Home / Browse projects / Mumbai Suburban, Maharashtra / AARAMBH WING A-B

Registration lapsed No litigation declared Residential / Group Housing project

AARAMBH WING A-B

By SATELLITE DEVELOPERS PVT LTD

RG-MH-29442 · RERA P51800028424 · Last updated on MahaRERA portal: 23 Jan 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 15 months past the filed date
  • 11 complaints at MahaRERA
  • Completion date moved by 10 months
  • 1 extension taken
  • Rs 92.95 crore secured on the land, in favour of State Bank of India
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

7 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jul 2025Possession promised15 months past this date
9 of 22Construction stages doneacross 2 buildings; furthest along: External plumbing and external plaster, 45%
11Complaints at MahaRERAon this registration
Jump to the 89 documents Report an error

AARAMBH WING A-B is a Residential / Group Housing project by SATELLITE DEVELOPERS PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800028424 on 2 Mar 2021. Possession was promised by 31 Jul 2025 and is now 15 months past that date. The completion date has moved by 10 months from the original filing. 11 complaints are on record with the regulator.

At a glance

Project

  • NameAARAMBH WING A-B
  • TypeResidential / Group Housing
  • Location
    • Off Azad Chourasiya Road
    • Appa Pada
    • Gandhi Nagar
    • Malad East
    • Borivali
    • Mumbai Suburban
    • 400097
  • Pincode400097
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800028424
  • ReraGenie IDRG-MH-29442

Builder

  • NameSATELLITE DEVELOPERS PVT LTD
  • Entity typeCompany
  • DirectorSARJAN SHAH
  • Other registrations4 more →
  • Completed3 of 5
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

15 months past promisethis monthRegisteredMar 2021First promiseSep 2024Revised toJul 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on2 Mar 2021
  • Promised completion31 Jul 2025
  • Revised completionRevised to 31 Jul 2025 (originally 30 Sep 2024)
  • Buildings2 building records
  • Documents filed89 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AARAMBH WING ANA2018000
AARAMBH WING BNA200000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 23 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is External plumbing and external plaster, at 45%.

AARAMBH WING A44%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.45%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.5%
AARAMBH WING B53%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises35%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.45%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.5%

Progress on shared amenities20

As on 23 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
Walking TrackYes0%
Multipurpose roomYes0%
Kids Play AreaYes0%
Indoor Games RoomYes0%
GymnasiumYes0%

Parking filed36

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots36
Closed/Covered36
BuildingClosed/CoveredTotal
AARAMBH WING A1616
AARAMBH WING B2020

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area627 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofState Bank of India
Secured amountRs 92.95 crore
Declared on30 Jul 2025

Approvals and building plan

Sanctioning authoritySLUM REHABILITATION AUTHORITY
Permissible FSI7143.0
Proposed, not sanctioned7,132 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchS V ROAD MALAD WEST MUMBAI-400064

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKIRAN SHIRVATKAR
EngineerAlpesh M Gandhi
Chartered AccountantNORO & Co
Chartered AccountantGupta Jasoria & Associates
PartnerRole in project
SATELLITE DEVELOPERS PVT LTD-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800024637Sep 2024 → Jul 2025

Reason as filed by the promoterAarambh is bigger layout with multiple wings being developed. We got earlier wings delayed by 6-8 months time for which we sought RERA extention and delivered the OC (Wing C-D OC received in March 2023 and Wing E-F OC received in October 2023). Due to the cascading effect of time overrun on the completion of other wings in the same layout adversely affected the execution time for current project i.e. Wing A-B.

Complaints filed with MahaRERA11

Case no.ComplainantRespondentFiled
CC006000000500565SATELLITE DEVELOPERS PVT LTD SATELLITE DEVELOPERS PVT LTDPRATAP NAVNATH NARSINGE25/05/2024
CC006000000500567SATELLITE DEVELOPERS PVT LTD SATELLITE DEVELOPERS PVT LTDANAM MUJADDADI25/05/2024
CC12500097VINAYAK ANKUSH GHADGESATELLITE DEVELOPERS PVT LTD10/01/2025
CC12500321SATELLITE DEVELOPERS PVT LTDPranil Pangale29/01/2025
CC12500553Swapnil SawantSATELLITE DEVELOPERS PVT LTD18/02/2025
CC12502445kiran suraj sonawaneSATELLITE DEVELOPERS PVT LTD17/07/2025
CC12503025Amar Devichand Mehta-27/08/2025
CC12503715Aniket Anil PrabhulkarSATELLITE DEVELOPERS PVT LTD20/10/2025
CC12503721Shobha Anil PatilSATELLITE DEVELOPERS PVT LTD21/10/2025
CC12504019Sanman Ramesh SawantSATELLITE DEVELOPERS PVT LTD14/11/2025
CC12603473Rajababu Ramashankar SinghSATELLITE DEVELOPERS PVT LTD05/06/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Feb 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Feb 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Feb 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Feb 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed89

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 89 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Aarambh AB-Q3 FY 24-25.pdf23 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 CA Aarambh AB FY-24-25 Q3.pdf23 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Aarambh AB-Q3 FY 24-25.pdf23 Jan 2025
Disclosure of sold/ booked inventoryFile: Investory Status Aarambh AB-Dec 24.pdf23 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Aarambh A-B - Form 5 FY 23-24.pdf24 Oct 2024
Declaration in FORM BFile: Form-B Promoter declaration for extension in time.pdf23 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Aarambh AB- RERA Cert 30 Sep 24.pdf23 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aarambh A-B Form-3 Q2 FY 24-25.pdf23 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh A-B Form-2 Q2 FY 24-25.pdf23 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold or Booked Investory Status 29 of 2021.pdf23 Oct 2024
Other - FinanceFile: SECURED LOAN.pdf23 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A-Aarambh AB March 24.pdf23 Oct 2024
Disclosure for secured/unsecured finance availed for the projectFile: SECURED LOAN.pdf23 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Aarambh AB- RERA Cert Q E Jun-24.pdf21 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aarambh A-B Form-3_Q1 Mar-25.pdf21 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh A-B Form-2 Q1 FY 24-25.pdf21 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aarambh A-B Form-1 Q4 FY 23-24.pdf31 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh A-B Form-2 Q4 FY 23-24.pdf31 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aarambh A-B Form-3_Q4 Mar-24.pdf31 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca fORM 3 ab.pdf28 May 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 02-Self Declaration of Bank Annexure-A Aarambh-AB Wing.pdf28 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aarambh A-B Form-3 CA Cert-FY-23-24 Q3-Final.pdf13 May 2024
Other - TechnicalFile: Justification for New Bank Account.pdf13 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aarambh A-B Form-1 Q3 FY 23-24.pdf21 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh A-B Form-2 Q3 FY 23-24.pdf21 Mar 2024
Disclosure of sold/ booked inventoryFile: Details of sold and unsold inventory-December 23.pdf21 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aarambh A-B Form-3 CA Cert-FY-23-24 Q3.pdf21 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A-Aarambh AB March 23.pdf19 Jan 2024
Details of encumbrances concerned to FinanceFile: 03-Aarambh AB-Legal and Finance Declaration.pdf18 Jan 2024
Details of encumbrances concerned to LegalFile: 03-Aarambh AB-Legal and Finance Declaration.pdf18 Jan 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration of seperate bank account.pdf18 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aarambh A-B Form-1 Q4 FY 22-23.pdf17 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aarambh A-B Form-1 Q1 FY 23-24.pdf17 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aarambh A-B Form-1 Q2 FY 23-24.pdf17 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh A-B Form-2 Q4 FY 22-23.pdf17 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh A-B Form-2 Q1 FY 23-24.pdf17 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh A-B Form-2 Q2 FY 23-24.pdf17 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aarambh A-B Form-3 CA Cert-FY-23-24 Q1.pdf10 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Q2 Form 3 FY 23-24.pdf10 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Aarambh A-B - Form 5 FY 22-23.pdf23 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aarambh A-B Form-3 CA Cert-FY-22-23 Q4.pdf5 Jun 2023
Details of encumbrances concerned to FinanceFile: Self-Certified Encumbrances Certificate.pdf13 Feb 2023
Details of encumbrances concerned to LegalFile: Self-Certified Encumbrances Certificate.pdf13 Feb 2023
Declaration about Commencement CertificateFile: Declaration on CC.pdf13 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aaambh AB Form-1 FY 20-21 Q4.pdf13 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aaambh AB Form-1 FY 21-22 Q2.pdf13 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aaambh AB Form-1 FY 21-22 Q3.pdf13 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aaambh AB Form-1 FY 21-22 Q4.pdf13 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aaambh AB Form-1 FY 22-23 Q1.pdf13 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aaambh AB Form-1 FY 22-23 Q2.pdf13 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aaambh AB Form-1 FY 22-23 Q3.pdf13 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh A-B Form 2 Q4 FY 20-21.pdf13 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh A-B Form 2 Q1 FY 21-22.pdf13 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh A-B Form 2 Q2 FY 21-22.pdf13 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh A-B Form 2 Q3 FY 21-22.pdf13 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh A-B Form 2 Q4 FY 21-22.pdf13 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh A-B Form 2 Q1 FY 22-23.pdf13 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh A-B Form 2 Q2 FY 22-23.pdf13 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aarambh A-B Form 2 Q3 FY 22-23.pdf13 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Aaambh AB Form-2A FY 20-21.pdf13 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Aaambh AB Form-2A FY 21-22.pdf13 Feb 2023
CERSAI detailsFile: CERSAI Details.pdf13 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aaambh AB Form-3 FY 20-21 Q4.pdf13 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aaambh AB Form-3 FY 21-22 Q2.pdf13 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aaambh AB Form-3 FY 21-22 Q3.pdf13 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aaambh AB Form-3 FY 21-22 Q4.pdf13 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aaambh AB Form-3 FY 22-23 Q1.pdf13 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aaambh AB Form-3 FY 22-23 Q2.pdf13 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form-5 Aarambh AB 2021.pdf13 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - Aarambh wing A-B 21-22.pdf13 Feb 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration on Bank Account.pdf13 Feb 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Arambh AB Declaration.pdf23 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form No 3 Aarambh AB.pdf14 Aug 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AB Form No 1.pdf13 Aug 2021
Layout approvalFile: Layout Plan_compressed_compressed (2).pdf24 Feb 2021
Copy of Layout Approval (in case of layout)File: Layout Plan_compressed_compressed (2).pdf24 Feb 2021
Commencement Certificates / NA Order for plotted developmentFile: CC Copy-Colour (1).pdf24 Feb 2021
Building plan approvalFile: Amended IOA.pdf19 Feb 2021
Layout approvalFile: LOI-Developers.pdf19 Feb 2021
PAN CardFile: Pan Card SDPL.PDF19 Feb 2021

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Satellite GazeboSatellite Gazebo Andheri Ghatkopar Link Road Chakala Andheri East Mumbai 40009342CompletedApr 2013Late, Jan 2015
Solitaire - 14S 14 Andheri Ghatkopar Link Road Andheri East Mumbai 400 09328CompletedJun 2012Late, Jan 2013
Satellite RoyaleSatellite Royale Pankaj Shah Marg Off Film City Road Goregaon East Mumbai 400063105CompletedMar 2012Late, Dec 2013

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 10 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AARAMBH WING A-B on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Appa Pada, Gandhi Nagar, Malad East6,700+ in Mumbai Suburban

2 kmAARAMBH WING A-BCompleted 56Lapsed / revoked 43Other 75Dot size: filed unitsN

Filed coordinates, straight-line distance. 174 registered projects within 2 km.

Builder: SATELLITE DEVELOPERS PVT LTD

SATELLITE DEVELOPERS PVT LTD has 5 registrations on MahaRERA, including SATELLITE GLORY and AARAMBH WING C -D. Its filings disclose 4 earlier MahaRERA projects: declares 0 of 4 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that AARAMBH WING A-B shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if AARAMBH WING A-B is delayed beyond 31 Jul 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AARAMBH WING A-B?

The registered promoter entity is SATELLITE DEVELOPERS PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AARAMBH WING A-B?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against AARAMBH WING A-B?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for AARAMBH WING A-B?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AARAMBH WING A-B?

The professionals named in the filing: Architect: KIRAN SHIRVATKAR; Engineer: Alpesh M Gandhi; Chartered Accountant: NORO & Co; Chartered Accountant: Gupta Jasoria & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AARAMBH WING A-B?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AARAMBH WING A-B. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AARAMBH WING A-B to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.