Home / Browse projects / Mumbai Suburban, Maharashtra / AEROVISTA

Registration lapsed No litigation declared Others project

AEROVISTA

By Gagangiri Construction

RG-MH-97398 · RERA P51800012150 · Last updated on MahaRERA portal: 15 Mar 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 5 complaints at MahaRERA
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
7 of 11Construction stages doneacross 4 buildings; furthest along: Staircases, 95%
120 of 213Units unsoldnot recorded sold or booked
5Complaints at MahaRERAon this registration
Jump to the 119 documents Report an error

AEROVISTA is a Others project by Gagangiri Construction in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800012150 on 1 Sep 2017. Possession was promised by 28 Dec 2025 and is now 10 months past that date. The completion date has moved by 24 months from the original filing. 93 of the 213 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete. 5 complaints are on record with the regulator.

At a glance

Project

  • NameAEROVISTA
  • TypeOthers
  • Location
    • Sahar Road
    • Parsiwada
    • Andheri
    • Mumbai Suburban
    • 400069
  • Pincode400069
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800012150
  • ReraGenie IDRG-MH-97398

Builder

  • NameGagangiri Construction
  • Entity typePartnership
  • PartnersHarsh Rajendra Dewoolkar, Jitendra Govind Dewoolkar, Anita Jitendra Dewoolkar, Parth Jitendra Dewoolkar
  • Other registrations4 more →
  • Completed1 of 5
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

10 months past promisethis monthRegisteredSep 2017First promiseDec 2023Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on1 Sep 2017
  • Promised completion28 Dec 2025
  • Revised completionRevised to 28 Dec 2025 (originally 30 Dec 2023)
  • Buildings4 building records
  • Documents filed119 files

Current status

44%93 of 213 units booked

Figures as on 15 Mar 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Kul PalladioNA160000
Sahar Tower CHSLA161346046
Sahar Tower CHSLB161349049
Sahar Tower CHSLC161410810118

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 15 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete across 4 buildings. The stage furthest along is Staircases, at 95%.

Kul Palladio89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%
Sahar Tower CHSL · wing ANot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
Sahar Tower CHSL · wing BNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
Sahar Tower CHSL · wing CNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 15 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes85%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes0%
Street LightingYes50%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes80%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed121

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots121
Closed/Covered121

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,673 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on1 Aug 2025
LandownerVillageDistrict
THE SAHAR TOWER CO-OPERATIVE HOUSING SOCIETY LTDMumbai CityMumbai City
Gagangiri ConstructionGreater Mumbai (M Corp.) (Part) (802794)Mumbai Suburban

Approvals and building plan

Sanctioning authorityMHADA
Permissible FSI13983.2
Proposed, not sanctioned13,966 sq m
Buildings approved3
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVEERA DESAI ROAD, ANDHERI WEST, MUMBAI-400053

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectEllora Project Consultants Pvt Ltd
EngineerSihavat Consultancy Services
Chartered AccountantParesh Dalal
PartnerRole in project
Gagangiri Construction-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800017643Dec 2023 → Dec 2024

Reason as filed by the promoter1. The erstwhile developers ‘M/s Kumar Builders Mumbai Realty Pvt Ltd’ was not able to complete the project within time period. 2. The project has been taken over by us (M/s Gagangiri Construction) in the month of February 2023. Accordingly change of promoter has been approved on 07-06-2023 by RERA authorities. 3. We are now in the process of completing the balance work of the project. 4. As per the current stage of work, the project cannot be complete by 30 December 2023, hence we have requested for this extension till 29 December 2024.

EXT51800025865Dec 2023 → Dec 2025

Reason as filed by the promoter1. Project was takeover by us in Feb 2023, due to non-performance of erstwhile developer. 2. Thereafter, we have complete Rehab portion and handover possession by obtaining part OC. 3. Sale portion has also been completed 85% which including 100% RCC, Brickwork, Plastering, external painting and balance work to be completed in 6-8 months. 4. Since we took over the project in Feb 2023, we tried our best to meet the time line, however it is not possible to complete the project in 20 months (i.e. Upto Dec 2024). 5. Now, to complete the balance work of the building as well as site infrastructure 6

