ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / AARAMBH WING C -D

Completed No litigation declared Residential / Group Housing project

AARAMBH WING C -D

By SATELLITE DEVELOPERS PVT LTD

RG-MH-38537 · RERA P51800015002 · Last updated on MahaRERA portal: 19 Jan 2024

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • 1 extension taken

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jan 2023Possession promisedregistration recorded completed
16 of 22Construction stages doneacross 2 buildings; furthest along: Basement (if any), 0%
2Complaints at MahaRERAon this registration
Jump to the 106 documents Report an error

AARAMBH WING C -D is a Residential / Group Housing project by SATELLITE DEVELOPERS PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800015002 on 22 Jan 2018. The registration is recorded completed; possession was promised by 25 Jan 2023. 2 complaints are on record with the regulator.

At a glance

Project

  • NameAARAMBH WING C -D
  • TypeResidential / Group Housing
  • Location
    • Off Azad Chourasiya road
    • Appa pada
    • Gandhi Nagar Malad East
    • Borivali
    • Mumbai Suburban
    • 400097
  • Pincode400097
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800015002
  • ReraGenie IDRG-MH-38537

Builder

  • NameSATELLITE DEVELOPERS PVT LTD
  • Entity typeCompany
  • DirectorSARJAN SHAH
  • Other registrations4 more →
  • Completed3 of 5
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

this monthRegisteredJan 2018PromisedJan 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on22 Jan 2018
  • Promised completion25 Jan 2023
  • Revised completionNone
  • Buildings2 building records
  • Documents filed106 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AARAMBH WING CNA200000
AARAMBH WING DNA200000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 19 Jan 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 0%.

AARAMBH WING C73%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
AARAMBH WING D73%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities20

As on 19 Jan 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
GymnasiumYes0%
INDOOR GAMES ROOMYes0%
WALKING TRACKYes0%
Multipurpose roomYes0%
KIDS PLAY AREAYes0%

Parking filed41

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots41
Closed/Covered41
BuildingClosed/CoveredTotal
AARAMBH WING C1919
AARAMBH WING D2222

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area576 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI6909.0
Proposed, not sanctioned6,909 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSandoz House, Dr AB Road Worli Mumbai 400018

Certifying professionals and partners10

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSandeep Shikre & Associates
ArchitectVivek Barve
EngineerAlpesh Gandhi
EngineerBalram Sudam Shendkar
EngineerWasim Ghori
Chartered AccountantAJ Saboo Associates
Chartered AccountantNORO & Co
Chartered AccountantRR Kabra & Birla
Chartered AccountantVC Shah and Co
Chartered AccountantSV Shah & Associates
PartnerRole in project
SATELLITE DEVELOPERS PVT LTD-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800013507Jan 2023 → Jun 2023

Reason as filed by the promoterCurrent project is affordable segment real estate project with unit cost upto 45Lakhs. Post covid-19 there was acute shortage of labour in Real Estate Market. Project can't afford higher labour cost than the budgeted cost. Hence to get the finishing work done with the limited resources 2-3months extra time is needed from the original estimated date i.e. 25Jan2023.

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC006000000500568SATELLITE DEVELOPERS PVT LTD SATELLITE DEVELOPERS PVT LTDSUSHANT SUBHASH MESTRI25/05/2024
CC12503189Saumya Dasappa GowdaBatul10/09/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Jan 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Jan 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Jan 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Feb 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 26 Jul 2023

Documents filed106

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 106 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Details of encumbrances concerned to FinanceFile: 03-Aarambh CD Legal Declaration.pdf19 Jan 2024
Details of encumbrances concerned to LegalFile: 03-Aarambh CD Legal Declaration.pdf19 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Aarambh C-D - Form 5 FY 22-23.pdf23 Nov 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: AARAMBH OC MARCH 2023.pdf26 Jul 2023
Architect’s Certificate on Completion of Project (Form 4)File: Aarambh C-D Form 4.pdf25 Jul 2023
Certificates of CA (Form 3)File: Aarambh C-D Form-3 CA Cert-FY-22-23 Q4.pdf5 Jun 2023
Certificates of CA (Form 3)File: CA Certificate Form 3 Qtr - June 2022.pdf11 Jan 2023
Certificates of CA (Form 3)File: CA Certificate Form 3 Qtr - Sep 2022.pdf11 Jan 2023
Certificates of CA (Form 3)File: CA Certificate Form 3 Qtr - Dec 2022.pdf11 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aarambh C D-Form-1-FY23-Q1.pdf9 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aarambh C D-Form-1-FY23-Q2.pdf9 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aarambh C D-Form-1-FY23-Q3.pdf9 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh C D-Form-2-FY23-Q1.pdf9 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh C D-Form-2-FY23-Q2.pdf9 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh C D-Form-2-FY23-Q3.pdf9 Jan 2023
Details of encumbrances concerned to FinanceFile: Self-Certified Encumbrances Certificate.pdf29 Dec 2022
Details of encumbrances concerned to LegalFile: Self-Certified Encumbrances Certificate.pdf29 Dec 2022
Declaration about Commencement CertificateFile: Declaration of CC.pdf29 Dec 2022
Disclosure of sold/ booked inventoryFile: Disclosure on sold inventory.pdf29 Dec 2022
CERSAI detailsFile: CERSAI Details.pdf29 Dec 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration on seperate bank account.pdf29 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Architect Certificate June 2021.pdf28 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Architect Certificate Sept 2021.pdf28 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Architect Certificate Dec 2021.pdf28 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Architect Certificate March 2022.pdf28 Dec 2022
Certificates of CA (Form 3)File: CA Certificate Form 3 - Qtr Mar 18.pdf28 Dec 2022
Certificates of CA (Form 3)File: CA Certificate Form 3 - Qtr June 18.pdf28 Dec 2022
Certificates of CA (Form 3)File: CA Certificate Form 3 - Qtr Sep 18.pdf28 Dec 2022
Certificates of CA (Form 3)File: CA Certificate Form 3 - Qtr Dec 18.pdf28 Dec 2022
Certificates of CA (Form 3)File: CA Certificate Form 3 - Qtr June 19.pdf28 Dec 2022
Certificates of CA (Form 3)File: CA Certificate Form 3 - Qtr Dec 19.pdf28 Dec 2022
Certificates of CA (Form 3)File: CA Certificate Form 3 - Qtr June 20.pdf28 Dec 2022
Certificates of CA (Form 3)File: CA Certificate Form 3 - Qtr Sep 20.pdf28 Dec 2022
Certificates of CA (Form 3)File: CA Certificate Form 3 - Qtr Dec 20.pdf28 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aarambh C D-Form-1-FY18Q4.pdf27 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aarambh C D-Form-1-FY19Q1.pdf27 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aarambh C D-Form-1-FY19Q2.pdf27 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aarambh C D-Form-1-FY19Q3.pdf27 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aarambh C D-Form-1-FY19Q4.pdf27 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aarambh C D-Form-1-FY20Q1.pdf27 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aarambh C D-Form-1-FY20Q2.pdf27 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aarambh C D-Form-1-FY20Q3.pdf27 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aarambh C D-Form-1-FY20Q4.pdf27 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aarambh C D-Form-1-FY21Q1.pdf27 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aarambh C D-Form-1-FY21Q2.pdf27 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aarambh C D-Form-1-FY21Q3.pdf27 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aarambh C D-Form-1-FY21Q4.pdf27 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh C D-Form-2-FY18Q4.pdf27 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh C D-Form-2-FY19Q1.pdf27 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh C D-Form-2-FY19Q2.pdf27 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh C D-Form-2-FY19Q3.pdf27 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh C D-Form-2-FY19Q4.pdf27 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh C D-Form-2-FY20Q1.pdf27 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh C D-Form-2-FY20Q2.pdf27 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh C D-Form-2-FY20Q3.pdf27 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh C D-Form-2-FY20Q3.pdf27 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh C D-Form-2-FY20Q4.pdf27 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh C D-Form-2-FY21Q1.pdf27 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh C D-Form-2-FY21Q2.pdf27 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh C D-Form-2-FY21Q3.pdf27 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh C D-Form-2-FY21Q4.pdf27 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Architect Certificate Dec 2021.pdf23 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Architect Certificate March 2022.pdf23 Dec 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Architect Certificate Sept 2021.pdf23 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Engineer Certificate June 2021.pdf23 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Engineer Certificate Sept 2021.pdf23 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Engineer Certificate Dec 2021.pdf23 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Engineer Certificate March 2022.pdf23 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-1 Architect Certificate Sept 2021.pdf23 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Quality Assurance Aarambh C-D 2020.pdf23 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Quality Assurance Aarambh C-D 2019.pdf23 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A-Quality Assurance Aarambh C-D 2022.pdf23 Dec 2022
Certificates of CA (Form 3)File: From-3 Aarambh C-D June 2021.pdf23 Dec 2022
Certificates of CA (Form 3)File: From-3 Aarambh C-D Sept 2021.pdf23 Dec 2022
Certificates of CA (Form 3)File: Form-3 Aarambh C-D Dec 2021.pdf23 Dec 2022
Certificates of CA (Form 3)File: Form-3 Aarambh C-D March 2022.pdf23 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: From-5 Aarambh C-D 2021-22.pdf23 Dec 2022
Certificates of CA (Form 3)File: CA Cost certficate Aarambh CD 2021.pdf15 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form No 5 C D.pdf15 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form-5 Aarambh CD 2021.pdf15 Dec 2022

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Satellite GazeboSatellite Gazebo Andheri Ghatkopar Link Road Chakala Andheri East Mumbai 40009342CompletedApr 2013Late, Jan 2015
Solitaire - 14S 14 Andheri Ghatkopar Link Road Andheri East Mumbai 400 09328CompletedJun 2012Late, Jan 2013
Satellite RoyaleSatellite Royale Pankaj Shah Marg Off Film City Road Goregaon East Mumbai 400063105CompletedMar 2012Late, Dec 2013

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AARAMBH WING C -D on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Appa pada, Gandhi Nagar Malad East6,700+ in Mumbai Suburban

2 kmAARAMBH WING C -DCompleted 56Lapsed / revoked 45Other 77Dot size: filed unitsN

Filed coordinates, straight-line distance. 178 registered projects within 2 km.

Builder: SATELLITE DEVELOPERS PVT LTD

SATELLITE DEVELOPERS PVT LTD has 5 registrations on MahaRERA, including SATELLITE GLORY and AARAMBH WING C -D. Its filings disclose 4 earlier MahaRERA projects: declares 0 of 4 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if AARAMBH WING C -D is delayed beyond 25 Jan 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AARAMBH WING C -D?

The registered promoter entity is SATELLITE DEVELOPERS PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AARAMBH WING C -D?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against AARAMBH WING C -D?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for AARAMBH WING C -D?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AARAMBH WING C -D?

The professionals named in the filing: Architect: Sandeep Shikre & Associates; Architect: Vivek Barve; Engineer: Alpesh Gandhi; Engineer: Balram Sudam Shendkar; Engineer: Wasim Ghori; Chartered Accountant: AJ Saboo Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AARAMBH WING C -D?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AARAMBH WING C -D. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AARAMBH WING C -D to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one