Home / Browse projects / Pune, Maharashtra / Aaradhyam Phase I

Completed No litigation declared Commercial project

Aaradhyam Phase I

By Jairaj Developers Unit 11

RG-MH-61728 · RERA P52100016084 · Last updated on MahaRERA portal: 5 Jul 2024

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2023Possession promisedregistration recorded completed
6 of 11Construction stages donefurthest along: Internal walls, 80%
0Complaints at MahaRERAon this registration
Jump to the 40 documents Report an error

Aaradhyam Phase I is a Commercial project by Jairaj Developers Unit 11 in Pune, Maharashtra, registered with MahaRERA as P52100016084 on 16 Apr 2018. The registration is recorded completed; possession was promised by 9 Dec 2023.

At a glance

Project

  • NameAaradhyam Phase I
  • TypeCommercial
  • Location
    • -
    • kondhwa BK
    • Haveli
    • Pune
    • 411048
  • Pincode411048
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100016084
  • ReraGenie IDRG-MH-61728

Builder

  • NameJairaj Developers Unit 11
  • Entity typePartnership
  • PartnersJignesh Gunvant Gopani, Jayant Hiralal Shah
  • Other registrations2 more →
  • Completed3 of 3

Key dates

this monthRegisteredApr 2018PromisedDec 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on16 Apr 2018
  • Promised completion9 Dec 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed40 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Commercial ShopsNA10000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 Jul 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 80%.

Commercial Shops: 74% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%

Progress on shared amenities15

As on 5 Jul 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,058 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1093.89
Proposed, not sanctioned1,094 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBhandarkar Road Pune 411004

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr Jagdish P Deshpande
PartnerRole in project
Jairaj Developers Unit 11-

Litigation declared1

CaseCourtStatus
00965/2015CJSD PuneNotice Unready

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Apr 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Apr 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Apr 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 20 Apr 2022

Documents filed40

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of ConveyanceFile: Aaradhyam Conveyance Deed 1865-2024 - Index-II.pdf5 Jul 2024
Architect’s Certificate on Completion of Project (Form 4)File: Arch_Certificate_Aaradhyam_Phase-I.pdf2 Nov 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Registration Certificate.pdf26 Oct 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: CompletionCetificatePhase1Shops.PDF20 Apr 2022
Annual Audit Report of Statutory CA (Form 5)File: F:\USB\JDU11\JAIRAJ DEVELOPERS UNIT 11Form5.pdf27 Sep 2019
Annual Audit Report of Statutory CA (Form 5)File: F:\USB\JDU11\JAIRAJ DEVELOPERS UNIT 11Form5.pdf27 Sep 2019
Proforma of Allotment letterFile: Allotment Letter.pdf23 May 2018
Proforma of Allotment letterFile: Application Form.pdf23 May 2018
Proforma of Allotment letterFile: Agreement (1).pdf23 May 2018
Proforma of Allotment letterFile: Signed Page 1.PDF23 May 2018
Building plan approvalFile: 05 Building Plan Approved.pdf10 Apr 2018
Layout approvalFile: 04 Layout Approved.pdf10 Apr 2018
PAN CardFile: 01 PAN Card.PDF10 Apr 2018
Copy of the legal title reportFile: 1 To 4.pdf10 Apr 2018
Copy of the legal title reportFile: 5 to 9.pdf10 Apr 2018
Copy of the legal title reportFile: 10 To 20.pdf10 Apr 2018
Copy of the legal title reportFile: 21 To 30.pdf10 Apr 2018
Copy of the legal title reportFile: 31To 40.pdf10 Apr 2018
Copy of the legal title reportFile: 41 To 50.pdf10 Apr 2018
Copy of the legal title reportFile: 51 To 60.pdf10 Apr 2018
Copy of the legal title reportFile: 61 To 70.pdf10 Apr 2018
Copy of the legal title reportFile: 71 To 80.pdf10 Apr 2018
Copy of the legal title reportFile: 81 To 90.pdf10 Apr 2018
Copy of the legal title reportFile: 91 To 100.pdf10 Apr 2018
Copy of the legal title reportFile: 101 To 110.pdf10 Apr 2018
Copy of the legal title reportFile: 111 To 120.pdf10 Apr 2018
Details of encumbrancesFile: 03 Details of Encumbrances.pdf10 Apr 2018
Copy of Layout Approval (in case of layout)File: 04 Layout Approved.pdf10 Apr 2018
Building Plan Approval (IOD)File: 05 Building Plan Approved.pdf10 Apr 2018
Commencement Certificates / NA Order for plotted developmentFile: 07 Commencement Cert - Building Plan.pdf10 Apr 2018
Declaration in FORM BFile: 10 Form-B.PDF10 Apr 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 12 Engineer Certificate.PDF10 Apr 2018
Certificates of CA (Form 3)File: 13 CA Certificate.PDF10 Apr 2018
Proforma of Allotment letterFile: 08 Allotment Letter.pdf10 Apr 2018
Proforma of Allotment letterFile: 09-Flat-Agreement-Aradhyam_07042018-(2)-1-6.pdf10 Apr 2018
Proforma of Allotment letterFile: 09-Flat-Agreement-Aradhyam_07042018-(2)-7-13.pdf10 Apr 2018
Proforma of Allotment letterFile: 09-Flat-Agreement-Aradhyam_07042018-(2)-14-21.pdf10 Apr 2018
Proforma of Allotment letterFile: 09-Flat-Agreement-Aradhyam_07042018-(2)-22-29.pdf10 Apr 2018
Proforma of Allotment letterFile: 09-Flat-Agreement-Aradhyam_07042018-(2)-30-37.pdf10 Apr 2018
Proforma of Allotment letterFile: 09-Flat-Agreement-Aradhyam_07042018-(2)-38-48.pdf10 Apr 2018

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Aaradhyam Phase I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near -13,700+ in Pune

2 kmAaradhyam Phase ICompleted 69Lapsed / revoked 37Other 52Dot size: filed unitsN

Filed coordinates, straight-line distance. 158 registered projects within 2 km.

Builder: Jairaj Developers Unit 11

Jairaj Developers Unit 11 has 3 registrations on MahaRERA, including Aaradhyam Phase I and Aaradhyam Phase II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Aaradhyam Phase I is delayed beyond 9 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Aaradhyam Phase I?

The registered promoter entity is Jairaj Developers Unit 11, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Aaradhyam Phase I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Aaradhyam Phase I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Aaradhyam Phase I?

The professionals named in the filing: Architect: Mr Jagdish P Deshpande. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Aaradhyam Phase I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Aaradhyam Phase I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Aaradhyam Phase I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.