ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Aman

Registered No litigation declared Residential / Group Housing project

Aman

By AVALON RESIDENCY LLP

RG-MH-47709 · RERA P51800012980 · Last updated on MahaRERA portal: 21 Apr 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 81 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jan 2030Possession promisedmoved 81 months from the original
1 of 11Construction stages donefurthest along: Basement (if any), 90%
11 of 13Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 27 documents Report an error

Aman is a Residential / Group Housing project by AVALON RESIDENCY LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800012980 on 7 Sep 2017. Possession is promised by 28 Jan 2030. The completion date has moved by 81 months from the original filing. 2 of the 13 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.

At a glance

Project

  • NameAman
  • TypeResidential / Group Housing
  • Location
    • ALMAS APT
    • Borivali
    • Mumbai Suburban
    • 400062
  • Pincode400062
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800012980
  • ReraGenie IDRG-MH-47709

Builder

  • NameAVALON RESIDENCY LLP
  • Entity typeLimited Liability Partnership
  • LLPINACA-9262
  • PartnersZakaria Abdul Patel, SAYEED ABDUL PATEL, SADIQ ABDUL PATEL
  • Other registrations2 more →

Key dates

this monthRegisteredSep 2017First promiseApr 2023Revised toJan 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on7 Sep 2017
  • Promised completion28 Jan 2030
  • Revised completionRevised to 28 Jan 2030 (originally 30 Apr 2023)
  • Buildings1 building record
  • Documents filed27 files

Current status

15%2 of 13 units booked
11.4%Work done, per cost certificate

Figures as on 21 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Aman CHSNA151512113

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 21 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 90%.

Aman CHS: 17% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)90%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 21 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed66

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots66
Closed/Covered66

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area714 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on8 Aug 2025

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI530.33
Proposed, not sanctioned530 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJogeshwari West
Estimated costRs 18.93 cr
Cost incurredRs 2.16 cr
Work done11.4%
BuildingWingEstimatedIncurred
Aman CHSNARs 18.93 crRs 2.16 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectYMS Consultants Ltd
ArchitectManoj Dubal &amp Associates Licensed Surveyors
EngineerHiren M Tanna
EngineerZAKIR KHAN
Chartered AccountantNEHALI DOSHI
PartnerRole in project
AVALON RESIDENCY LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA26082502439Apr 2023 → Jan 2030

Reason as filed by the promoter1 At the outset we would like to invite your attention to the fact that the Project Aman which was started by M/s Patel Developers ("the erstwhile Developer") in the year 2017 and the Original Project Completion was 30th April, 2023 2 It is relevant to note that the Aman Co-operative Housing Society Ltd. alongwith its members ("the Landowner") and the allottees/purchasers to whom the erstwhile Developer had agreed to sell the flats in the then proposed building cancelled the Development Agreement dated 8th January, 2013 executed by and between them and the erstwhile Developer and have appointe

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 15 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Aug 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Aug 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 28 Jan 2030

Documents filed27

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf21 Apr 2026
Withdrawal Update Form 2File: form 2 (2).pdf21 Apr 2026
Withdrawal Update Form 3File: Signed CA.pdf21 Apr 2026
Withdrawal Update Form 1File: Form 1 (Architect Certificate).pdf19 Feb 2026
Withdrawal Update Form 2File: form 2 (engineer certificate).pdf19 Feb 2026
Withdrawal Update Form 3File: Signed CA Certificate balwa tower 4_ dec 25.pdf19 Feb 2026
Withdrawal Update Form 1File: form1 sept 25.pdf12 Nov 2025
Withdrawal Update Form 2File: form 2 (engineer certificate).pdf12 Nov 2025
Withdrawal Update Form 3File: Signed CA Certificate balwa tower 4.pdf12 Nov 2025
Withdrawal Update Form 1File: form 1.pdf8 Nov 2025
Withdrawal Update Form 2File: form 2.pdf8 Nov 2025
Withdrawal Update Form 3File: form 3.pdf8 Nov 2025
Layout approvalFile: IOD_Part2.pdf15 Aug 2017
Building plan approvalFile: IOD_Part1.pdf15 Aug 2017
Building plan approvalFile: IOD_Part2.pdf15 Aug 2017
PAN CardFile: PAN.pdf15 Aug 2017
Copy of the legal title reportFile: Title.pdf15 Aug 2017
Details of encumbrancesFile: Encumbrance.pdf15 Aug 2017
Copy of Layout Approval (in case of layout)File: IOD_Part2.pdf15 Aug 2017
Building Plan Approval (IOD)File: IOD_Part1.pdf15 Aug 2017
Building Plan Approval (IOD)File: IOD_Part2.pdf15 Aug 2017
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf15 Aug 2017
Declaration in FORM BFile: Form-B.pdf15 Aug 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 Arch.pdf15 Aug 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Engg.pdf15 Aug 2017
Certificates of CA (Form 3)File: Form-3 CA.pdf15 Aug 2017
Proforma of Allotment letterFile: Agreement of Sale.pdf15 Aug 2017

How this compares with Mumbai Suburban

15%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 81 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Aman on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Borivali6,700+ in Mumbai Suburban

2 kmAmanCompleted 137Lapsed / revoked 71Abeyance 1Other 135Dot size: filed unitsN

Filed coordinates, straight-line distance. 344 registered projects within 2 km.

Builder: AVALON RESIDENCY LLP

AVALON RESIDENCY LLP has 3 registrations on MahaRERA, including Aman and Avalon Residency. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Aman is delayed beyond 28 Jan 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Aman?

The registered promoter entity is AVALON RESIDENCY LLP, a limited liability partnership as per the filing. Its LLPIN ACA-9262 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Aman?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Aman?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Aman?

The professionals named in the filing: Architect: YMS Consultants Ltd; Architect: Manoj Dubal &amp Associates Licensed Surveyors; Engineer: Hiren M Tanna; Engineer: ZAKIR KHAN; Chartered Accountant: NEHALI DOSHI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Aman?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Aman. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Aman to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.