Complaints filed with MahaRERA5

Case no.ComplainantRespondentFiled
CC006000000000629Jeetendra PatelKumar Builders Mumbai Realty Pvt. Ltd.07/10/2017
CC006000000001063SUMEET SURESH MOREKUMAR BUILDERS MUMBAI REALTY PVT. LTD.04/10/2017
CC006000000000965BHUSHAN WAMAN DHAVALEKUMAR BUILDERS MUMBAI REALITY PVT LTD07/10/2017
CC006000000192812Sahil dalal, Ruchi Dalal and Mallika DalalKumar Urban Developers Private Limited03/03/2020
CC12400123Kumar Urban Development Pvt LtdGagangiri Construction16/09/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Jul 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Jul 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Jul 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed119

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 119 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Other - TechnicalFile: Part OC 19102023.pdf15 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Aerovista Form 1.pdf3 Jan 2025
Certificates of CA (Form 3)File: Form 3Aerovista signed.pdf3 Jan 2025
Certificates of CA (Form 3)File: Aerovista Form 3.pdf3 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Aerovista Form 2.pdf3 Jan 2025
OtherFile: Resolution of the Association of Allotees.pdf3 Jan 2025
OtherFile: Aerovista Bar Chart for Extention.pdf3 Jan 2025
Disclosure of sold/ booked inventoryFile: Aerovista Inventory.pdf3 Jan 2025
Declaration in FORM BFile: Form B Declaration.pdf30 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2022-23.pdf30 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Sahar.pdf30 Dec 2024
Commencement Certificates / NA Order for plotted developmentFile: CC renew 25102024.pdf28 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A RERA Sahar Tower 14102024.pdf14 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Aerovis form 1 Sep 2024.pdf7 Oct 2024
Certificates of CA (Form 3)File: Aerovista Form 3 sep 24.pdf7 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Aerovista Form 2 Sep 2024.pdf7 Oct 2024
Disclosure of sold/ booked inventoryFile: Aerovista inventory sep 24.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Aerovista Form 5.pdf7 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Aerovista Architect Certificate Form1.pdf8 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Aerovista Engineer certificate Form 2.pdf8 Jul 2024
Disclosure of sold/ booked inventoryFile: Aerovista Inventory.pdf8 Jul 2024
Certificates of CA (Form 3)File: Aerovista CA certificate Form 3.pdf8 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sahar Architect certificate_11zon.pdf6 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sahar Architect certificate.pdf6 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Adobe Scan 06 Apr 2024_11zon.pdf6 Apr 2024
Disclosure of sold/ booked inventoryFile: Aerovista inventory march 2024_11zon.pdf6 Apr 2024
Certificates of CA (Form 3)File: Aerovista FORM 3.pdf6 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arc certificate Aerovista_compressed.pdf13 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Aerovista Engineers certificate_compressed.pdf13 Jan 2024
Disclosure of sold/ booked inventoryFile: Aerovista Inventory_compressed.pdf13 Jan 2024
Certificates of CA (Form 3)File: Aerovista CA certificate_compressed.pdf13 Jan 2024
Commencement Certificates / NA Order for plotted developmentFile: Further CC 25102023.pdf27 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Aerovista Architect certificate Sep 23.pdf21 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Aerovista Engineer certificate Sep.pdf21 Oct 2023
Disclosure of sold/ booked inventoryFile: Aerovista Sep Inventory.pdf21 Oct 2023
Certificates of CA (Form 3)File: Aerovista Form 3 sep 2023_11zon.pdf18 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Aerovista Form 5.pdf26 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest.pdf9 Sep 2023
Details of encumbrances concerned to FinanceFile: non encumbrance financial 170823.pdf21 Aug 2023
Details of encumbrances concerned to LegalFile: non encumbrance financial 170823.pdf21 Aug 2023
Layout approvalFile: Sahar Tower Demarcation Plan (00000003) MHADA_11zon.pdf11 Jul 2023
Building plan approvalFile: Sahar Tower IOA-pages-1-3.pdf11 Jul 2023
Layout approvalFile: Sahar Tower IOA-pages-4 Plan No 1_11zon.pdf11 Jul 2023
Building plan approvalFile: Sahar Tower IOA-pages-4 Plan No 1_11zon.pdf11 Jul 2023
Building plan approvalFile: Sahar Tower IOA-pages-5 Plan No.pdf11 Jul 2023
Building plan approvalFile: Sahar Tower IOA-pages-6 plan.pdf11 Jul 2023
Building plan approvalFile: Sahar Tower IOA-pages-7 Plan 4.pdf11 Jul 2023
Building plan approvalFile: Sahar Tower IOA-pages-8 Plan No.pdf11 Jul 2023
Building plan approvalFile: Sahar Tower IOA-pages-9 Plan No.pdf11 Jul 2023
Building plan approvalFile: Sahar Tower IOA-pages-10 11zon.pdf11 Jul 2023
Building plan approvalFile: Sahar Tower IOA-pages-11 8_11zon.pdf11 Jul 2023
Building plan approvalFile: Sahar Tower IOA-pages-12 9_11zon.pdf11 Jul 2023
Building plan approvalFile: Sahar Tower IOA-pages-13 10_11zon.pdf11 Jul 2023
Building plan approvalFile: Sahar Tower IOA-pages-14 11_11zon.pdf11 Jul 2023
Layout approvalFile: Sahar Tower Demarcation Plan (00000003) MHADA_11zon.pdf11 Jul 2023
PAN CardFile: Gagangiri Construction PAN.pdf11 Jul 2023
Copy of the legal title reportFile: Sahar Tower Title Report.pdf11 Jul 2023
Details of encumbrances concerned to FinanceFile: Non Encumbrance.pdf11 Jul 2023
Details of encumbrances concerned to FinanceFile: Non Encumbrance.pdf11 Jul 2023
Details of encumbrances concerned to LegalFile: Non Encumbrance.pdf11 Jul 2023
Details of encumbrances concerned to LegalFile: Non Encumbrance.pdf11 Jul 2023
Copy of Layout Approval (in case of layout)File: Sahar Tower Demarcation Plan (00000003) MHADA_11zon.pdf11 Jul 2023
Copy of Layout Approval (in case of layout)File: Sahar Tower IOA-pages-4 Plan No 1_11zon.pdf11 Jul 2023
Copy of Layout Approval (in case of layout)File: Sahar Tower Demarcation Plan (00000003) MHADA_11zon.pdf11 Jul 2023
Building Plan Approval (IOD)File: Sahar Tower IOA-pages-1-3.pdf11 Jul 2023
Building Plan Approval (IOD)File: Sahar Tower IOA-pages-4 Plan No 1_11zon.pdf11 Jul 2023
Building Plan Approval (IOD)File: Sahar Tower IOA-pages-5 Plan No.pdf11 Jul 2023
Building Plan Approval (IOD)File: Sahar Tower IOA-pages-6 plan.pdf11 Jul 2023
Building Plan Approval (IOD)File: Sahar Tower IOA-pages-7 Plan 4.pdf11 Jul 2023
Building Plan Approval (IOD)File: Sahar Tower IOA-pages-8 Plan No.pdf11 Jul 2023
Building Plan Approval (IOD)File: Sahar Tower IOA-pages-9 Plan No.pdf11 Jul 2023
Building Plan Approval (IOD)File: Sahar Tower IOA-pages-10 11zon.pdf11 Jul 2023
Building Plan Approval (IOD)File: Sahar Tower IOA-pages-11 8_11zon.pdf11 Jul 2023
Building Plan Approval (IOD)File: Sahar Tower IOA-pages-12 9_11zon.pdf11 Jul 2023
Building Plan Approval (IOD)File: Sahar Tower IOA-pages-13 10_11zon.pdf11 Jul 2023
Building Plan Approval (IOD)File: Sahar Tower IOA-pages-14 11_11zon.pdf11 Jul 2023
Commencement Certificates / NA Order for plotted developmentFile: 8696_furthercc_signed 05072023.pdf11 Jul 2023
Declaration about Commencement CertificateFile: CC Declaration 060723.pdf11 Jul 2023
Declaration in FORM BFile: Declaration Form B_11zon.pdf11 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate June 2023_11zon.pdf11 Jul 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Gagan 138P51800033983KURLA EAST, Mumbai Suburban101Mar 2022OngoingDec 2025Not delivered

How this compares with Mumbai Suburban

44%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 24 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AEROVISTA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Parsiwada6,700+ in Mumbai Suburban

2 kmAEROVISTACompleted 75Lapsed / revoked 37Other 78Dot size: filed unitsN

Filed coordinates, straight-line distance. 190 registered projects within 2 km.

Builder: Gagangiri Construction

Gagangiri Construction has 5 registrations on MahaRERA, including AEROVISTA and Gagan 138. Its filings disclose 4 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that AEROVISTA shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if AEROVISTA is delayed beyond 28 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AEROVISTA?

The registered promoter entity is Gagangiri Construction, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AEROVISTA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against AEROVISTA?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for AEROVISTA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AEROVISTA?

The professionals named in the filing: Architect: Ellora Project Consultants Pvt Ltd; Engineer: Sihavat Consultancy Services; Chartered Accountant: Paresh Dalal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AEROVISTA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AEROVISTA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AEROVISTA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.