Registered Litigation declared Residential / Group Housing project

Ace and Matchpoint

By Ricardo Constructions Private Limited

RG-MH-12007 · RERA P51800007641 · Last updated on MahaRERA portal: 30 Jun 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 26 cases
  • 104 complaints at MahaRERA
  • Completion date moved by 87 months
  • 2 extensions taken
  • Rs 1,200.00 crore secured on the land, in favour of Beacon Trusteeship Limited as Trustee

Clear

  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2028Possession promisedmoved 87 months from the original
5 of 11Construction stages donefurthest along: Slabs of Super Structure, 51%
56 of 397Units unsoldnot recorded sold or booked
104Complaints at MahaRERAon this registration
Jump to the 104 documents Report an error

Ace and Matchpoint is a Residential / Group Housing project by Ricardo Constructions Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800007641 on 17 Aug 2017. Possession is promised by 30 Jun 2028. The completion date has moved by 87 months from the original filing. 341 of the 397 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 104 complaints are on record with the regulator.

At a glance

Project

  • NameAce and Matchpoint
  • TypeResidential / Group Housing
  • Location
    • JSD ROAD
    • MULUND WEST
    • Kurla
    • Mumbai Suburban
    • 400080
  • Pincode400080
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800007641
  • ReraGenie IDRG-MH-12007

Builder

  • NameRicardo Constructions Private Limited
  • Entity typeCompany
  • DirectorSreeram Kuppa
  • Other registrations2 more →
  • Declared earlier projects4 →

Key dates

this monthRegisteredAug 2017First promiseMar 2021Revised toJun 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Aug 2017
  • Promised completion30 Jun 2028
  • Revised completionRevised to 30 Jun 2028 (originally 30 Mar 2021)
  • Buildings1 building record
  • Documents filed104 files

Current status

86%341 of 397 units booked
3.0%Work done, per cost certificate

Figures as on 30 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ACE AND MATCHPOINTNA48403970397

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 30 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 51%.

ACE AND MATCHPOINT: 54% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure51%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks38%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 30 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed69

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots69
Closed/Covered69

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,171 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofBeacon Trusteeship Limited as Trustee
Secured amountRs 1,200.00 crore
CERSAI search filedYes
Declared on13 Jan 2026

Approvals and building plan

Sanctioning authorityMunicipal Corporation of Greater Mumbai
Permissible FSI32809.54
Proposed, not sanctioned15,701 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor, Jehangir Building, M G Road, Fort, Mumbai- 400001
Estimated costRs 79.06 cr
Cost incurredRs 2.40 cr
Work done3.04%
BuildingWingEstimatedIncurred
ACE AND MATCHPOINTNARs 73.06 crRs 2.40 cr
-NARs 6.00 cr-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDaisaria Associates
EngineerUmadevan Chinnathambi
EngineerAmarnath Shetty
Chartered AccountantM R B & Associates
Chartered AccountantB R Nagda & Co
PartnerRole in project
Ricardo Constructions Private Limited-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800012886Mar 2021 → Mar 2026

Reason as filed by the promoterSubmission on 24th January 2023: Please refer Tab No. 3 of the “Resolution of the Association of Allottees” wherein the Promoter has enclosed order dated 9th January 2023 passed by the Hon’ble Chairman MahaRERA granting extension to the project till 31st March 2026, thereby disposing of the extension application. Earlier submissions: a) Refer to attachment "Others" called "Explanatory Statement for Extension" b) We have uploaded the 232 consents received from the allottees of the project - “OTHERS” TAB c) We have uploaded Application for Extension of Project Completion date under Section 7(3)

EA14012619453Mar 2021 → Jun 2028

Reason as filed by the promoterThe delay in the completion of the project has primarily occurred due to several unresolved legacy issues pertaining to the larger layout, which were inherited from the previous Promoter, Nirmal Lifestyle Limited, upon the takeover of the project by the current Promoter, Ricardo Constructions Private Limited, on 29 June 2019. These inherited complications resulted in substantial and unforeseen delays in the processing of development permissions by the Municipal Corporation of Greater Mumbai (MCGM). Furthermore, the project's timeline was severely impacted by an extended period of regulatory an

Litigation declared26

CaseCourtStatus
CC/ 548/ 2017/2017The National Consumer Disputes Redressal CommissionNew DelhiAdjourned
CC/1092/2016/2016The National Consumer Disputes Redressal Commission New DelhiAdjourned
CC/1240/2016/2016The National Consumer Disputes Redressal Commission New DelhiAdjourned
CC/1091/2016/2016The National Consumer Disputes Redressal Commission New DelhiAdjourned
CC/1093/2016/2016The National Consumer Disputes Redressal Commission New DelhiAdjourned
CC/572/2016/2016The National Consumer Disputes Redressal Commission New DelhiAdjourned
CC/551 /2017/2007The National Consumer Disputes Redressal Commission New DelhiAdjourned
COMS/64/2024(Stamp)/2024Bombay High CourtOngoing
WP/36046/2025/2025Bombay High CourtOngoing
WP/1122/2023/2023Bombay High CourtOngoing
COMS/133/2023/2023Bombay High CourtOngoing
CC12502921/2025Maharashtra Real Estate Appellate Tribunal (MahaREAT)Ongoing
CC006000000000333/2025Maharashtra Real Estate Appellate Tribunal (MahaREAT)Ongoing
CC006000000209478/2025Maharashtra Real Estate Appellate Tribunal (MahaREAT)Ongoing
CC006000000199159/2025Maharashtra Real Estate Appellate Tribunal (MahaREAT)Ongoing
CC006000000194841/2025Maharashtra Real Estate Appellate Tribunal (MahaREAT)Ongoing
AT006000000053447/2025Maharashtra Real Estate Appellate Tribunal (MahaREAT)Ongoing
AT006000000053445/2025Maharashtra Real Estate Appellate Tribunal (MahaREAT)Ongoing
AT006000000053448/2025Maharashtra Real Estate Appellate Tribunal (MahaREAT)Ongoing
AT006000000053456/2025Maharashtra Real Estate Appellate Tribunal (MahaREAT)Ongoing
AT006000000053446/2025Maharashtra Real Estate Appellate Tribunal (MahaREAT)Ongoing
AT006000000053440/2025Maharashtra Real Estate Appellate Tribunal (MahaREAT)Ongoing
CP/936/24/2025National Company Law Tribunal (NCLT)Ongoing
CC/5/2024/2025The National Consumer Disputes Redressal Commission (NCDRC)Ongoing
CC 5/2023/2023District Consumer Disputes Redressal CommissionOngoing
Not Assigned/2022National Company Law Tribunal (NCLT)Ongoing

