Home / Browse projects / Aurangabad, Maharashtra / Aakash Ganga Phase II

Registered No litigation declared Residential / Group Housing project

Aakash Ganga Phase II

By Aakash Ganga Developers

RG-MH-52517 · RERA P51500054973 · Last updated on MahaRERA portal: 29 May 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 16 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Feb 2027Possession promisedmoved 16 months from the original
7 of 11Construction stages donefurthest along: Basement (if any), 0%
5 of 12Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 76 documents Report an error

Aakash Ganga Phase II is a Residential / Group Housing project by Aakash Ganga Developers in Aurangabad, Maharashtra, registered with MahaRERA as P51500054973 on 21 Feb 2024. Possession is promised by 21 Feb 2027. The completion date has moved by 16 months from the original filing. 7 of the 12 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.

At a glance

Project

  • NameAakash Ganga Phase II
  • TypeResidential / Group Housing
  • Location
    • Nakshtrawadi
    • Mouje-Nakshtrawadi
    • Aurangabad (M Corp.)
    • Aurangabad
    • 431005
  • Pincode431005
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51500054973
  • ReraGenie IDRG-MH-52517

Builder

  • NameAakash Ganga Developers
  • Entity typePartnership
  • GSTIN27AALFA5173F1ZF
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersSurekha Ashok Patil, Sunita Ramesh Dhorde
  • Partner & Authorised SignatoriesKiran Vasantrao Patil, Shodhan Yashwant Joshi
  • Other registrations2 more →

Key dates

this monthRegisteredFeb 2024First promiseOct 2025Revised toFeb 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on21 Feb 2024
  • Promised completion21 Feb 2027
  • Revised completionRevised to 21 Feb 2027 (originally 1 Oct 2025)
  • Buildings1 building record
  • Documents filed76 files

Current status

58%7 of 12 units booked
100.0%Work done, per cost certificate

Figures as on 29 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block - CBlock - C2212012

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 29 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

Block - C · wing Block - C: 64% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 29 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes99%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes99%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes99%
Street LightingYes99%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed12

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots12
Open Space12

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,712 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
Declared on29 Jan 2026

Approvals and building plan

Sanctioning authorityMunicipal Corporation Chhtrapati Sambhajinagar
Permissible FSI929.76
Proposed, not sanctioned930 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKanchan Chambers , Kranti chowk Station Road
Estimated costRs 1.64 cr
Cost incurredRs 1.64 cr
Work done100.0%
BuildingWingEstimatedIncurred
Block - CBlock - CRs 1.53 crRs 1.53 cr
-NARs 10.50 lakhRs 10.50 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSATYAM B JADHAV
EngineerRavindra Bhabhulay
Chartered AccountantCA Santosh Garud
Chartered AccountantSunil Salunke
PartnerRole in project
Aakash Ganga Developers-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA08092502533Oct 2025 → Feb 2027

Reason as filed by the promoterWe have encountered unforeseen delays in the completion of the project, primarily due to a difference between the demand we had initially anticipated during the registration process and the actual market response observed after commencement. At the time of registration, the original project timeline was based on our comprehensive assessment of expected demand. However, as the project progressed, it became clear that the market response was not aligned with our initial projections. This variance in demand has led to several adjustments in our construction schedule, resulting in a revised and ex

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Oct 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Jan 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Sep 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jan 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 21 Feb 2027

Documents filed76

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: 1 Form 1 Phase II Q4.pdf29 May 2026
Withdrawal Update Form 2File: 2 Form 2 Phase II Q4.pdf29 May 2026
Withdrawal Update Form 3File: 3 Form 3 Phase II Q4.pdf29 May 2026
Withdrawal Update Form 1File: 1 Form 1 Phase II Q4.pdf28 May 2026
Withdrawal Update Form 2File: Form-2 Phase II.pdf28 May 2026
Withdrawal Update Form 3File: 3 Form 3 Phase II Q4.pdf28 May 2026
Withdrawal Update Form 1File: Form 1 Phase II.pdf16 Feb 2026
Withdrawal Update Form 2File: Form-2 Phase II.pdf16 Feb 2026
Withdrawal Update Form 3File: Form 3 Phase II.pdf16 Feb 2026
Layout approvalFile: New Layout ORIGINAL_edited.pdf8 Jan 2026
Layout approvalFile: GSR 2020-21.pdf4 Dec 2025
Withdrawal Update Form 1File: Phase 2 Form 1 Q2 25-26.pdf28 Oct 2025
Withdrawal Update Form 1File: Phase 2 Form 1 Q2 25-26.pdf28 Oct 2025
Withdrawal Update Form 2File: Phase 2 Form 2 Q2 25-26.pdf28 Oct 2025
Withdrawal Update Form 2File: Phase 2 Form 2 Q2 25-26.pdf28 Oct 2025
Withdrawal Update Form 3File: Phase 2 Form 3 Q2 25-26.pdf28 Oct 2025
Withdrawal Update Form 3File: Phase 2 Form 3 Q2 25-26.pdf28 Oct 2025
Form 5 (FY 2024-2025)File: Form 5 phase 2.pdf7 Oct 2025
Form 2A (FY 2024-2025)File: Form 2A.pdf25 Sep 2025
Form 1File: Final Form 1.pdf5 Sep 2025
Form 2File: Final Form 2.pdf5 Sep 2025
Form 3File: Final Form 3.pdf5 Sep 2025
Disclosure of Sold and Booked InventoryFile: Dissclosure of Sold & Booked Inventory.pdf5 Sep 2025
Form 1File: Form 1.pdf7 Aug 2025
Form 2File: Form 2.pdf7 Aug 2025
Form 3File: Form 3 Phase 2 Q4.pdf7 Aug 2025
Disclosure of Sold and Booked InventoryFile: Form 3 Phase 2 Q4.pdf7 Aug 2025
Form 1File: Form 1.pdf7 Aug 2025
Form 2File: Form 2.pdf7 Aug 2025
Form 3File: Phase II Q 1 Form 3.pdf7 Aug 2025
Disclosure of Sold and Booked InventoryFile: Phase II Q 1 Form 3.pdf7 Aug 2025
Form 1File: Form 1 Q3 Phase2.pdf22 Jul 2025
Form 2File: Form 2.pdf22 Jul 2025
Form 3File: Aakashganga phase 2 Q3 Form 3.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: Aakashganga phase 2 Q3 Form 3.pdf22 Jul 2025
Form 1File: Form 1 Q3 Phase2.pdf22 Jul 2025
Form 2File: Form 2.pdf22 Jul 2025
Form 3File: Aakashganga phase 2 Q3 Form 3.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: Aakashganga phase 2 Q3 Form 3.pdf22 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf28 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf28 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf28 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf28 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf28 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf28 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf28 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf28 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf28 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf12 Jun 2024
Commencement Certificates / NA Order for plotted developmentFile: Mail Reply.pdf29 Jan 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf15 Jan 2024
Declaration about Commencement CertificateFile: format D.pdf2 Jan 2024
Declaration about Commencement CertificateFile: format D.pdf4 Dec 2023
Layout approvalFile: Building Layout.pdf20 Nov 2023
Copy of Layout Approval (in case of layout)File: Building Layout.pdf20 Nov 2023
Other - TechnicalFile: Plinth Completion Certificate.pdf6 Nov 2023
Copy of the legal title reportFile: GUT NO 20 NAKSHATRAWADI.pdf9 Oct 2023
Deviation Report with respect to Allotment letterFile: deviation wrt allotment letter.pdf9 Oct 2023
Deviation Report with respect to model copy of AgreementFile: deviation wrt model copy of agreement.pdf9 Oct 2023
CERSAI detailsFile: CERSAI Report.pdf4 Oct 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: bank-signed.pdf4 Oct 2023
Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to Finance (1).pdf25 Sep 2023
Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Finance (1).pdf25 Sep 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separte bank account.pdf25 Sep 2023
Declaration in FORM BFile: Declaration form B.pdf24 Sep 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest.pdf24 Sep 2023
Building plan approvalFile: 6Building Plan Approval _ NA Order for plotted development.pdf21 Sep 2023
PAN CardFile: 1PAN.pdf21 Sep 2023
Copy of the legal title reportFile: 2Legal title report_compressed.pdf21 Sep 2023
Building Plan Approval / NA Order for plotted developmentFile: 6Building Plan Approval _ NA Order for plotted development.pdf21 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecture Certificate (1).pdf21 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate _compressed.pdf21 Sep 2023
CERSAI detailsFile: 12CERSAI Search Report.pdf21 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed.pdf21 Sep 2023
Proforma of Agreement for saleFile: ATS.pdf21 Sep 2023
Proforma of Allotment letterFile: Allotment Letter.pdf21 Sep 2023

How this compares with Aurangabad

58%of this project is bookeddistrict median 6%
14%of Aurangabad projects moved their completion datethis one moved by 16 months
32%of Aurangabad registrations have lapsed or been cancelledthis one is on the register

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep Aakash Ganga Phase II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mouje-Nakshtrawadi1,400+ in Aurangabad

2 kmAakash Ganga Phase IICompleted 4Lapsed / revoked 7Other 12Dot size: filed unitsN

Filed coordinates, straight-line distance. 23 registered projects within 2 km.

Builder: Aakash Ganga Developers

Aakash Ganga Developers has 3 registrations on MahaRERA, including Aakash Ganga Phase I and Aakash Ganga Phase II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What are my rights if Aakash Ganga Phase II is delayed beyond 21 Feb 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Aakash Ganga Phase II?

The registered promoter entity is Aakash Ganga Developers, a partnership as per the filing. Its GSTIN 27AALFA5173F1ZF can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Aakash Ganga Phase II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Aakash Ganga Phase II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Aakash Ganga Phase II?

The professionals named in the filing: Architect: SATYAM B JADHAV; Engineer: Ravindra Bhabhulay; Chartered Accountant: CA Santosh Garud; Chartered Accountant: Sunil Salunke. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Aakash Ganga Phase II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Aakash Ganga Phase II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Aakash Ganga Phase II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.