ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Akashvedh Phase 2

Registered No litigation declared Residential / Group Housing project

Akashvedh Phase 2

By Raghvendra Buildcon

RG-MH-16229 · RERA P52100025282 · Last updated on MahaRERA portal: 19 Jun 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 36 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 36 months from the original
11 of 11Construction stages doneevery applicable stage filed complete
0 of 65Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 140 documents Report an error

Akashvedh Phase 2 is a Residential / Group Housing project by Raghvendra Buildcon in Pune, Maharashtra, registered with MahaRERA as P52100025282 on 1 Apr 2020. Possession is promised by 31 Dec 2026. The completion date has moved by 36 months from the original filing. 65 of the 65 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete.

At a glance

Project

  • NameAkashvedh Phase 2
  • TypeResidential / Group Housing
  • Location
    • Dehu- Alandi Road
    • Chikhali
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 411062
  • Pincode411062
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100025282
  • ReraGenie IDRG-MH-16229

Builder

  • NameRaghvendra Buildcon
  • Entity typePartnership
  • PartnersDamodar Vamanrao More, Devendra Annarao Patil
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredApr 2020First promiseDec 2023Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on1 Apr 2020
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed140 files

Current status

100%65 of 65 units booked
100.0%Work done, per cost certificate

Figures as on 19 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C WingNA131165065

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

C Wing: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 19 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed17

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots17
Closed/Covered1
Open Space16

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,600 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on10 Jun 2026
LandownerVillageDistrict
Yashwant Laxman AlhatPimpri Chinchawad (M Corp.)Pune
Jaywant Laxman AlhatPimpri Chinchawad (M Corp.)Pune
Lilabai Laxman AlhatPimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Sanctioning authoritypimpari chinchwad municipal corporation
Permissible FSI3232.59
Proposed, not sanctioned3,233 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchOmkar Plaza, Ground Floor, Plot Gp 77, G bLOCK, Thermax Chowk, Pune
Estimated costRs 8.45 cr
Cost incurredRs 8.45 cr
Work done100.0%
BuildingWingEstimatedIncurred
C WingNARs 7.50 crRs 7.50 cr
-NARs 95.00 lakhRs 95.00 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUday Kulkarni
EngineerSantosh Namdeo Bhosale
Chartered AccountantS Gautam & Asoociates LLP
Chartered Accountantsumeet kate
PartnerRole in project
Raghvendra Buildcon-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100025518Dec 2023 → Dec 2026

Reason as filed by the promoter1. Legitimate Reasons for Extension Sought: We are requesting an extension for the submission of the Completion Certificate due to unforeseen technical delays. Despite submitting our application to the Planning Authority on 28th June 2022, the Completion Certificate has not been issued yet due to procedural and technical issues beyond our control. 2. Justification for Extension Proposal: The delay in receiving the Completion Certificate is a result of technical challenges in the approval process. We have complied with all regulatory requirements and are working with the concerned authorities t

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Mar 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Mar 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Mar 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Mar 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 29 Mar 2025