Complaints filed with MahaRERA104

Case no.ComplainantRespondentFiled
CC006000000055233AVINASHDHAWALESh. Dharmesh Jain, MD03/07/2018
CC006000000192983AVINASH DHAWALENirmal lifestyle ltd and its directors, Ricardo construction pvt ltd and its director12/03/2020
CC006000000000333Kundlik N BhapkarDharmesh Jain14/09/2017
CC006000000302889Kundlik N BhapkarRICARDO Construction PVT Ltd30/09/2022
CC006000000001694MAHENDRA DASHARTH BORKARNIRMAL LIFESTYLE LTD16/03/2018
CC006000000001588Pramod AshtekarNirmal Lifestyle Ltd03/11/2017
CC006000000001682Saurabh PathakM/s Nirmal Lifestyle Ltd04/11/2017
CC006000000001683Sherly AlbertNirmal Lifestyle06/11/2017
CC006000000001689Yogesh Ganpat SurveNirmal Lifestyle06/11/2017
CC006000000001690Satej RajeshirkeNirmla lifestyle07/11/2017
CC006000000044260Dilip GagwaniNIRMAL LIFE STYLE24/04/2018
CC006000000054839Mayank ChaudharyNirmal Lifestyle Ltd09/06/2018
CC006000000055524Gul RochlaniM/S NIRMAL LIFESTYLE LTD02/08/2018
CC006000000055822John MathewNirmal Lifestyle Ltd.18/08/2018
CC006000000058064Mr Narendra Parmanand LilaneyM/s Nirmal Lifestyle Ltd12/02/2019
CC006000000078311NARESH JAYSUKHALAL PARIKHNIRMAL LIFESTYLE LTD01/03/2019
CC006000000078774ANAND RAJARAMNirmal Lifestyles Limited04/04/2019
CC006000000079139Mr Vishal Bhanudas Ghule and Ms Nutan Chudaman WankhedeRicardo Constructions Private Limited04/05/2019
CC006000000089577SivaramakrishnanNirmal Lifestyle Limited03/06/2019
CC006000000089730PRAJKTA AND AMIT KULKARNINIRMAL LIFESTYLE PVT. LTD.13/06/2019
CC006000000100459Gracious Communication Pvt. Ltd.Nirmal Lifestyle Pvt. Ltd.14/08/2019
CC006000000141071Deepak Jaiprakash Rai and Swatantra Jaiprakash RaiRicardo Construction Private Limited03/10/2019
CC006000000161352Amol SawantNirmal Lifestyle Limited04/11/2019
CC006000000182051sunilmahendrachaurasianirmal lifestyle Ltd & now known as ricardo constructions Pvt. Ltd & ors.02/01/2020
CC006000000192120Swapnil GawasRICARDO CONSTRUCTIONS PVT LTD10/01/2020
CC006000000192365US OPEN AOARicardo Construction Private Limited30/01/2020
CC006000000196174HT Media LimitedRicardo Constructions Private Limited26/02/2021
CC006000000196175HT Media LimitedRicardo Constructions Private Limited26/02/2021
CC006000000196176HT Media LimitedRicardo Constructions Private Limited26/02/2021
CC006000000196177HT Media LimitedRicardo Constructions Private Limited26/02/2021
CC006000000194841Dr Rajkaran Singh and Mrs Shahsi SinghNirmal Lifestyle Ltd07/11/2020
CC006000000196382Arun RamasubramanianNirmal Lifestyle Limited22/03/2021
CC006000000197317Rahul Surendraprasad DwivediRicardo Constructions Private Limited22/06/2021
CC006000000198360Prakash H ChandiramaniDharmesh s. Jain.20/09/2021
CC006000000198527Mr. Anand Raman and Mrs, Shweta AnandRicardo Constructions Pvt Ltd05/10/2021
CC006000000198529Mr. Shailesh Dave and Mrs, Matangi DaveRicardo Constructions Pvt Ltd04/10/2021
CC006000000198577Mr. Shekhar Shimpi and Mrs. Preeti AgarwalNirmal Lifestyle Ltd07/10/2021
CC006000000198578Mrs. Mini GuptaNirmal Lifestyle Ltd07/10/2021
CC006000000198598Mr Kirti Dedhia Mrs Hansa DedhiaNirmal Lifestyle Ltd08/10/2021
CC006000000198643Mrs Shilpa Sanjeev SharmaNirmal Lifestyle Ltd11/10/2021
CC006000000198647Mr Anil Kumar Jha and Mrs Bindu Anilkumar JhaNirmal Lifestyle Ltd12/10/2021
CC006000000198665Mr Saurabh Pathak and Mrs Leena PathakNirmal Lifestyle Ltd21/10/2021
CC006000000198701Mr Manojkumar D JethwaniNirmal Lifestyle Ltd18/10/2021
CC006000000198703Mr. Rakesh Bhojraj PahujaNirmal Lifestyle Ltd18/10/2021
CC006000000198727Mr. Bharatendu KapoorNirmal Lifestyle Ltd22/10/2021
CC006000000198856Mr Shailesh Kadri Mohandas and Mrs Supriya Shailesh MohandasNirmal Lifestyle Ltd29/10/2021
CC006000000198859Mr Abhinay Dilip Joshi Mr Dilip Goinnd JoshiNirmal Lifestyle Ltd29/10/2021
CC006000000199050Mr Ajay Nair and Mrs Smitha NairNirmal Lifestyle Ltd18/11/2021
CC006000000199070Mrs Sherley Albert and Mr Albert Thayyil AntonyNirmal Lifestyle Ltd18/11/2021
CC006000000199159Mr Himanshu Vasudeo Bharambay and Mrs Rohini Vasudeo BharambayNirmal Lifestyle Ltd26/11/2021
CC006000000209398Sunita Manohar TejwaniNirmal Lifestyle Limited13/12/2021
CC006000000209442Manohar TejwaniNirmal Lifestyle Ltd17/12/2021
CC006000000209731Prashant Janardhan KachareNirmal Lifestyle Limited25/01/2022
CC006000000199278Mr Anoop Gupte and Mrs Swati Anoop GupteNirmal Lifestyle Ltd06/12/2021
CC006000000209359Mr Pramod Shankar Mahimkar and Mrs Shubhangi Pramod MahimkarNirmal Lifestyle Ltd10/12/2021
CC006000000209394Vishal Ramesh HaldankarNirmal Lifestyle Ltd16/12/2021
CC006000000209478Mrs Anjali Deepak Pandit and Mr Adwait Deepak PanditNirmal Lifestyle Ltd21/12/2021
CC006000000210205Mr Sundip Lokhande & Mrs Vimal LokhandeNirmal Lifestyle Ltd02/03/2022
CC006000000397985Ricardo Constructions Private LimitedMayank Chemiplast Private Limited26/10/2023
CC12400220Kundlik N BhapkarRicardo Constructions Private Limited25/09/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Dec 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2028

