Home / Browse projects / Aaiji Crystal Phase II

Registered No litigation declared Residential / Group Housing project

Aaiji Crystal Phase II

By AAIJI DEVELOPERS

RG-MH-18844 · RERA P52100077661 · Last updated on MahaRERA portal: 3 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 2 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Oct 2026Possession promisedmoved 6 months from the original
8 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 95%
86 of 120Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 118 documents Report an error

Aaiji Crystal Phase II is a Residential / Group Housing project by AAIJI DEVELOPERS in pune, 411015, registered with MahaRERA as P52100077661 on 17 Oct 2024. Possession is promised by 1 Oct 2026. The completion date has moved by 6 months from the original filing. 34 of the 120 units on this registration are recorded sold or booked, and 8 of 22 construction stages are filed complete.

At a glance

Project

  • NameAaiji Crystal Phase II
  • TypeResidential / Group Housing
  • Location
    • Tingre Nagar
    • pune
    • 411015
  • Pincode411015
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100077661
  • ReraGenie IDRG-MH-18844

Builder

  • NameAAIJI DEVELOPERS
  • Entity typePartnership
  • GSTIN27AAOFA2448J1Z7
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersHemant Jiwaram Choudhary, JIWARAM MAGAJI CHOUDHARY, SURESH JIWARAM CHOUDHARY
  • Other registrations8 more →
  • Completed3 of 9
  • No longer live3 lapsed, de-registered or revoked
  • Past their filed date2
  • Declared earlier projects2 →

Key dates

this monthRegisteredOct 2024First promiseApr 2026Revised toOct 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Oct 2024
  • Promised completion1 Oct 2026
  • Revised completionRevised to 1 Oct 2026 (originally 1 Apr 2026)
  • Buildings2 building records
  • Documents filed118 files

Current status

28%34 of 120 units booked
71.3%Work done, per cost certificate

Figures as on 3 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building BNA181560060
Building CNA181560060

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 3 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 95%.

Building B72%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Building C65%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises25%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%

Progress on shared amenities15

As on 3 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes95%
Landscaping & Tree PlantingYes95%
Street LightingYes80%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes90%
Water conservation /Rain water harvestingYes90%
Energy managemcntYes80%
Fire protection and fire safety requirementsYes85%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed195

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots195
Closed/Covered195
BuildingClosed/CoveredTotal
Building B9090
Building C105105

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,478 sq m
Land owned byNot the promoter
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on14 Jul 2025
LandownerVillageDistrict
Mangesh Vitthalrao DhadgePune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI14000.0
Proposed, not sanctioned12,293 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchICICI Bank Ltd., Sunanda Apartment, Vishrantwadi, Pune, Maharashtra.411015
Estimated costRs 36.56 cr
Cost incurredRs 26.06 cr
Work done71.29%
BuildingWingEstimatedIncurred
Building BNARs 16.25 crRs 14.00 cr
Building CNARs 16.25 crRs 12.00 cr
-NARs 4.06 crRs 6.33 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSOMNATH KERUR
EngineerMr Kanhu Katke
EngineerNitin Ovhal
Chartered AccountantPatel & Sharma
Chartered AccountantAgarwal Sarawgi and Associates Chartered Accountant
PartnerRole in project
AAIJI DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA01042620515Apr 2026 → Oct 2026

Reason as filed by the promoterThe project commenced post to the outbreak of the COVID-19 pandemic. However, from March 2020 to February 2022, construction activities were severely affected due to nationwide lockdowns, movement restrictions, and mandatory safety protocols. The pandemic caused widespread disruption in the availability of skilled and unskilled labour, as well as in the supply chain for construction materials and equipment. These constraints resulted in prolonged inactivity and slow progress on site. Despite these unprecedented conditions, continuous efforts were made to sustain limited operations and mitigate

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Oct 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Mar 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Dec 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Aug 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed118

