Home / Browse projects / Pune, Maharashtra / AKSHAY GALAXY BUILDING A AND D

Registered Litigation declared Mixed project

AKSHAY GALAXY BUILDING A AND D

By A. P. BHANDARI DEVELOPERS

RG-MH-05665 · RERA P52100066532 · Last updated on MahaRERA portal: 10 Jul 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 2 cases
  • Completion date moved by 36 months
  • 1 extension taken

Clear

  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2029Possession promisedmoved 36 months from the original
4 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 75%
144 of 157Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 105 documents Report an error

AKSHAY GALAXY BUILDING A AND D is a Mixed project by A. P. BHANDARI DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100066532 on 11 Jun 2024. Possession is promised by 31 Dec 2029. The completion date has moved by 36 months from the original filing. 13 of the 157 units on this registration are recorded sold or booked, and 4 of 22 construction stages are filed complete.

At a glance

Project

  • NameAKSHAY GALAXY BUILDING A AND D
  • TypeMixed
  • Location
    • PUNE BOPDEV GHAT ROAD
    • YEWALEWADI KONDHWA BK
    • YAWALEWADI
    • Haveli
    • Pune
    • 411048
  • Pincode411048
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100066532
  • ReraGenie IDRG-MH-05665

Builder

  • NameA. P. BHANDARI DEVELOPERS
  • Entity typePartnership
  • PartnersAKSHAY ASHOK BHANDARI, ASHOK PHULCHAND BHANDARI
  • Other registrations2 more →
  • Completed2 of 3
  • Declared earlier projects7 →

Key dates

this monthRegisteredJun 2024First promiseDec 2026Revised toDec 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Jun 2024
  • Promised completion31 Dec 2029
  • Revised completionRevised to 31 Dec 2029 (originally 31 Dec 2026)
  • Buildings2 building records
  • Documents filed105 files

Current status

8%13 of 157 units booked
57.8%Work done, per cost certificate

Figures as on 10 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING ANA17151106116
BUILDING DNA6404141

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 10 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 75%.

BUILDING A25%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure75%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING D25%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 10 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed342

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots342
Closed/Covered142
Open Space200
BuildingClosed/CoveredOpen SpaceTotal
BUILDING A58119177
BUILDING D8481165

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,535 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
Declared on23 May 2025
LandownerVillageDistrict
A P BHANDARI DEVELOPERSMarket YardPune
Dinesh NimbalkarYAWALEWADIPune
Rahul NimbalkarYAWALEWADIPune

Approvals and building plan

Sanctioning authorityPUNE MUNICIPAL CORPORATION
Permissible FSI12751.4
Proposed, not sanctioned12,751 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchICICI Bank Ltd., Plot No. 84, Lane No. 1, Market Yard, Pune, Maharashtra.411037
Estimated costRs 62.19 cr
Cost incurredRs 35.95 cr
Work done57.81%
BuildingWingEstimatedIncurred
-NARs 33.69 crRs 20.57 cr
BUILDING ANARs 24.25 crRs 13.34 cr
BUILDING DNARs 4.25 crRs 2.04 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRajendra Khire Khire
EngineerGA Bhilare Consultant Pvt Ltd
Chartered AccountantK G JHAMVAR AND CO
Chartered AccountantAkshay Doshi and Associates
Chartered AccountantRajanikant Birla
PartnerRole in project
A. P. BHANDARI DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA25062621526Dec 2026 → Dec 2029

Reason as filed by the promoter1) We would like to inform to this authority that, earlier RERA registered was done only for commercial floors of both Building A and D. After the revised sanction of additional 14 floor we have to revise the extension date which is 31ˢᵗ December 2029 as the earlier validity was calculated only as per Ground floor of commercial area. 2) We would like to inform to this authority that, we have updated all the project details time to time. There is delay caused by almost 6 months in the construction due to some paperwork related to the project such as revised commencement certificate and revised

Litigation declared2

CaseCourtStatus
1098/2016Pune Civil CourtOngoing
01/2018Pune District and Session CourtOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Apr 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Sep 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Jan 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Sep 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2029

