AEROVISTA
RG-MH-97398 · RERA P51800012150 · Last updated on MahaRERA portal: 15 Mar 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- 5 complaints at MahaRERA
- Completion date moved by 24 months
- 2 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
AEROVISTA is a Others project by Gagangiri Construction in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800012150 on 1 Sep 2017. Possession was promised by 28 Dec 2025 and is now 10 months past that date. The completion date has moved by 24 months from the original filing. 93 of the 213 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete. 5 complaints are on record with the regulator.
At a glance
Project
- NameAEROVISTA
- TypeOthers
- Location
- Sahar Road
- Parsiwada
- Andheri
- Mumbai Suburban
- 400069
- Pincode400069
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800012150
- ReraGenie IDRG-MH-97398
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on1 Sep 2017
- Promised completion28 Dec 2025
- Revised completionRevised to 28 Dec 2025 (originally 30 Dec 2023)
- Buildings4 building records
- Documents filed119 files
Current status
Figures as on 15 Mar 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Kul Palladio | NA | 16 | 0 | 0 | 0 | 0 |
| Sahar Tower CHSL | A | 16 | 13 | 46 | 0 | 46 |
| Sahar Tower CHSL | B | 16 | 13 | 49 | 0 | 49 |
| Sahar Tower CHSL | C | 16 | 14 | 108 | 10 | 118 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 15 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
7 of 11 construction stages are filed complete across 4 buildings. The stage furthest along is Staircases, at 95%.
Kul Palladio89%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 85% |
Sahar Tower CHSL · wing ANot stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Sahar Tower CHSL · wing BNot stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Sahar Tower CHSL · wing CNot stated
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities15
As on 15 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 80% |
| Water Supply | Yes | 85% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | Yes | 90% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 50% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 80% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 90% |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed121
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership2
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| THE SAHAR TOWER CO-OPERATIVE HOUSING SOCIETY LTD | Mumbai City | Mumbai City |
| Gagangiri Construction | Greater Mumbai (M Corp.) (Part) (802794) | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ellora Project Consultants Pvt Ltd |
| Engineer | Sihavat Consultancy Services |
| Chartered Accountant | Paresh Dalal |
| Partner | Role in project |
|---|---|
| Gagangiri Construction | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1. The erstwhile developers ‘M/s Kumar Builders Mumbai Realty Pvt Ltd’ was not able to complete the project within time period. 2. The project has been taken over by us (M/s Gagangiri Construction) in the month of February 2023. Accordingly change of promoter has been approved on 07-06-2023 by RERA authorities. 3. We are now in the process of completing the balance work of the project. 4. As per the current stage of work, the project cannot be complete by 30 December 2023, hence we have requested for this extension till 29 December 2024.
Reason as filed by the promoter1. Project was takeover by us in Feb 2023, due to non-performance of erstwhile developer. 2. Thereafter, we have complete Rehab portion and handover possession by obtaining part OC. 3. Sale portion has also been completed 85% which including 100% RCC, Brickwork, Plastering, external painting and balance work to be completed in 6-8 months. 4. Since we took over the project in Feb 2023, we tried our best to meet the time line, however it is not possible to complete the project in 20 months (i.e. Upto Dec 2024). 5. Now, to complete the balance work of the building as well as site infrastructure 6
Complaints filed with MahaRERA5
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000000629 | Jeetendra Patel | Kumar Builders Mumbai Realty Pvt. Ltd. | 07/10/2017 |
| CC006000000001063 | SUMEET SURESH MORE | KUMAR BUILDERS MUMBAI REALTY PVT. LTD. | 04/10/2017 |
| CC006000000000965 | BHUSHAN WAMAN DHAVALE | KUMAR BUILDERS MUMBAI REALITY PVT LTD | 07/10/2017 |
| CC006000000192812 | Sahil dalal, Ruchi Dalal and Mallika Dalal | Kumar Urban Developers Private Limited | 03/03/2020 |
| CC12400123 | Kumar Urban Development Pvt Ltd | Gagangiri Construction | 16/09/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 11 Jul 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 11 Jul 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 11 Jul 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed119
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 119 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Other - TechnicalFile: Part OC 19102023.pdf | 15 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Aerovista Form 1.pdf | 3 Jan 2025 |
| Certificates of CA (Form 3)File: Form 3Aerovista signed.pdf | 3 Jan 2025 |
| Certificates of CA (Form 3)File: Aerovista Form 3.pdf | 3 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Aerovista Form 2.pdf | 3 Jan 2025 |
| OtherFile: Resolution of the Association of Allotees.pdf | 3 Jan 2025 |
| OtherFile: Aerovista Bar Chart for Extention.pdf | 3 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Aerovista Inventory.pdf | 3 Jan 2025 |
| Declaration in FORM BFile: Form B Declaration.pdf | 30 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2022-23.pdf | 30 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Sahar.pdf | 30 Dec 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC renew 25102024.pdf | 28 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A RERA Sahar Tower 14102024.pdf | 14 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Aerovis form 1 Sep 2024.pdf | 7 Oct 2024 |
| Certificates of CA (Form 3)File: Aerovista Form 3 sep 24.pdf | 7 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Aerovista Form 2 Sep 2024.pdf | 7 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Aerovista inventory sep 24.pdf | 7 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Aerovista Form 5.pdf | 7 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Aerovista Architect Certificate Form1.pdf | 8 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Aerovista Engineer certificate Form 2.pdf | 8 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Aerovista Inventory.pdf | 8 Jul 2024 |
| Certificates of CA (Form 3)File: Aerovista CA certificate Form 3.pdf | 8 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sahar Architect certificate_11zon.pdf | 6 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Sahar Architect certificate.pdf | 6 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Adobe Scan 06 Apr 2024_11zon.pdf | 6 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Aerovista inventory march 2024_11zon.pdf | 6 Apr 2024 |
| Certificates of CA (Form 3)File: Aerovista FORM 3.pdf | 6 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arc certificate Aerovista_compressed.pdf | 13 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Aerovista Engineers certificate_compressed.pdf | 13 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Aerovista Inventory_compressed.pdf | 13 Jan 2024 |
| Certificates of CA (Form 3)File: Aerovista CA certificate_compressed.pdf | 13 Jan 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Further CC 25102023.pdf | 27 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Aerovista Architect certificate Sep 23.pdf | 21 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Aerovista Engineer certificate Sep.pdf | 21 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Aerovista Sep Inventory.pdf | 21 Oct 2023 |
| Certificates of CA (Form 3)File: Aerovista Form 3 sep 2023_11zon.pdf | 18 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Aerovista Form 5.pdf | 26 Sep 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest.pdf | 9 Sep 2023 |
| Details of encumbrances concerned to FinanceFile: non encumbrance financial 170823.pdf | 21 Aug 2023 |
| Details of encumbrances concerned to LegalFile: non encumbrance financial 170823.pdf | 21 Aug 2023 |
| Layout approvalFile: Sahar Tower Demarcation Plan (00000003) MHADA_11zon.pdf | 11 Jul 2023 |
| Building plan approvalFile: Sahar Tower IOA-pages-1-3.pdf | 11 Jul 2023 |
| Layout approvalFile: Sahar Tower IOA-pages-4 Plan No 1_11zon.pdf | 11 Jul 2023 |
| Building plan approvalFile: Sahar Tower IOA-pages-4 Plan No 1_11zon.pdf | 11 Jul 2023 |
| Building plan approvalFile: Sahar Tower IOA-pages-5 Plan No.pdf | 11 Jul 2023 |
| Building plan approvalFile: Sahar Tower IOA-pages-6 plan.pdf | 11 Jul 2023 |
| Building plan approvalFile: Sahar Tower IOA-pages-7 Plan 4.pdf | 11 Jul 2023 |
| Building plan approvalFile: Sahar Tower IOA-pages-8 Plan No.pdf | 11 Jul 2023 |
| Building plan approvalFile: Sahar Tower IOA-pages-9 Plan No.pdf | 11 Jul 2023 |
| Building plan approvalFile: Sahar Tower IOA-pages-10 11zon.pdf | 11 Jul 2023 |
| Building plan approvalFile: Sahar Tower IOA-pages-11 8_11zon.pdf | 11 Jul 2023 |
| Building plan approvalFile: Sahar Tower IOA-pages-12 9_11zon.pdf | 11 Jul 2023 |
| Building plan approvalFile: Sahar Tower IOA-pages-13 10_11zon.pdf | 11 Jul 2023 |
| Building plan approvalFile: Sahar Tower IOA-pages-14 11_11zon.pdf | 11 Jul 2023 |
| Layout approvalFile: Sahar Tower Demarcation Plan (00000003) MHADA_11zon.pdf | 11 Jul 2023 |
| PAN CardFile: Gagangiri Construction PAN.pdf | 11 Jul 2023 |
| Copy of the legal title reportFile: Sahar Tower Title Report.pdf | 11 Jul 2023 |
| Details of encumbrances concerned to FinanceFile: Non Encumbrance.pdf | 11 Jul 2023 |
| Details of encumbrances concerned to FinanceFile: Non Encumbrance.pdf | 11 Jul 2023 |
| Details of encumbrances concerned to LegalFile: Non Encumbrance.pdf | 11 Jul 2023 |
| Details of encumbrances concerned to LegalFile: Non Encumbrance.pdf | 11 Jul 2023 |
| Copy of Layout Approval (in case of layout)File: Sahar Tower Demarcation Plan (00000003) MHADA_11zon.pdf | 11 Jul 2023 |
| Copy of Layout Approval (in case of layout)File: Sahar Tower IOA-pages-4 Plan No 1_11zon.pdf | 11 Jul 2023 |
| Copy of Layout Approval (in case of layout)File: Sahar Tower Demarcation Plan (00000003) MHADA_11zon.pdf | 11 Jul 2023 |
| Building Plan Approval (IOD)File: Sahar Tower IOA-pages-1-3.pdf | 11 Jul 2023 |
| Building Plan Approval (IOD)File: Sahar Tower IOA-pages-4 Plan No 1_11zon.pdf | 11 Jul 2023 |
| Building Plan Approval (IOD)File: Sahar Tower IOA-pages-5 Plan No.pdf | 11 Jul 2023 |
| Building Plan Approval (IOD)File: Sahar Tower IOA-pages-6 plan.pdf | 11 Jul 2023 |
| Building Plan Approval (IOD)File: Sahar Tower IOA-pages-7 Plan 4.pdf | 11 Jul 2023 |
| Building Plan Approval (IOD)File: Sahar Tower IOA-pages-8 Plan No.pdf | 11 Jul 2023 |
| Building Plan Approval (IOD)File: Sahar Tower IOA-pages-9 Plan No.pdf | 11 Jul 2023 |
| Building Plan Approval (IOD)File: Sahar Tower IOA-pages-10 11zon.pdf | 11 Jul 2023 |
| Building Plan Approval (IOD)File: Sahar Tower IOA-pages-11 8_11zon.pdf | 11 Jul 2023 |
| Building Plan Approval (IOD)File: Sahar Tower IOA-pages-12 9_11zon.pdf | 11 Jul 2023 |
| Building Plan Approval (IOD)File: Sahar Tower IOA-pages-13 10_11zon.pdf | 11 Jul 2023 |
| Building Plan Approval (IOD)File: Sahar Tower IOA-pages-14 11_11zon.pdf | 11 Jul 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: 8696_furthercc_signed 05072023.pdf | 11 Jul 2023 |
| Declaration about Commencement CertificateFile: CC Declaration 060723.pdf | 11 Jul 2023 |
| Declaration in FORM BFile: Declaration Form B_11zon.pdf | 11 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate June 2023_11zon.pdf | 11 Jul 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Gagan 138P51800033983 | KURLA EAST, Mumbai Suburban | 101 | Mar 2022 | Ongoing | Dec 2025 | Not delivered |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 119 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep AEROVISTA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Parsiwada6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 190 registered projects within 2 km.
Nityanand Nagar Vibhag IV Cooperative Housing
BAJAJ INTERNATIONAL REALTY PRIVATE LIMITED
FORTUNE ELITE
SAFFRON SPACES LIMITED
NICCO RESIDENCY
NEELKAMAL REALTY & CONSTRUCTION LLP
Parleshwar Aangan
Panom Developers LLP
ATHARV AARADHYAM
Atharv Infra LLP
Krishna Milan Heights
Milan Interbuilt Private Limited
See every Mumbai Suburban project, with the district possession charts
Builder: Gagangiri Construction
Gagangiri Construction has 5 registrations on MahaRERA, including AEROVISTA and Gagan 138. Its filings disclose 4 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that AEROVISTA shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if AEROVISTA is delayed beyond 28 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of AEROVISTA?
The registered promoter entity is Gagangiri Construction, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in AEROVISTA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against AEROVISTA?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for AEROVISTA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at AEROVISTA?
The professionals named in the filing: Architect: Ellora Project Consultants Pvt Ltd; Engineer: Sihavat Consultancy Services; Chartered Accountant: Paresh Dalal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in AEROVISTA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback