Home / Browse projects / Raigarh, Maharashtra / ALIYA PARK

Registered No litigation declared Others project

ALIYA PARK

By UNITY CONSTRUCTION

RG-MH-30344 · RERA P52000030922 · Last updated on MahaRERA portal: 3 May 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 39 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 39 months from the original
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 80%
38 of 64Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 71 documents Report an error

ALIYA PARK is a Others project by UNITY CONSTRUCTION in Raigarh, Maharashtra, registered with MahaRERA as P52000030922 on 29 Sep 2021. Possession is promised by 31 Mar 2027. The completion date has moved by 39 months from the original filing. 26 of the 64 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameALIYA PARK
  • TypeOthers
  • Location
    • SURVEY NO 79 PLOT NO 1
    • MAMDAPUR
    • Karjat
    • Raigarh
    • 410101
  • Pincode410101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000030922
  • ReraGenie IDRG-MH-30344

Builder

  • NameUNITY CONSTRUCTION
  • Entity typePartnership
  • PartnersMUDASSAR GULZAR PALTE, MOHAMMED AKRAM CHOUHAN, AMINBHAI KASAMBHAI MEMAN, ZEESHAN ASIF MUFTI, AEJAZ AHMED ANEES SAYED

Key dates

this monthRegisteredSep 2021First promiseDec 2023Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 Sep 2021
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 31 Dec 2023)
  • Buildings1 building record
  • Documents filed71 files

Current status

41%26 of 64 units booked
90.3%Work done, per cost certificate

Figures as on 3 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ALIYA PARK A B C WINGNA6458664

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 80%.

ALIYA PARK A B C WING: 68% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises38%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks62%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%

Progress on shared amenities15

As on 3 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes75%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes75%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes75%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed73

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots73
Closed/Covered53
Open Space20

Land and ownership6

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,400 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on4 Aug 2025
LandownerVillageDistrict
AZIZ YUNUS PALTEMamdapurRaigarh
SHABBIR YUNUS PALTEMamdapurRaigarh
ZAHIR YUNUS PALTEMamdapurRaigarh
RAUF YUNUS PLATEMamdapurRaigarh
BILKIS HAJIAMAD FALKEMamdapurRaigarh
NAZNEEN A GANI LAGADMamdapurRaigarh

Approvals and building plan

Sanctioning authorityRAIGAD ZILLA PARISHAD
Permissible FSI1679.64
Proposed, not sanctioned1,680 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNERAL KARJAT RAIGAD
Estimated costRs 4.51 cr
Cost incurredRs 4.07 cr
Work done90.28%
BuildingWingEstimatedIncurred
ALIYA PARK A B C WINGNARs 4.23 crRs 3.90 cr
-NARs 28.19 lakhRs 16.91 lakh

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVASTU RACHANA CONSULTANCY
EngineerATUL KUDTARKAR
Chartered AccountantNIRAJ JITENDRA OSWAL
PartnerRole in project
UNITY CONSTRUCTION-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000018604Dec 2023 → Dec 2024

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.

EXT52000025996Dec 2023 → Mar 2027

Reason as filed by the promoterI, Mr. Mudassar Gulzar Palte, hereby declare the following with respect to the project “Aliya Park” bearing registration number P52000030922 registered under MahaRERA The reasons for the delay in completion of the real estate project are, 1. Unavailability of funds due to Lack of enquiry and Bookings for the project. 2. Delay in disbursement of funds from already sold units 3. Escalation of labour and material costs We have attached PERT chart/Planning details describing how the balance project work shall be completed We hereby humbly request you to grant extension to the real estate project “

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Sep 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Jul 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jul 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Jul 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed71

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM1.pdf3 May 2026
Withdrawal Update Form 1File: FORM 1 Q4.pdf3 May 2026
Withdrawal Update Form 2File: FORM2.pdf3 May 2026
Withdrawal Update Form 2File: FORM 2 Q4.pdf3 May 2026
Withdrawal Update Form 3File: FORM 3 Q3.pdf3 May 2026
Withdrawal Update Form 3File: FORM 3 Q4 25-26.pdf3 May 2026
Withdrawal Update Form 1File: ACHITECT CERT Q2 25-26.pdf24 Dec 2025
Withdrawal Update Form 2File: ENGINEER CERT Q2 25-26.pdf24 Dec 2025
Withdrawal Update Form 3File: CA CERT FINAL Q2 25-26.pdf24 Dec 2025
Form 1File: FORM 1 MAR 25.pdf4 Aug 2025
Form 2File: FORM 2 MAR 25.pdf4 Aug 2025
Form 3File: ca_certificate Q4 2024-25.pdf4 Aug 2025
Disclosure of Sold and Booked InventoryFile: MAR 25 SOLD INVENTORY.pdf4 Aug 2025
Withdrawal Update Form 1File: FORM 1 JUNE 25.pdf4 Aug 2025
Withdrawal Update Form 2File: FORM 2 JUNE 25.pdf4 Aug 2025
Withdrawal Update Form 3File: Withdrawal Application Form3 (12).pdf4 Aug 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 December 2024.pdf14 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 2023-2024.pdf14 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca_certificate Q1 2024-25.pdf2 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca_certificate Q2 2024-25.pdf2 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca_certificate Q3 2024-25.pdf2 Jan 2025
Details of encumbrances concerned to FinanceFile: Encumbrance.pdf31 Dec 2024
Declaration in FORM BFile: FORM B ALIYA 310327.pdf31 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERT 23 07 2024.pdf31 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERT 23 10-2024.pdf31 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERT 31122024.pdf31 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER 31122024.pdf31 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER Unity Construction - Sep 24.pdf31 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER Unity Construction - June 24.pdf31 Dec 2024
Disclosure of sold/ booked inventoryFile: Circular 29.pdf31 Dec 2024
CERSAI detailsFile: CERSAI DECLARATION.pdf31 Dec 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: BANK ACOUNT.pdf31 Dec 2024
Details of encumbrances concerned to LegalFile: Encumbrance.pdf31 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: DIN AEJAZ SAYED.pdf31 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: DIN AMINBHAI MEMAN.pdf31 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: DIN M B CHAUHAN.pdf31 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: DIN MUDASAR PALTE.pdf31 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: DIN ZEESHAN MUFTI.pdf31 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: QUALITY CERT.pdf31 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERT FINAL.pdf20 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERT.pdf20 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERT FINAL.pdf20 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca_certificate correction.pdf20 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22.pdf8 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf8 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_11zon.pdf6 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sept 23_11zon.pdf6 Jan 2024
Disclosure of sold/ booked inventoryFile: Circular 29.pdf6 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sept 23_11zon.pdf6 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22.pdf6 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23.pdf6 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Aliya Park - September 2023.pdf5 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - Aliya Park - FY 2021-22.pdf5 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - Aliya Park - FY 2022-23.pdf5 Jan 2024
Declaration in FORM BFile: Form B.pdf2 Jan 2024
Copy of the legal title reportFile: LEGAL REPORT NEW FORMAT.pdf23 Sep 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca_certificate final.pdf17 Aug 2021
Declaration about Commencement CertificateFile: COMMENCEMENT DECLARATION.pdf10 Aug 2021
Building plan approvalFile: APPROVED PLAN_compressed.pdf25 Jul 2021
Layout approvalFile: LAY OUT_compressed.pdf25 Jul 2021
PAN CardFile: UNITY CONS PAN.pdf25 Jul 2021
Copy of the legal title reportFile: ALIYA SEARCH REPORT.pdf25 Jul 2021
Details of encumbrancesFile: aliya park ENCUMBRACES.pdf25 Jul 2021
Copy of Layout Approval (in case of layout)File: LAY OUT_compressed.pdf25 Jul 2021
Building Plan Approval / NA Order for plotted developmentFile: APPROVED PLAN_compressed.pdf25 Jul 2021
Commencement Certificates / NA Order for plotted developmentFile: UNITY CONS COMMENCEMENT.pdf25 Jul 2021
Declaration in FORM BFile: ALIYA PROMOTER FORM B.pdf25 Jul 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERT ALIYA.pdf25 Jul 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CER ALIYA.pdf25 Jul 2021
Proforma of Allotment letterFile: Blank Agreement for sale Alia Park.pdf25 Jul 2021
OtherFile: GST CERTIFICATE_UNITY CONSTRUCTION (1).pdf25 Jul 2021

How this compares with Raigarh

41%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 39 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ALIYA PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MAMDAPUR5,900+ in Raigarh

2 kmALIYA PARKCompleted 79Lapsed / revoked 46Other 52Dot size: filed unitsN

Filed coordinates, straight-line distance. 177 registered projects within 2 km.

Builder: UNITY CONSTRUCTION

UNITY CONSTRUCTION has 1 registration on MahaRERA, including ALIYA PARK. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if ALIYA PARK is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ALIYA PARK?

The registered promoter entity is UNITY CONSTRUCTION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ALIYA PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ALIYA PARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ALIYA PARK?

The professionals named in the filing: Architect: VASTU RACHANA CONSULTANCY; Engineer: ATUL KUDTARKAR; Chartered Accountant: NIRAJ JITENDRA OSWAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ALIYA PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ALIYA PARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ALIYA PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.