Home / Browse projects / Aurangabad, Maharashtra / AMAZON PARK
AMAZON PARK
RG-MH-08121 · RERA P51500019184 · Last updated on MahaRERA portal: 12 Oct 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 7 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 61 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
AMAZON PARK is a Residential / Group Housing project by PRATHAMESH BUILDERS in Aurangabad, Maharashtra, registered with MahaRERA as P51500019184 on 9 Jan 2019. Possession was promised by 31 Mar 2026 and is now 7 months past that date. The completion date has moved by 61 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameAMAZON PARK
- TypeResidential / Group Housing
- Location
- PAITHAN ROAD
- KANCHANWADI
- Aurangabad (M Corp.)
- Aurangabad
- 431001
- Pincode431001
- RERA no.P51500019184
- ReraGenie IDRG-MH-08121
Builder
- NamePRATHAMESH BUILDERS
- Entity typePartnership
- PartnersPANKAJA DWARKADAS TILWANE, PARAG DWARKADAS TILWANE
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on9 Jan 2019
- Promised completion31 Mar 2026
- Revised completionRevised to 31 Mar 2026 (originally 28 Feb 2021)
- Buildings1 building record
- Documents filed54 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| ROW HOUSE | NA | 2 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 12 Oct 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
2 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 20%.
ROW HOUSE: 25% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 0% |
| Stilt Floor | 20% |
| Slabs of Super Structure | 20% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 20% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 12 Oct 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed5
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership3
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| DWARKADAS KISHANRAO TILWANE | Aurangabad (M Corp.) | Aurangabad |
| PARAG DWARKADAS TILWANE | Aurangabad (M Corp.) | Aurangabad |
| PUNKAJA DWARKADAS TILWANE | Aurangabad (M Corp.) | Aurangabad |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | GANESH MHAROLKAR |
| Partner | Role in project |
|---|---|
| PRATHAMESH BUILDERS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to personal issues and health issues we have not completed project and we also applied for new permission as the permission was expired now we received new final permission and there is no sale proceed in the said project. hence we request you to extend our project ill 31/03/2026.
Litigation declared1
| Case | Court | Status |
|---|---|---|
| 140/2016 | IN THE COURT OF HONBLE CIVIL JUDGE SENIOR DIVISION AT AURANGABAD | DISPOSED |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC003000000010062 | ANIL VISHWANATH SHARMA | PRATHMESH BUILDERS | 22/01/2020 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Aug 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Aug 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Aug 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 3 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed54
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf | 12 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A prathmesh Builders 2019-20.pdf | 22 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Prathmesh Builders 2020-21.pdf | 22 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Prathmesh Builders2021-22.pdf | 22 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A apr.pdf | 13 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A apr.pdf | 13 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A apr.pdf | 13 Apr 2023 |
| Certificates of CA (Form 3)File: Amazon Park Form - 3.pdf | 10 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A.pdf | 20 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD NEW.pdf | 20 Mar 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A.pdf | 16 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 2019-2020.pdf | 10 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2020-2021.pdf | 10 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2020-2021.pdf | 10 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2021-2022.pdf | 10 Mar 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Cert_RB_210638_381LOzGFSign.pdf | 3 Mar 2023 |
| Declaration about Commencement CertificateFile: Format D.pdf | 3 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: Discloser Of Sold.pdf | 3 Mar 2023 |
| Certificates of CA (Form 3)File: CA CERTFICT.PDF | 3 Jan 2019 |
| Proforma of Allotment letterFile: AMAZON PARK AGREEMENT TO SALE OF ROW HOUSE.pdf | 3 Jan 2019 |
| OtherFile: NA Orders Vaishali Mokate .PDF | 2 Jan 2019 |
| OtherFile: N A Order .PDF | 2 Jan 2019 |
| OtherFile: Declaration.PDF | 2 Jan 2019 |
| Building plan approvalFile: BUILDING PLAN NEW.pdf | 29 Aug 2018 |
| Layout approvalFile: LAYOUT.pdf | 29 Aug 2018 |
| PAN CardFile: PAN OF FIRM.pdf | 29 Aug 2018 |
| PAN CardFile: Pankaja Pan Card.PDF | 29 Aug 2018 |
| PAN CardFile: Parag Pan Card.PDF | 29 Aug 2018 |
| PAN CardFile: Dwarkadas Tilwane Pand Card.PDF | 29 Aug 2018 |
| Details of encumbrancesFile: Date of Release.PDF | 29 Aug 2018 |
| Copy of Layout Approval (in case of layout)File: LAYOUT.pdf | 29 Aug 2018 |
| Building Plan Approval (IOD)File: BUILDING PLAN NEW.pdf | 29 Aug 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate 2017-18.PDF | 29 Aug 2018 |
| OtherFile: Declaration new1.pdf | 29 Aug 2018 |
| OtherFile: Declaration 9638 NEW.pdf | 29 Aug 2018 |
| OtherFile: Correction To Delaration.PDF | 29 Aug 2018 |
| OtherFile: Revisesed Deed of Declarations NEW.pdf | 29 Aug 2018 |
| OtherFile: New Sat Bara 13-2-3.PDF | 29 Aug 2018 |
| OtherFile: New Sat Bara 13-2-2 .PDF | 29 Aug 2018 |
| OtherFile: partnership prathamesh.PDF | 29 Aug 2018 |
| OtherFile: partnership anand.PDF | 29 Aug 2018 |
| OtherFile: Sale Deed .PDF | 29 Aug 2018 |
| OtherFile: court plaint in splcs140 of 16.PDF | 29 Aug 2018 |
| OtherFile: compromise in court Splcs 140 of 16.PDF | 29 Aug 2018 |
| OtherFile: COURT decree Splcs 140 OF 16.PDF | 29 Aug 2018 |
| OtherFile: G P A Telwane Sir 2010.PDF | 29 Aug 2018 |
| OtherFile: G P A Telewane Sir 2017 new.pdf | 29 Aug 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.PDF | 28 Aug 2018 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Regestration Certificate .PDF | 28 Aug 2018 |
| Copy of the legal title reportFile: Searhch Reprod .PDF | 27 Aug 2018 |
| Details of encumbrancesFile: Non Encumbraance Certificate.PDF | 27 Aug 2018 |
| Details of encumbrancesFile: Deed Of Release.PDF | 27 Aug 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate .PDF | 27 Aug 2018 |
| Declaration in FORM BFile: Affidavit Cum Declarations .PDF | 25 Aug 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Aurangabad
Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- All 54 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep AMAZON PARK on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KANCHANWADI1,400+ in Aurangabad
Capital Trade Centre
KRK Landmark LLP
AQ TOWN
AQ INFRASTRUCTURE PRIVATE LIMITED
KALYANI SAI VISHWA
RAJASHREE UDYOG
AMRUT SAI PLAZA PH 2
Shree Amrut Sai Developer Pvt.Ltd
PRASSANA HIGH CLASS CITY PHASE - I
SHRI KRISHNA NAGAR SAHAKARI GRAH NIRMAN SA
SHRIRAM RESIDENCY
UNIQUE BUILDCON
See every Aurangabad project, with the district possession charts
Builder: PRATHAMESH BUILDERS
PRATHAMESH BUILDERS has 1 registration on MahaRERA, including AMAZON PARK. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.
Frequently asked questions
What does it mean that AMAZON PARK shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if AMAZON PARK is delayed beyond 31 Mar 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of AMAZON PARK?
The registered promoter entity is PRATHAMESH BUILDERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in AMAZON PARK?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against AMAZON PARK?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for AMAZON PARK?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at AMAZON PARK?
The professionals named in the filing: Architect: GANESH MHAROLKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in AMAZON PARK?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback