Home / Browse projects / Nashik, Maharashtra / Aditi Apartment

Registration lapsed No litigation declared Residential / Group Housing project

Aditi Apartment

By Minaxi Chaitanya Sompura

RG-MH-14989 · RERA P51600034046 · Last updated on MahaRERA portal: 6 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 27 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 2 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Jul 2024Possession promised27 months past this date
3 of 11Construction stages donefurthest along: Staircases, 60%
0Complaints at MahaRERAon this registration
Jump to the 38 documents Report an error

Aditi Apartment is a Residential / Group Housing project by Minaxi Chaitanya Sompura in Nashik, Maharashtra, registered with MahaRERA as P51600034046 on 17 Mar 2022. Possession was promised by 6 Jul 2024 and is now 27 months past that date.

At a glance

Project

  • NameAditi Apartment
  • TypeResidential / Group Housing
  • Location
    • Bendkule Nagar
    • Anandwalli Shiwar
    • Nashik
    • 422005
  • Pincode422005
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600034046
  • ReraGenie IDRG-MH-14989

Builder

  • NameMinaxi Chaitanya Sompura
  • Entity typeIndividual
  • Declared earlier projects2 →

Key dates

27 months past promisethis monthRegisteredMar 2022PromisedJul 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on17 Mar 2022
  • Promised completion6 Jul 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed38 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Aditi ApartmentNA00000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 60%.

Aditi Apartment: 41% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 6 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area494 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1562.28
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchThatte Nagar, College Road Nashik

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMINAXI CHAITANYA SOMPURA
EngineerMayuresh Construction
Chartered AccountantPatil Hiran Jajoo
PartnerRole in project
Minaxi Chaitanya Sompura-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Mar 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Mar 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed38

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Jan 25.pdf6 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Signed Q4 2324compressed.pdf31 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Signed 24-25 Q1_compressed.pdf31 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 Signed Q2 24-25_compressed.pdf31 Jan 2025
Declaration in FORM BFile: form b.pdf3 Aug 2024
Disclosure of sold/ booked inventoryFile: sold unsold.pdf3 Aug 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Default Folder_20240408.pdf10 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q1.pdf20 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q3.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q1 23-24 Legacy Properties.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q2 23-24 Legacy Properties final.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q3 23-24 Legacy properties final.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Mar 23_compressed.pdf29 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: legacy property_Form 2A.pdf22 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Legacy Properties_comp.pdf21 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Legacy Properties_comp.pdf21 Feb 2023
Details of encumbrances concerned to FinanceFile: Encumberance.pdf16 Feb 2023
Details of encumbrances concerned to LegalFile: Encumberance.pdf16 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf16 Feb 2023
Disclosure of sold/ booked inventoryFile: FY 20-21.pdf16 Feb 2023
Disclosure of sold/ booked inventoryFile: 03 Dec 22 Qtr end sold-unsold.pdf16 Feb 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank details for Rera.pdf16 Feb 2023
Copy of the legal title reportFile: Tittle Report(rera).pdf11 Mar 2022
Details of encumbrancesFile: Declaration for Encumbrances.pdf10 Mar 2022
Building plan approvalFile: BUILDING PLAN.pdf9 Mar 2022
Layout approvalFile: Layout 2 Aditi Appt_compressed.pdf9 Mar 2022
Copy of Layout Approval (in case of layout)File: Layout 2 Aditi Appt_compressed.pdf9 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: BUILDING PLAN.pdf9 Mar 2022
Declaration about Commencement CertificateFile: Declaration of commencement (Scan).pdf4 Mar 2022
CERSAI detailsFile: CERSAI_Search_Report_200231574102_For_Asset_Based_Search_04_03_2022_11_19_25_126.pdf4 Mar 2022
Proforma of Allotment letterFile: Allotment Letter 01 (Scan).pdf4 Mar 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement certificate.pdf13 Feb 2022
Declaration in FORM BFile: AFFIDEVIT CUM DECLARATION_compressed.pdf13 Feb 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed.pdf13 Feb 2022
Proforma of Allotment letterFile: Agreement Draft - English.pdf13 Feb 2022
PAN CardFile: PAN.pdf12 Feb 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate_compressed (1).pdf12 Feb 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_compressed.pdf12 Feb 2022

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
AVADH APARTMENTP NO 2&3 S NO 48-2-2 SERENE MEADOWS8CompletedApr 2015Apr 2015
EESHANYA APARTMENTP NO 71-96 S NO 53-A-2P & 54 BENDKULE NAGAR8CompletedMar 2014Mar 2014

How this compares with Nashik

10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is among them

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Aditi Apartment on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Anandwalli Shiwar4,100+ in Nashik

2 kmAditi ApartmentCompleted 48Lapsed / revoked 8Other 34Dot size: filed unitsN

Filed coordinates, straight-line distance. 90 registered projects within 2 km.

Builder: Minaxi Chaitanya Sompura

Minaxi Chaitanya Sompura has 1 registration on MahaRERA, including Aditi Apartment. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What does it mean that Aditi Apartment shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Aditi Apartment is delayed beyond 6 Jul 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Aditi Apartment?

The registered promoter entity is Minaxi Chaitanya Sompura, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Aditi Apartment?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Aditi Apartment?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Aditi Apartment?

The professionals named in the filing: Architect: MINAXI CHAITANYA SOMPURA; Engineer: Mayuresh Construction; Chartered Accountant: Patil Hiran Jajoo. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Aditi Apartment?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Aditi Apartment. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Aditi Apartment to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.