Home / Browse projects / Aurangabad, Maharashtra / Amrut Sai Gold Star
Amrut Sai Gold Star
RG-MH-08499 · RERA P51500020039 · Last updated on MahaRERA portal: 25 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 25 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Amrut Sai Gold Star is a Residential / Group Housing project by AMRUT SAI GOLD STAR in Aurangabad, Maharashtra, registered with MahaRERA as P51500020039 on 19 Mar 2019. Possession is promised by 30 Apr 2027. The completion date has moved by 25 months from the original filing. 12 of the 156 units on this registration are recorded sold or booked, and 77 of 99 construction stages are filed complete.
At a glance
Project
- NameAmrut Sai Gold Star
- TypeResidential / Group Housing
- Location
- Golwadi Waluj Mahanagar-4
- Opp 30 Green
- Aurangabad (CB)
- Aurangabad
- 431005
- Pincode431005
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51500020039
- ReraGenie IDRG-MH-08499
Builder
- NameAMRUT SAI GOLD STAR
- Entity typeOthers
- GSTIN27AAIAA3715F1Z0
- Named personsMahesh Shankarlal Lila, Sulochana Rajkumar Lila
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on19 Mar 2019
- Promised completion30 Apr 2027
- Revised completionRevised to 30 Apr 2027 (originally 30 Mar 2025)
- Buildings9 building records
- Documents filed145 files
Current status
Figures as on 25 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing A-1 | NA | 5 | 5 | 16 | 0 | 16 |
| Wing A-2 | NA | 5 | 5 | 16 | 0 | 16 |
| Wing A-3 | NA | 5 | 5 | 16 | 0 | 16 |
| Wing A-4 | NA | 5 | 5 | 16 | 0 | 16 |
| Wing A-5 | NA | 5 | 5 | 16 | 0 | 16 |
| Wing B-1 | NA | 5 | 5 | 16 | 0 | 16 |
| Wing B-2 | NA | 4 | 4 | 16 | 0 | 16 |
| Wing A-6 | NA | 5 | 5 | 16 | 0 | 16 |
| Wing C-1 | NA | 8 | 8 | 28 | 0 | 28 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building9
As on 25 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
77 of 99 construction stages are filed complete across 9 buildings. The stage furthest along is Internal walls, at 40%.
Wing A-182%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Wing A-282%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Wing A-382%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Wing A-482%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Wing A-582%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Wing B-182%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Wing B-282%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Wing A-682%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Wing C-152%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 10% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 20% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 25 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Parking filed152
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Wing A-1 | 16 | 0 | 16 |
| Wing A-2 | 16 | 0 | 16 |
| Wing A-3 | 16 | 0 | 16 |
| Wing A-4 | 16 | 0 | 16 |
| Wing A-5 | 1 | 0 | 1 |
| Wing B-1 | 16 | 16 | 32 |
| Wing B-2 | 16 | 0 | 16 |
| Wing A-6 | 11 | 0 | 11 |
| Wing C-1 | 28 | 0 | 28 |
Land and ownership2
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Sulochana Rajkumar Lila | Aurangabad (M Corp.) | Aurangabad |
| Mahesh Kumar Shankarlal Lila | Aurangabad (M Corp.) | Aurangabad |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 6.77 cr | Rs 9.75 cr |
| Wing C-1 | NA | Rs 1.64 cr | Rs 2.36 cr |
| Wing A-6 | NA | Rs 1.21 cr | Rs 1.75 cr |
| Wing A-4 | NA | Rs 1.20 cr | Rs 1.73 cr |
| Wing A-5 | NA | Rs 1.20 cr | Rs 1.73 cr |
| Wing A-2 | NA | Rs 1.18 cr | Rs 1.69 cr |
| Wing A-1 | NA | Rs 1.15 cr | Rs 1.66 cr |
| Wing A-3 | NA | Rs 1.12 cr | Rs 1.61 cr |
| Wing B-1 | NA | Rs 73.43 lakh | Rs 1.06 cr |
| Wing B-2 | NA | Rs 72.14 lakh | Rs 1.04 cr |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Manggal Design Pramaod Vithoba Narale |
| Engineer | Core Consultants |
| Engineer | Prakash Uttamrao Vidhatge |
| Chartered Accountant | Nikhil N Loya |
| Chartered Accountant | SNGP & Company |
| Chartered Accountant | Sonawane Sahane & Associates |
| Chartered Accountant | Alkesh Rawka And Associates |
| Partner | Role in project |
|---|---|
| AMRUT SAI GOLD STAR | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe are requesting an extension for our project in MahaRERA due to the incorporation of two additional buildings, Wing A-6 and C-1, into the current development plan. The addition of these buildings requires extra time for planning, approvals, and construction, which is the main reason for requesting an extension to the project timeline.
Reason as filed by the promoterAdditional time is required for obtaining the Occupancy Certificate from the Municipal Authority, for which the application has already been duly submitted (inward). Further, time is also required for execution of agreements with the allottees/prospective purchasers and completion of related formalities. Hence, extension of the RERA registration is requested.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 13 Mar 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 13 Mar 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 23 Mar 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 20 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 12 Feb 2024
Documents filed145
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 145 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: Form 2A 24-25.pdf | 25 Jul 2026 |
| Form 5 (FY 2025-2026)File: Signed Form 5.pdf | 23 Jul 2026 |
| Withdrawal Update Form 1File: Form-1 ASGS-I Q-1.pdf | 20 Jul 2026 |
| Withdrawal Update Form 2File: Form-2 ASGS-I Q-1.pdf | 20 Jul 2026 |
| Withdrawal Update Form 3File: Form-3 ASGS-I Q-1.pdf | 20 Jul 2026 |
| Form 2A (FY 2024-2025)File: Form 2A 24-25.pdf | 20 Jul 2026 |
| Form 5 (FY 2024-2025)File: FORM 5 24-25_2.pdf | 20 Jul 2026 |
| Form 1File: Form-1 ASGS-I Q-4.pdf | 1 May 2026 |
| Form 2File: Form-2 ASGS-I Q-4.pdf | 1 May 2026 |
| Form 3File: Form-3 ASGS-I Q-4.pdf | 1 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold 2025-26 Q4.pdf | 1 May 2026 |
| Form 1File: Form-1 ASGS PH-I dt 2025-26 Q2.pdf | 19 Feb 2026 |
| Form 2File: Form-2 ASGS PH-I dt 2025-26 Q2.pdf | 19 Feb 2026 |
| Form 3File: Form 3 2025-26 Q2 Sign.pdf | 19 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold 2025-26 Q2.pdf | 19 Feb 2026 |
| Form 1File: Form-1 ASGS-I Q-3.pdf | 19 Feb 2026 |
| Form 2File: Form-2 ASGS-I Q-3.pdf | 19 Feb 2026 |
| Form 3File: Form-3 ASGS-I Q-3.pdf | 19 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold 2025-26 Q3.pdf | 19 Feb 2026 |
| Form 1File: Form 1-2023-24-Q3.pdf | 15 Aug 2025 |
| Form 2File: Form 2-2023-24-Q3.pdf | 15 Aug 2025 |
| Form 3File: Form 3-2023-24-Q3.pdf | 15 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold-2023-24-Q3.pdf | 15 Aug 2025 |
| Form 1File: Form 1-2024-25-Q2.pdf | 15 Aug 2025 |
| Form 2File: Form 2-2024-25-Q2.pdf | 15 Aug 2025 |
| Form 3File: Form 3-2024-25-Q2.pdf | 15 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold-2024-25-Q2.pdf | 15 Aug 2025 |
| Form 1File: Form 1-2024-25-Q4.pdf | 15 Aug 2025 |
| Form 2File: Form 2-2024-25-Q4.pdf | 15 Aug 2025 |
| Form 3File: Form 3-2024-25-Q4.pdf | 15 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold-2024-25-Q4.pdf | 15 Aug 2025 |
| Form 1File: Form-1 2025-26 Q1.pdf | 19 Jul 2025 |
| Form 2File: Form-2 2025-26 Q1.pdf | 19 Jul 2025 |
| Form 3File: ASGS PH-II Form 3.pdf | 19 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold 2025-26 Q1.pdf | 19 Jul 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2024-25 Q2.pdf | 13 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2022-23.pdf | 13 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2022-23 Q1.pdf | 12 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2022-23 Q2.pdf | 12 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2022-23 Q3.pdf | 12 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2022-23 Q4.pdf | 12 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2023-24 Q1.pdf | 12 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2023-24 Q2.pdf | 12 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2023-24 Q3.pdf | 12 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2023-24 Q4.pdf | 12 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2024-25 Q1.pdf | 12 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2024-25 Q3.pdf | 12 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2024-25 Q4.pdf | 12 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2 2023-24.pdf | 12 May 2025 |
| Certificates of CA (Form 3)File: Form 3 2024-25 Q4.pdf | 12 Apr 2025 |
| Declaration in FORM BFile: Form B.pdf | 5 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 2024-25 Q4_11zon.pdf | 5 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: PERT UPLOAD.pdf | 5 Apr 2025 |
| Certificates of CA (Form 3)File: Form 3 2024-25 Q4.pdf | 5 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2024-25 Q4.pdf | 5 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 2024-25 Q2.pdf | 5 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold 2024-25 Q4.pdf | 5 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold 2024-25 Q1.pdf | 5 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold 2024-25 Q2.pdf | 5 Apr 2025 |
| Certificates of CA (Form 3)File: ASGS CA Certificate PH-1_.pdf | 28 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ASGS PH-1 FORM 1.pdf | 27 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ASGS PH-1 FORM 2.pdf | 27 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: ASGS PH-1 SOLD UNSOLD.pdf | 27 Jan 2025 |
| Certificates of CA (Form 3)File: Form 3 2024-25 Q2_.pdf | 25 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 I upload.pdf | 23 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 I.pdf | 23 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold I Upload.pdf | 23 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold unsold inventory PH I 24-25 Q1.pdf | 18 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3 Phase I 24-25 Q1.pdf | 18 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 3 Phase I 24-25 Q1.pdf | 18 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: sold unsold PHASE-1 Q4.pdf | 15 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1.pdf | 13 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2.pdf | 13 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: sold unsold P2.pdf | 13 Apr 2024 |
| Building plan approvalFile: Details in building plan.pdf | 23 Mar 2024 |
| Building plan approvalFile: A6 Building plan upload.pdf | 23 Mar 2024 |
| Building plan approvalFile: C1 Building Plan upload.pdf | 23 Mar 2024 |
| Building plan approvalFile: Details in building plan.pdf | 23 Mar 2024 |
| Building Plan Approval (IOD)File: Details in building plan.pdf | 23 Mar 2024 |
| Building Plan Approval (IOD)File: A6 Building plan upload.pdf | 23 Mar 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Aurangabad
Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 145 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Amrut Sai Gold Star on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Opp 30 Green1,400+ in Aurangabad
Filed coordinates, straight-line distance. 54 registered projects within 2 km.
One World Phase I
SIMAR PRIDE VENTURES LLP
The Solitairee Phase I
Dizzi Land Farms Private Limited
Neo Orbit
Piyush Infratech Pvt.Ltd.
180 and 51 Greens
A.M.PATEL INFRA PVT LTD
MILLENNIUM BUSINESS CENTER
MILLENNIUMPRO NEST LLP
The Solitairee Phase II
Dizzi Land Farms Private Limited
See every Aurangabad project, with the district possession charts
Builder: AMRUT SAI GOLD STAR
AMRUT SAI GOLD STAR has 2 registrations on MahaRERA, including Amrut Sai Gold Star and Amrut Sai Gold Star Phase II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.
Frequently asked questions
What are my rights if Amrut Sai Gold Star is delayed beyond 30 Apr 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Amrut Sai Gold Star?
The registered promoter entity is AMRUT SAI GOLD STAR, an others as per the filing. Its GSTIN 27AAIAA3715F1Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Amrut Sai Gold Star?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Amrut Sai Gold Star?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Amrut Sai Gold Star?
The professionals named in the filing: Architect: Manggal Design Pramaod Vithoba Narale; Engineer: Core Consultants; Engineer: Prakash Uttamrao Vidhatge; Chartered Accountant: Nikhil N Loya; Chartered Accountant: SNGP & Company; Chartered Accountant: Sonawane Sahane & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Amrut Sai Gold Star?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.