Documents filed104

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 104 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Ace MP- Form 2A- FY 25-26.pdf30 Jun 2026
Withdrawal Update Form 1File: Ace MP- Form 1- Mar 2026.pdf8 Jun 2026
Withdrawal Update Form 2File: Ace MP- Form 2- Mar 2026.pdf8 Jun 2026
Withdrawal Update Form 3File: Ace MP- Form 3- March 2026.pdf8 Jun 2026
Form 1File: Ace MP- Form 1- March 2025.pdf7 Apr 2026
Form 2File: Ace MP- Form 2- March 2025.pdf7 Apr 2026
Form 3File: Ace MP- Form 3- March 2025.pdf7 Apr 2026
Disclosure of Sold and Booked InventoryFile: Ace MP- Inventory Report- March 2025.pdf7 Apr 2026
Self-declaration of Quarterly ProgressFile: Ace Mp- PPR- Mar 2025.pdf7 Apr 2026
Withdrawal Update Form 1File: Ace MP- Form 1- Dec 2025.pdf2 Apr 2026
Withdrawal Update Form 1File: Ace MP- Form 1- Dec 2025.pdf2 Apr 2026
Withdrawal Update Form 2File: Ace MP- Form 2- Dec 2025.pdf2 Apr 2026
Withdrawal Update Form 2File: Ace MP- Form 2- Dec 2025.pdf2 Apr 2026
Withdrawal Update Form 3File: Ace MP- Form 3- Dec 2025.pdf2 Apr 2026
Withdrawal Update Form 3File: Ace MP- Form 3- Dec 2025.pdf2 Apr 2026
Withdrawal Update Form 1File: Ace MP- Form 1- June 2025.pdf14 Jan 2026
Withdrawal Update Form 1File: Ace MP- Form 1- June 2025.pdf14 Jan 2026
Withdrawal Update Form 2File: Ace MP- Form 2- June 2025.pdf14 Jan 2026
Withdrawal Update Form 2File: Ace MP- Form 2- Sept 2025.pdf14 Jan 2026
Withdrawal Update Form 3File: Ace MP- Form 3- June 2025.pdf14 Jan 2026
Withdrawal Update Form 3File: Ace MP- Form 3- Sept 2025.pdf14 Jan 2026
Form 5 (FY 2024-2025)File: Ace MP- Form 5- FY 24-25.pdf8 Oct 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ace MP- PPR- Sept 2024.pdf18 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ace MP- Form 1- Sept 2024.pdf18 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ace MP- PPR- Dec 2024.pdf18 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ace MP- Form 1- Dec 2024.pdf18 Feb 2025
Certificates of CA (Form 3)File: Ace MP- No Withdrawal- Sept 2024.pdf18 Feb 2025
Certificates of CA (Form 3)File: Ace MP- Form 3- Sept 2024.pdf18 Feb 2025
Certificates of CA (Form 3)File: Ace MP- No Withdrawal- Dec 2024.pdf18 Feb 2025
Certificates of CA (Form 3)File: Ace MP- Form 3- Dec 2024.pdf18 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Ace MP- Form 2- Sept 2024.pdf18 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Ace MP- Form 2- Dec 2024.pdf18 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Ace MP- Form 5- FY 2023-24.pdf9 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Ace MP- Form 5- FY 2023-24.pdf9 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: acemp.pdf31 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ace MP- Physical Report- June 2024.pdf31 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Ace MP- Form 2- June 2024.pdf31 Jul 2024
Certificates of CA (Form 3)File: Ace MP- Form 3- June 2024 (reduced).pdf31 Jul 2024
Certificates of CA (Form 3)File: Ace MP- No Withdrawal Declaration- June 2024.pdf31 Jul 2024
CERSAI detailsFile: CERSAI Report- Ricardo- IOM- Mulund.pdf23 Jul 2024
Details of encumbrancesFile: Ace MP- Encumbrance Letter- June 2024.pdf3 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Acemp- Mar 24.pdf1 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ace MP- Form 1- March 2024.pdf29 Jun 2024
Certificates of CA (Form 3)File: Ace MP- Form 3- March 2024.pdf29 Jun 2024
Certificates of CA (Form 3)File: Ace MP- Self Declaration for CA Certificate.pdf29 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Ace MP- Form 5 (FY 22-23).pdf30 Sep 2023
Declaration in FORM BFile: Form B- Aces and MP (with Annexure).pdf8 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- March 2020.pdf14 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- March 2021.pdf14 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- June 2021.pdf14 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Sept 2021.pdf14 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Dec 2021.pdf14 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- March 2022.pdf14 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Acemp- Dec 22.pdf14 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: March 2020.pdf14 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: March 2021.pdf14 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: June 2021.pdf14 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Sept 2021.pdf14 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Dec 2021.pdf14 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: March 2022.pdf14 Feb 2023
Certificates of CA (Form 3)File: Form-3 Ace and Match point (reduced size).pdf14 Feb 2023
Certificates of CA (Form 3)File: March 2020.pdf14 Feb 2023
Certificates of CA (Form 3)File: March 2021.pdf14 Feb 2023
Certificates of CA (Form 3)File: June 2021.pdf14 Feb 2023
Certificates of CA (Form 3)File: Sept 2021.pdf14 Feb 2023
Certificates of CA (Form 3)File: Dec 2021.pdf14 Feb 2023
Certificates of CA (Form 3)File: March 2022.pdf14 Feb 2023
Certificates of CA (Form 3)File: AceMP- Self Declaration for CA Certificate.pdf14 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Exemption for non filing of Form 5 for FY 2019.pdf14 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Ace MP- Form 5- FY 21-22.pdf12 Jan 2023
Layout approvalFile: Layout Approval Letter- 19th Apr 21.pdf7 Dec 2022
Layout approvalFile: Layout Plan- 19th Apr 21.pdf7 Dec 2022
Copy of Layout Approval (in case of layout)File: Layout Approval Letter- 19th Apr 21.pdf7 Dec 2022
Copy of Layout Approval (in case of layout)File: Layout Plan- 19th Apr 21.pdf7 Dec 2022
Declaration about Commencement CertificateFile: Format-D- Declaration under CC.pdf7 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Acemp- Form 1- Nov'22.pdf7 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Ricardo- Declaration- Form 2A.pdf7 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Ricardo- Declaration- Form 2A.pdf7 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Ricardo- Declaration- Form 2A.pdf7 Dec 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory - Aces.pdf7 Dec 2022

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Relish, CherishCity Of Joy CTS No. 661-1-7 Jatashankar Road Mulund W Mumbai 400080332CompletedSep 2009Late, Mar 2010
Bliss, RejoiceCity Of Joy CTS No. 661-1-7 Jatashankar Road Mulund W Mumbai 400080332CompletedSep 2009Late, Mar 2010
Happyness, HurrahCity Of Joy CTS No. 661-1-7 Jatashankar Road Mulund W Mumbai 400080228CompletedJun 2007Late, Dec 2007
Celebration, SparkleCity Of Joy CTS No. 661-1-7 Jatashankar Road Mulund W Mumbai 400080228CompletedJun 2007Late, Dec 2007

How this compares with Mumbai Suburban

86%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 87 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Ace and Matchpoint on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MULUND WEST6,700+ in Mumbai Suburban

2 kmAce and MatchpointCompleted 99Lapsed / revoked 83Other 118Dot size: filed unitsN

Filed coordinates, straight-line distance. 300 registered projects within 2 km.

Builder: Ricardo Constructions Private Limited

Ricardo Constructions Private Limited has 3 registrations on MahaRERA, including Ace and Matchpoint and Grand Slam and Game Point. Its filings disclose 4 earlier MahaRERA projects: declares 0 of 4 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Ace and Matchpoint is delayed beyond 30 Jun 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Ace and Matchpoint?

The registered promoter entity is Ricardo Constructions Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Ace and Matchpoint?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Ace and Matchpoint?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Ace and Matchpoint?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Ace and Matchpoint?

The professionals named in the filing: Architect: Daisaria Associates; Engineer: Umadevan Chinnathambi; Engineer: Amarnath Shetty; Chartered Accountant: M R B & Associates; Chartered Accountant: B R Nagda & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Ace and Matchpoint?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Ace and Matchpoint. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Ace and Matchpoint to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.