Home / Browse projects / Satara, Maharashtra / Anandgriha Phase III

De-registered No litigation declared Residential / Group Housing project

Anandgriha Phase III

By KACHHI PROPERTIES

RG-MH-20855 · RERA P52700007506 · Last updated on MahaRERA portal: 4 May 2025

Source: official MahaRERA filing

Red flags

  • De-registered
  • Possession 46 months past the filed date
  • Completion date moved by 36 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.
Dec 2022Possession promised46 months past this date
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 35%
0Complaints at MahaRERAon this registration
Jump to the 81 documents Report an error

Anandgriha Phase III is a Residential / Group Housing project by KACHHI PROPERTIES in Satara, Maharashtra, registered with MahaRERA as P52700007506 on 17 Aug 2017. Possession was promised by 30 Dec 2022 and is now 46 months past that date. The completion date has moved by 36 months from the original filing.

At a glance

Project

  • NameAnandgriha Phase III
  • TypeResidential / Group Housing
  • Location
    • Satara
    • 415002
  • Pincode415002
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52700007506
  • ReraGenie IDRG-MH-20855

Builder

  • NameKACHHI PROPERTIES
  • Entity typePartnership
  • PartnersSalim Gaffar Kachhi, Hamid Salim Kachhi, Majid Salim Kachhi
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

46 months past promisethis monthRegisteredAug 2017First promiseDec 2019Revised toDec 2022

Key facts

Registration and timeline

  • StatusDe-registered
  • Registered on17 Aug 2017
  • Promised completion30 Dec 2022
  • Revised completionRevised to 30 Dec 2022 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed81 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building CNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 35%.

Building C: 40% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure35%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks5%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities17

As on 4 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes70%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes50%
Street LightingYes0%
Community BuildingsYes70%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable
Compound WallYes100%
Entrance GateYes100%

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,693 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2924.82
Proposed, not sanctioned2,925 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPratapganj Peth,Satara-415002

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVikas Ghadge & Associates
EngineerAB Kulkarni & Associates
EngineerSandeep Dilip Salunkhe
Chartered AccountantRajeshwar Kasar & Associates
PartnerRole in project
KACHHI PROPERTIES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52700002124Dec 2019 → Jun 2022

Reason as filed by the promoterRespected Authority, The said project comprises of the larger project Anandgriha which also has registered Anadgriha Phas I and Anadgriha Phae II A& B Building. Out of which Phase I project is completed within time and compliance has been uploaded on maharera web. So also Phase II A & B Building is near completion. The Said project i.e Anandgriha Phase II- C Building although was registered with Maharera but no booking was ever taken in the said project. We has just started the Marketing of the said project and not even single booking was taken out of total 48 flats as priority was given to co

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed81

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 81 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: sept2022 QPR.PDF4 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: sept 2024 ending QPR.PDF4 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: june 2024 ending QPR.PDF4 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: march2024 ending QPR.PDF4 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: dec 2023 ending QPR.PDF4 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: sept 2023 ending QPR.PDF4 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: june 2023 ending QPR.PDF4 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: march 2023 ending QPR.PDF4 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: dec 2022 ending QPR.PDF4 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: JUNE2020 QPR.PDF4 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: jane 2022.PDF4 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: march 2022.PDF4 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: dec 2021.PDF4 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: sept 2021 Qpr.PDF4 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: june 2021 Qpr.PDF4 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: dec 2020 Qpr.PDF4 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SEPT 2020sept Qpr.PDF4 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: for sept 2020endingQPR.PDF17 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: for dec 24 ending QPR.PDF17 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: for sept 2024 ending QPR.PDF17 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: for june 2024 ending QPR.PDF17 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: for march 2024 ending QPR.PDF17 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: for dec 2023 ending QPR.PDF17 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: for sept 2023 ending QPR.PDF17 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: for june 2023 ending QPR.PDF17 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: for march2023 ending QPR.PDF17 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: for dec 2022 ending QPR.PDF17 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: for jane 2022 ending QPR.PDF17 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: for sept 2022 ending QPR.PDF17 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: for june 2020ending OPR.PDF17 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: for dec 2020endingQPR.PDF17 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: for March 2021 ending QPR.PDF17 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: for Jane 2021 ending QPR.PDF17 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: for sept 2021 ending QPR.PDF17 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: for dec 2021 ending QPR.PDF17 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: for March 2022 ending QPR.PDF17 Apr 2025
Certificates of CA (Form 3)File: ca QPR ending sept 2024.PDF17 Apr 2025
Certificates of CA (Form 3)File: ca QPR ending june 2024.PDF17 Apr 2025
Certificates of CA (Form 3)File: ca QPR ending march 2024.PDF17 Apr 2025
Certificates of CA (Form 3)File: ca QPR ending Dec 2023.PDF17 Apr 2025
Certificates of CA (Form 3)File: ca QPR ending sept 2023.PDF17 Apr 2025
Certificates of CA (Form 3)File: ca april to june 2023.PDF17 Apr 2025
Certificates of CA (Form 3)File: ca QPR March 2023.PDF17 Apr 2025
Certificates of CA (Form 3)File: ca QPRending dec 2022.PDF17 Apr 2025
Certificates of CA (Form 3)File: ca QPR sept 2022.PDF17 Apr 2025
Certificates of CA (Form 3)File: ca april to jan 22.PDF17 Apr 2025
Certificates of CA (Form 3)File: ca jane to march 22.PDF17 Apr 2025
Certificates of CA (Form 3)File: ca oct 21 to dec 2021.PDF17 Apr 2025
Certificates of CA (Form 3)File: ca jully to sept 2021.PDF17 Apr 2025
Certificates of CA (Form 3)File: ca april to jan 21.PDF17 Apr 2025
Certificates of CA (Form 3)File: ca jan to march 21.PDF17 Apr 2025
Certificates of CA (Form 3)File: ca for oct2020 to dec 2020.PDF17 Apr 2025
Certificates of CA (Form 3)File: ca jully to sept2020.PDF17 Apr 2025
Certificates of CA (Form 3)File: c a april to june 2020.PDF17 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Anand Griha Architiect Certificate Phase -III-1.pdf8 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate-Sandeep Salunkhe.pdf8 May 2024
Certificates of CA (Form 3)File: C A Certificate - Ananad Griha Phase - III -1.pdf8 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA Audit AG Phase-3 [21-22].pdf24 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Anandgroha Phase-III [Form-5] Audit- 2020-21.pdf22 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Anandgroha Phase-III [Form-5] Audit 2018-19.pdf11 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Anandgroha Phase-III [Form-5] Audit- 2019-20.pdf11 Aug 2021
Certificates of CA (Form 3)File: C A Certificate C Building.pdf7 Aug 2019
Certificates of CA (Form 5)File: Phase II- C.pdf15 Oct 2018
OtherFile: Anand Grih Phase II - C Building.pdf12 Oct 2018
Building plan approvalFile: IOD declaration.pdf30 Jul 2017
Layout approvalFile: Anandgriha Towers Plan sheet 3.pdf30 Jul 2017
Layout approvalFile: Anandgriha Towers Plan Sheet 1.pdf30 Jul 2017
Layout approvalFile: Anandgriha Phase I ( Sheet 1 ).pdf30 Jul 2017
PAN CardFile: PAN KP.pdf30 Jul 2017
Copy of the legal title reportFile: Title Search Report (Anandgriha Towers).PDF30 Jul 2017
Details of encumbrancesFile: Morgage Deed - 5731-2016 .pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: Anandgriha Towers Plan sheet 3.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: Anandgriha Towers Plan Sheet 1.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: Anandgriha Phase I ( Sheet 1 ).pdf30 Jul 2017
Building Plan Approval (IOD)File: IOD declaration.pdf30 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Building permission (Anandgriha Towers).PDF30 Jul 2017
Declaration in FORM BFile: Form B Affidavit AG Phase 2 C.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Phase 2 C Building.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Phase 2 C Building.pdf30 Jul 2017
Certificates of CA (Form 3)File: C A Certificate AG Phase 2 C Building.pdf30 Jul 2017

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
One EarthS NO 87-A-7 Saidapur Satara104CompletedJan 2016Late, Apr 2016
ShantiniketanCTS - 633 Mangalwar Peth Satara18CompletedJul 2015Late, Jul 2015

How this compares with Satara

16%of Satara projects moved their completion datethis one moved by 36 months
35%of Satara registrations have lapsed or been cancelledthis one is among them

Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.

Keep Anandgriha Phase III on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Satara1,100+ in Satara

2 kmAnandgriha Phase IIICompleted 33Lapsed / revoked 36Other 49Dot size: filed unitsN

Filed coordinates, straight-line distance. 118 registered projects within 2 km.

Builder: KACHHI PROPERTIES

KACHHI PROPERTIES has 3 registrations on MahaRERA, including Anandgriha- Phase I and Anandgriha Phase III. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Read the full track record. See more projects on the Satara district page.

Frequently asked questions

What does it mean that Anandgriha Phase III shows as de-registered on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Anandgriha Phase III is delayed beyond 30 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Anandgriha Phase III?

The registered promoter entity is KACHHI PROPERTIES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Anandgriha Phase III?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Anandgriha Phase III?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Anandgriha Phase III?

The professionals named in the filing: Architect: Vikas Ghadge & Associates; Engineer: AB Kulkarni & Associates; Engineer: Sandeep Dilip Salunkhe; Chartered Accountant: Rajeshwar Kasar & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Anandgriha Phase III?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Anandgriha Phase III. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Anandgriha Phase III to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.