Documents filed140

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 140 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: form 1 raghvendra_page-0001.pdf19 Jun 2026
Withdrawal Update Form 1File: form 1 raghvendra_page-0001_page-0001.pdf19 Jun 2026
Withdrawal Update Form 2File: form 2 raghvendra_page-0001_page-0001.pdf19 Jun 2026
Withdrawal Update Form 2File: form 2 raghvendra_page-0001_page-0001_page-0001.pdf19 Jun 2026
Withdrawal Update Form 3File: form 3 raghvendra_page-0001.pdf19 Jun 2026
Withdrawal Update Form 3File: form 3 raghvendra_page-0001_page-0001.pdf19 Jun 2026
Form 1File: FORM 1 (3).pdf5 May 2026
Form 2File: FORM2.pdf5 May 2026
Form 3File: FORM 3 (3).pdf5 May 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD UNIT_page-0001.pdf5 May 2026
Form 1File: FORM 1_page-0001.pdf9 Oct 2025
Form 2File: FORM2_page-0001.pdf9 Oct 2025
Form 3File: FORM 3_page-0001.pdf9 Oct 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD_page-0001.pdf9 Oct 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion certificate - Akashvedh C wing.pdf29 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31092024.pdf27 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31062024.pdf27 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31032024.pdf27 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30032024.pdf27 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30062024.pdf27 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30092024.pdf27 Dec 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: FORMAT A.pdf27 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 2020-21.pdf12 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 2021-22.pdf12 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 2022-23.pdf12 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 2023-24.pdf12 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RB_Akashvedh phase 2_Signed_Form 3_Q2.pdf9 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RB_Akashvedh phase 2_Signed_Form 3_Q2.pdf9 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RB_Akashvedh phase 2_Signed_Form 3_Q1.pdf9 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RB_Akashvedh phase 2_Signed_Form 4_Q.pdf9 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RB_Akashvedh phase 2_Signed_Form 3_Q3.pdf9 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RB_Akashvedh phase 2_Signed_Form 3_Q1.pdf9 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RB_Akashvedh phase 2_Signed_Form 3_Q4.pdf9 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RB_Akashvedh phase 2_Signed_Form 3_Q3.pdf9 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RB_Akashvedh phase 2_Signed_Form 3_Q1.pdf9 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RB_Akashvedh phase 2_Signed_Form 3_Q4.pdf9 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RB_Akashvedh phase 2_Signed_Form 3_Q2.pdf9 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RB_Akashvedh phase 2_Signed_Form 3_Q1.pdf9 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RB_Akashvedh phase 2_Signed_Form 3_Q4.pdf9 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RB_Akashvedh phase 2_Signed_Form 3_Q3.pdf9 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RB_Akashvedh phase 2_Signed_Form 3_Q2.pdf9 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RB_Akashvedh phase 2_Signed_Form 3_Q1.pdf9 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - 31092022.pdf28 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - 31122024.pdf28 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - 31122023.pdf28 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - 31122022.pdf28 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - 31122021.pdf28 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - 30092024.pdf28 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - 30092023.pdf28 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - 30062024.pdf28 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - 30032021.pdf28 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - 30032022.pdf28 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - 30032023.pdf28 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - 30032024.pdf28 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - 30032024.pdf28 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - 30062021.pdf28 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - 30062022.pdf28 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - 30062023.pdf28 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - 30062024.pdf28 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - 30092021.pdf28 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - 30-03-2021.pdf27 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - 30-03-2022.pdf27 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - 30-09-2022.pdf27 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - 30-12-2021.pdf27 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 -30-09-2024.pdf27 Nov 2024
Disclosure of sold/ booked inventoryFile: SALE FLAT 2024 -3.pdf27 Nov 2024
Disclosure of sold/ booked inventoryFile: SALE FLAT 2024 -2.pdf27 Nov 2024
Disclosure of sold/ booked inventoryFile: SALE FLAT 2024 -1.pdf27 Nov 2024
Disclosure of sold/ booked inventoryFile: SALE FALT 2023 -4.pdf27 Nov 2024
Disclosure of sold/ booked inventoryFile: SALE FALT 2023 -3.pdf27 Nov 2024
Disclosure of sold/ booked inventoryFile: SALE FALT 2023 -2.pdf27 Nov 2024
Disclosure of sold/ booked inventoryFile: SALE FALT 2023 -1.pdf27 Nov 2024
Disclosure of sold/ booked inventoryFile: SALE FLAT 2022 -4.pdf27 Nov 2024
Disclosure of sold/ booked inventoryFile: SALE FLAT 2022 -3.pdf27 Nov 2024
Disclosure of sold/ booked inventoryFile: SALE FLAT 2022 -1.pdf27 Nov 2024
Disclosure of sold/ booked inventoryFile: SOLD FLAT 2021 -4.pdf27 Nov 2024
Disclosure of sold/ booked inventoryFile: SOLD FLAT 2021 -3.pdf27 Nov 2024
Disclosure of sold/ booked inventoryFile: SOLD FLAT 2021 -2.pdf27 Nov 2024
Disclosure of sold/ booked inventoryFile: SOLD FLAT 2021 -1.pdf27 Nov 2024
Disclosure of sold/ booked inventoryFile: SALE FLAT 2022 -2.pdf27 Nov 2024

How this compares with Pune

100%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 36 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Akashvedh Phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chikhali13,700+ in Pune

2 kmAkashvedh Phase 2Completed 12Lapsed / revoked 4Other 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 19 registered projects within 2 km.

Builder: Raghvendra Buildcon

Raghvendra Buildcon has 2 registrations on MahaRERA, including Akashvedh Phase 1 and Akashvedh Phase 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Akashvedh Phase 2 is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Akashvedh Phase 2?

The registered promoter entity is Raghvendra Buildcon, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Akashvedh Phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Akashvedh Phase 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Akashvedh Phase 2?

The professionals named in the filing: Architect: Uday Kulkarni; Engineer: Santosh Namdeo Bhosale; Chartered Accountant: S Gautam & Asoociates LLP; Chartered Accountant: sumeet kate. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Akashvedh Phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Akashvedh Phase 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Akashvedh Phase 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.