pdf31 Dec 2020
PAN CardFile: FIRM PAN.pdf31 Dec 2020
Copy of the legal title reportFile: Title Report.pdf31 Dec 2020
Details of encumbrancesFile: Declaration Regarding Encumbrances.pdf31 Dec 2020
Copy of Layout Approval (in case of layout)File: 01.pdf31 Dec 2020
Copy of Layout Approval (in case of layout)File: 02.pdf31 Dec 2020
Copy of Layout Approval (in case of layout)File: 03.pdf31 Dec 2020
Proforma of Allotment letterFile: AGG FOR SALE RERA.pdf31 Dec 2020

How this compares with Thane

35%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 12 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Anandi Height on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Subhash Road7,600+ in Thane

Builder: Prathmesh Developers

Prathmesh Developers has 6 registrations on MahaRERA, including PRATHMESH DREAMS and Prathmesh Heights. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that Anandi Height shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Anandi Height is delayed beyond 29 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Anandi Height?

The registered promoter entity is Prathmesh Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Anandi Height?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Anandi Height?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Anandi Height?

The professionals named in the filing: Architect: STHAPATYA NIRMAAN SHIRISH NACHANE; Engineer: RAJESH THAKRE RAJESH THAKARE; Chartered Accountant: Narendra Mangilal Barfa MANGILAL BARFA; Chartered Accountant: KRISHNA PAL ASHOK SINGH; Chartered Accountant: VIKRAM CHOUDHARY. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Anandi Height?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Anandi Height. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Anandi Height to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.