Registered No litigation declared Others project

ABK JAGIRDAR TOWN PLAZA

By ABK REALTY

RG-MH-13412 · RERA P51500047019 · Last updated on MahaRERA portal: 13 May 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedno revision filed
11 of 11Construction stages doneevery applicable stage filed complete
26 of 46Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 79 documents Report an error

ABK JAGIRDAR TOWN PLAZA is a Others project by ABK REALTY in Aurangabad, Maharashtra, registered with MahaRERA as P51500047019 on 26 Sep 2022. Possession is promised by 31 Mar 2027. 20 of the 46 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete.

At a glance

Project

  • NameABK JAGIRDAR TOWN PLAZA
  • TypeOthers
  • Location
    • CTS No.2172/2
    • Makai Gate Road
    • Near Ghati
    • MAKAI GATE ROAD
    • AURANGABAD
    • Aurangabad (M Corp.)
    • Aurangabad
    • 431001
  • Pincode431001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500047019
  • ReraGenie IDRG-MH-13412

Builder

  • NameABK REALTY
  • Entity typePartnership
  • PartnersABDUL RAHMAN JAVED KHAN, SYED BILAL MOHIUDDIN QUADRI, JAVED AHMED KHAN

Key dates

this monthRegisteredSep 2022PromisedMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on26 Sep 2022
  • Promised completion31 Mar 2027
  • Revised completionNone
  • Buildings1 building record
  • Documents filed79 files

Current status

43%20 of 46 units booked
85.0%Work done, per cost certificate

Figures as on 13 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ABK JAGIRDAR TOWN PLAZANA77301646

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 13 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 11 construction stages are filed complete.

ABK JAGIRDAR TOWN PLAZA: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 13 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed73

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots73
Closed/Covered73

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area695 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on19 May 2025
LandownerVillageDistrict
SHAUKAT ALI KHAN SHABBIR ALI KHANAurangabad (M Corp.)Aurangabad

Approvals and building plan

Sanctioning authorityAurangabad Municipal Corporation
Permissible FSI2555.79
Proposed, not sanctioned2,556 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRAUZA BAUGH AURANGABAD
Estimated costRs 9.23 cr
Cost incurredRs 7.85 cr
Work done85.0%
BuildingWingEstimatedIncurred
ABK JAGIRDAR TOWN PLAZANARs 9.23 crRs 7.85 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMd. Nazeeruddin
EngineerKHAN SOHEL
Chartered AccountantYASH NAGAR
PartnerRole in project
ABK REALTY-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Sep 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Sep 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Sep 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Sep 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed79

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Architect oct 2025.pdf13 May 2026
Withdrawal Update Form 1File: Form 1 Architect oct 2025.pdf13 May 2026
Withdrawal Update Form 2File: Form 2 Engineer oct 2025.pdf13 May 2026
Withdrawal Update Form 2File: Form 2 Engineer oct 2025.pdf13 May 2026
Withdrawal Update Form 3File: Form 3 CA Certificate oct 2025.pdf13 May 2026
Withdrawal Update Form 3File: Form 3 CA Certificate oct 2025.pdf13 May 2026
Withdrawal Update Form 1File: Form 1 Architect oct 2025.pdf22 Nov 2025
Withdrawal Update Form 2File: Form 2 Engineer oct 2025.pdf22 Nov 2025
Withdrawal Update Form 3File: Form 3 CA Certificate oct 2025.pdf22 Nov 2025
Withdrawal Update Form 1File: FORM 1 2025-26 Q1.pdf21 Aug 2025
Withdrawal Update Form 2File: Form 2 2025-26 Q1.pdf21 Aug 2025
Withdrawal Update Form 3File: FORM 3 2025-26 Q1.pdf21 Aug 2025
Form 1File: Form 1 Architect Certificate oct nov dec 2024.pdf16 Aug 2025
Form 2File: Form 2 engineers Certificate oct nov dec 2024.pdf16 Aug 2025
Form 3File: FORM 3 Upload.pdf16 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold 24-25 Q3.pdf16 Aug 2025
Form 1File: Form 1 2024-25 Q2.pdf16 Aug 2025
Form 2File: Form 2 2024-25 Q2.pdf16 Aug 2025
Form 3File: FORM 3 2024-25 Q2.pdf16 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold 2024-25 Q2.pdf16 Aug 2025
Form 1File: FORM 1 24-25 Q1.pdf16 Aug 2025
Form 2File: Form 2 2024-25 Q1.pdf16 Aug 2025
Form 3File: Form 3 2024-25 Q1.pdf16 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD INVENTORY 24-25 Q1.pdf16 Aug 2025
Withdrawal Update Form 1File: FORM 1 2025-26 Q1.pdf16 Aug 2025
Withdrawal Update Form 2File: Form 2 2025-26 Q1.pdf16 Aug 2025
Withdrawal Update Form 3File: FORM 3 2025-26 Q1.pdf16 Aug 2025
Form 1File: Form 1 2024-25 Q4.pdf19 May 2025
Form 2File: Form 2 2024-25 Q4.pdf19 May 2025
Form 3File: Form 3 2024-25 Q4.pdf19 May 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold 2024-25 Q4.pdf19 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate oct nov dec 2024.pdf28 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Upload.pdf28 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 engineers Certificate oct nov dec 2024.pdf28 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold 24-25 Q3.pdf28 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 2024-25 Q2.pdf16 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 2024-25 Q2_.pdf16 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 2024-25 Q2.pdf16 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold 2024-25 Q2.pdf16 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 24-25 Q2.pdf11 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 24-25 Q2.pdf11 Jul 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY 24-25 Q2.pdf11 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 24-25 Q2.pdf11 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality assurance certificate Form 2A.pdf25 May 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf25 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_c.pdf25 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf24 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf24 May 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf2 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 OCT TO DEC 2023.pdf2 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: CCF26022024.pdf27 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: CCF26022024_0001.pdf27 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 RERA 2ND QTR 2023.pdf5 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf8 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf8 Nov 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf8 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CCF14082023.pdf14 Aug 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold.pdf12 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf9 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf9 Jul 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank.pdf31 Mar 2023
CERSAI detailsFile: CERSAI_Search_Report.pdf12 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_11zon.pdf12 Sep 2022
Proforma of Allotment letterFile: Performa of allotment letter_11zon.pdf12 Sep 2022
Proforma of Allotment letterFile: RERA_Agreement _for_sale_11zon.pdf12 Sep 2022
Copy of the legal title reportFile: Rera Search Report.pdf10 Sep 2022
Details of encumbrances concerned to FinanceFile: Encumbrance Cert.pdf10 Sep 2022
Details of encumbrances concerned to LegalFile: Encumbrance To Legal.pdf10 Sep 2022
Declaration about Commencement CertificateFile: Declaration of Commencement Cert.pdf10 Sep 2022
Declaration in FORM BFile: Form B.pdf10 Sep 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Seprate Bank Declaration.pdf10 Sep 2022
Deviation Report with respect to Allotment letterFile: Deviation of Allotment Letter.pdf10 Sep 2022
Deviation Report with respect to model copy of AgreementFile: Deviation of Agreement to sale.pdf10 Sep 2022
Layout approvalFile: Layout Plan.pdf8 Sep 2022
Building plan approvalFile: Building Plan_11zon.pdf8 Sep 2022
PAN CardFile: Firm Pan Card.pdf8 Sep 2022
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf8 Sep 2022
Building Plan Approval / NA Order for plotted developmentFile: Building Plan_11zon.pdf8 Sep 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf8 Sep 2022

How this compares with Aurangabad

43%of this project is bookeddistrict median 6%
14%of Aurangabad projects moved their completion datethis one has not
32%of Aurangabad registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep ABK JAGIRDAR TOWN PLAZA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MAKAI GATE ROAD, AURANGABAD1,400+ in Aurangabad

2 kmABK JAGIRDAR TOWN PLAZACompleted 7Lapsed / revoked 9Other 8Dot size: filed unitsN

Filed coordinates, straight-line distance. 24 registered projects within 2 km.

Builder: ABK REALTY

ABK REALTY has 1 registration on MahaRERA, including ABK JAGIRDAR TOWN PLAZA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What are my rights if ABK JAGIRDAR TOWN PLAZA is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ABK JAGIRDAR TOWN PLAZA?

The registered promoter entity is ABK REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ABK JAGIRDAR TOWN PLAZA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ABK JAGIRDAR TOWN PLAZA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ABK JAGIRDAR TOWN PLAZA?

The professionals named in the filing: Architect: Md. Nazeeruddin; Engineer: KHAN SOHEL; Chartered Accountant: YASH NAGAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ABK JAGIRDAR TOWN PLAZA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ABK JAGIRDAR TOWN PLAZA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ABK JAGIRDAR TOWN PLAZA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.