Documents filed105

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 105 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Architect Certificate (As On 30-06-2026).pdf10 Jul 2026
Withdrawal Update Form 2File: Form 2 Structural Engineer Certificate (As On 30-06-2026).pdf10 Jul 2026
Withdrawal Update Form 3File: FORM 3 Building A and D (As On 30-06-2026).pdf10 Jul 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate (As On 31-03-2026).pdf24 Apr 2026
Withdrawal Update Form 2File: Form 2 Structural Engineer Certificate (As On 31-03-2026).pdf24 Apr 2026
Withdrawal Update Form 3File: FORM 3 building A and D (As On 31-03-2026).pdf24 Apr 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate (As On 30-09-2025).pdf20 Jan 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate (As On 31-12-2025).pdf20 Jan 2026
Withdrawal Update Form 2File: Form 2 Structural Engineer Certificate (As on 30-09-2025).pdf20 Jan 2026
Withdrawal Update Form 2File: Form 2 Structural Engineer Certificate (As on 31-12-2025).pdf20 Jan 2026
Withdrawal Update Form 3File: FORM 3 building A and D (Till 30-09-2025).pdf20 Jan 2026
Withdrawal Update Form 3File: FORM 3 building A and D (Till 31-12-2025).pdf20 Jan 2026
Building plan approvalFile: plan 08-11_compressed.pdf3 Jan 2026
Building plan approvalFile: plan 09-11_compressed.pdf3 Jan 2026
Building plan approvalFile: plan 10-11_compressed.pdf3 Jan 2026
Building plan approvalFile: plan 11-11_compressed.pdf3 Jan 2026
Form 5 (FY 2024-2025)File: Form 5 CA Annual Report (As on 31-03-2025).pdf10 Oct 2025
Layout approvalFile: Sanctioned Plan and Layout 01 of 11.pdf29 Sep 2025
Building plan approvalFile: plan 2_compressed.pdf29 Sep 2025
Building plan approvalFile: PLAN 3_compressed.pdf29 Sep 2025
Building plan approvalFile: PLAN 4_compressed.pdf29 Sep 2025
Building plan approvalFile: PLAN 5_compressed.pdf29 Sep 2025
Building plan approvalFile: PLAN 6_compressed.pdf29 Sep 2025
Building plan approvalFile: PLAN 7_compressed.pdf29 Sep 2025
Withdrawal Update Form 1File: Form 1 Architect Certificate As On 30 JUNE 2025).pdf19 Sep 2025
Withdrawal Update Form 2File: Form 2 Structural Engineer Certificate JUNE 2025.pdf19 Sep 2025
Withdrawal Update Form 3File: Form 3 JUNE 2025.pdf19 Sep 2025
Commencement certificateFile: COMMENCEMENT CERTIFICATE.pdf17 Sep 2025
Withdrawal Update Form 1File: Form 1 Architect Certificate As On 30 JUNE 2025).pdf17 Sep 2025
Withdrawal Update Form 2File: Form 2 Structural Engineer Certificate JUNE 2025.pdf17 Sep 2025
Withdrawal Update Form 3File: Form 3 JUNE 2025.pdf17 Sep 2025
Form 1File: Form 1 Architect Certificate (As on 30-06-2024).pdf26 Jun 2025
Form 2File: Form 2 Structural Engineer Certificate (As on 30-06-2024).pdf26 Jun 2025
Form 3File: Form 3 CA Certificate (As on 30-06-2024).pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: Form 3 CA Certificate (As on 30-06-2024).pdf26 Jun 2025
Form 1File: Form 1 - Architect Certificate as on 31-12-2024.pdf26 Jun 2025
Form 2File: Form 2 Structural Engineer Certificate (As on 31-12-2024).pdf26 Jun 2025
Form 3File: Form 3 CA Certificate as on 31-12-2024.pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: Form 3 CA Certificate as on 31-12-2024.pdf26 Jun 2025
Form 1File: Form 1 Architect Certificate (As On 31-03-2025).pdf26 Jun 2025
Form 2File: Form 2 Structural Engineer Certificate (As on 31-03-2025).pdf26 Jun 2025
Form 3File: FORM 3 building A and D Commercial (Till 31-03-2025).pdf26 Jun 2025
Disclosure of Sold and Booked InventoryFile: FORM 3 building A and D Commercial (Till 31-03-2025).pdf26 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate (As On 31-03-2025).pdf6 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 building A and D Commercial (Till 31-03-2025).pdf6 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Structural Engineer Certificate (As on 31-03-2025).pdf6 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Quality Assurance (As on 31-03-2025).pdf6 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certificate as on 31-12-2024.pdf13 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate as on 31-12-2024.pdf13 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Structural Engineer Certificate (As on 31-12-2024).pdf13 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 (As on 30-09-2024).pdf20 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 (As on 30-09-2024).pdf20 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 (As on 30-09-2024).pdf20 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate (As on 30-06-2024).pdf5 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Structural Engineer Certificate (As on 30-06-2024).pdf5 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Quality Assurance Certificate.pdf5 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Quality Assurance Certificate.pdf5 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Quality Assurance Certificate.pdf5 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Quality Assurance Certificate.pdf5 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Quality Assurance Certificate.pdf5 Aug 2024
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure of Secured or Unsecured Finance for the Project.pdf5 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate (As on 30-06-2024).pdf5 Aug 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B of Seperate Bank Account.pdf5 Aug 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A Declaration of Seperate Bank Account from Promoter.pdf5 Aug 2024
Other - LegalFile: POA.pdf5 Aug 2024
Declaration in FORM BFile: FORM B BUILDER DECLARATION.pdf3 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 AKSHAY GALAXY.pdf3 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: OTHER ORGANIZATIONAL DETAILS (From A P Bhandari Developers).pdf22 May 2024
Proforma of Agreement for saleFile: Agreement For Sale Proforma.pdf3 May 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report with respect to Model of Agreement For Sale.pdf3 May 2024
CERSAI detailsFile: Undertaking of NO CERSAI REPORT.pdf25 Apr 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration of Seperate Bank Account.pdf25 Apr 2024
Details of encumbrances concerned to FinanceFile: No Encumbrance Certiticate Finance.pdf23 Apr 2024
Details of encumbrances concerned to LegalFile: No Encumbrance Certiticate Finance.pdf23 Apr 2024
Layout approvalFile: Layout with Marking of Building A and D.pdf22 Apr 2024
Copy of Layout Approval (in case of layout)File: Layout with Marking of Building A and D.pdf22 Apr 2024
Proforma of Allotment letterFile: Allotment Letter Proforma.pdf21 Apr 2024
Deviation Report with respect to Allotment letterFile: Deviation Report with respect to Allotment Letter Proforma.pdf21 Apr 2024
Other - LegalFile: Sale Deed.pdf21 Apr 2024
Other - LegalFile: Development Agreement.pdf21 Apr 2024

Promoter's earlier projects7

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise5 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
AKSHAY GALAXY - BUILDING BP52100028684Yewalewadi, Pune74Mar 2021CompletedDec 2024Apr 2024
Akshay Galaxy Building CS NO 9-1b Yewalewadi pune86-CompletedDec 2021Mar 2021
Akshay GalaxyS no 9 1b Pune Saswad Road Yewalewadi Pune 41104886-CompletedDec 2020Late, Mar 2021
AKSHAY FLORATHITE NAGAR KHARADI PUNE 41101428-CompletedOct 2013Late, Jan 2014
AKSHAY VILLASKHARADI14-CompletedMay 2013Late, Jun 2013
AKSHAY TEJPARASHAR SOCIETY KHARADI PUNE 41101410-CompletedJun 2010Late, Sep 2010
AKSHAY GLORYNEAR BALAJI HOSPITAL KHARADI PUNE 41101418-CompletedAug 2007Late, Sep 2007

How this compares with Pune

8%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 36 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AKSHAY GALAXY BUILDING A AND D on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near YEWALEWADI KONDHWA BK13,700+ in Pune

2 kmAKSHAY GALAXY BUILDING ACompleted 50Lapsed / revoked 27Other 22Dot size: filed unitsN

Filed coordinates, straight-line distance. 99 registered projects within 2 km.

Builder: A. P. BHANDARI DEVELOPERS

A. P. BHANDARI DEVELOPERS has 3 registrations on MahaRERA, including AKSHAY GALAXY and AKSHAY GALAXY - BUILDING B. Its filings disclose 7 earlier MahaRERA projects: declares 2 of 7 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if AKSHAY GALAXY BUILDING A AND D is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AKSHAY GALAXY BUILDING A AND D?

The registered promoter entity is A. P. BHANDARI DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AKSHAY GALAXY BUILDING A AND D?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for AKSHAY GALAXY BUILDING A AND D?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AKSHAY GALAXY BUILDING A AND D?

The professionals named in the filing: Architect: Rajendra Khire Khire; Engineer: GA Bhilare Consultant Pvt Ltd; Chartered Accountant: K G JHAMVAR AND CO; Chartered Accountant: Akshay Doshi and Associates; Chartered Accountant: Rajanikant Birla. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AKSHAY GALAXY BUILDING A AND D?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AKSHAY GALAXY BUILDING A AND D. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AKSHAY GALAXY BUILDING A AND D to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.