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 118 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf3 Aug 2026
Withdrawal Update Form 2File: Aaiji Crystal Phase II Eng From 2 June-26.pdf3 Aug 2026
Withdrawal Update Form 3File: CAFrom3_Signed_compressed.pdf3 Aug 2026
Withdrawal Update Form 1File: ARCHITECTS CERTIFICATE AAIJI CRYSTAL PHASE II.pdf4 Jul 2026
Withdrawal Update Form 2File: FORM 2 ENGINEER CERTIFICATE AAIJI CRYSTAL PHASE II.pdf4 Jul 2026
Withdrawal Update Form 3File: FORM 3 CA CERTIFICATE AAIJI CRYSTAL PHASE II Compressed.pdf4 Jul 2026
Layout approvalFile: 00 Layout Plan.pdf30 Mar 2026
Withdrawal Update Form 1File: Aaiji Crystal Phase II Form 1 ArchitectCertificate 10-01-2026.pdf13 Jan 2026
Withdrawal Update Form 2File: Aaiji Crystal Phase II Form 2 Engineer Certificate 10-01-2026.pdf13 Jan 2026
Withdrawal Update Form 3File: Aaiji Crystal Phase II from 3 CA Certificate dt 10-01-2026.pdf13 Jan 2026
Building plan approvalFile: Aaiji Crystal Basement 2 Parking No 2-10 1156-25 Dt 30-06-25.pdf1 Dec 2025
Building plan approvalFile: Aaiji Crystal Ground parking Plan No 3-10 1156-25 Dt 30-06-25.pdf1 Dec 2025
Building plan approvalFile: Aaiji Crystal Typical Floor Plan No 4-10 1156-25 Dt 30-06-25.pdf1 Dec 2025
Building plan approvalFile: Aaiji Crystal Floor Plan No 5-10 1156-25 Dt 30-06-25.pdf1 Dec 2025
Building plan approvalFile: Aaiji Crystal Floor Plan No 6-10 1156-25 Dt 30-06-25.pdf1 Dec 2025
Building plan approvalFile: Aaiji Crystal Wing B and C Plan No 8-10 1156-25 Dt 30-06-25.pdf1 Dec 2025
Form 2A (FY 2024-2025)File: Aaiji Crystal Phase II Form 2A QAC Engineer Certificate Format F.Y. 24-25.pdf28 Nov 2025
Form 5 (FY 2024-2025)File: Aaiji Crystal Phase II From 5.pdf24 Nov 2025
Withdrawal Update Form 1File: Form 1.pdf21 Nov 2025
Withdrawal Update Form 2File: Form 2.pdf21 Nov 2025
Withdrawal Update Form 3File: Form 3 Ph II Sep 25 Revised.pdf21 Nov 2025
Withdrawal Update Form 1File: Form 1.pdf31 Oct 2025
Withdrawal Update Form 2File: Form 2.pdf31 Oct 2025
Withdrawal Update Form 3File: Form 3_Compressed.pdf31 Oct 2025
Form 1File: 3 Aaiji Crystal Phase I I Architect certificate March-2025.pdf17 Oct 2025
Form 2File: 1 Aaiji Crystal Phase II Form 2 Engineer Certificate Format 31-03-25.pdf17 Oct 2025
Form 3File: 2 Aaiji Crystal Phase II Form 3 CA Certificate Format 31-03-25 _organized.pdf17 Oct 2025
Disclosure of Sold and Booked InventoryFile: 4 Aaiji Crystal Phase II RERA Sold and Unsold B Buil.pdf17 Oct 2025
Withdrawal Update Form 1File: Aaiji Crystal Phase I I Architect certificate Ph II June-2025.pdf24 Sep 2025
Withdrawal Update Form 1File: Aaiji Crystal Phase I I Architect certificate Ph II June-2025.pdf24 Sep 2025
Withdrawal Update Form 2File: Aaiji Crystal Phase II Form 2 Engineer Certificate 30-06-25.pdf24 Sep 2025
Withdrawal Update Form 2File: Aaiji Crystal Phase II Form 2 Engineer Certificate 30-06-25_Revised.pdf24 Sep 2025
Withdrawal Update Form 3File: Form 3 Ph II June 25 Organized Uploaded.pdf24 Sep 2025
Withdrawal Update Form 3File: Form 3 Ph II June 25 Organized Uploaded.pdf24 Sep 2025
Layout approvalFile: Aaiji Crystal Revised Plan No 1-10 1156-25 Dt 30-06-25.pdf5 Aug 2025
Building plan approvalFile: Aaiji Crystal Revised Plan No 2-10 1156-25 Dt 30-06-25.pdf5 Aug 2025
Building plan approvalFile: Aaiji Crystal Revised Plan No 3-10 1156-25 Dt 30-06-25.pdf5 Aug 2025
Building plan approvalFile: Aaiji Crystal Revised Plan No 4-10 1156-25 Dt 30-06-25.pdf5 Aug 2025
Building plan approvalFile: Aaiji Crystal Revised Plan No 5-10 1156-25 Dt 30-06-25.pdf5 Aug 2025
Building plan approvalFile: Aaiji Crystal Revised Plan No 6-10 1156-25 Dt 30-06-25.pdf5 Aug 2025
Building plan approvalFile: Aaiji Crystal Revised Plan No 7-10 1156-25 Dt 30-06-25.pdf5 Aug 2025
Building plan approvalFile: Aaiji Crystal Revised Plan No 8-10 1156-25 Dt 30-06-25.pdf5 Aug 2025
Building plan approvalFile: Aaiji Crystal Revised Plan No 9-10 1156-25 Dt 30-06-25.pdf5 Aug 2025
Building plan approvalFile: Aaiji Crystal Revised Plan No 10-10 1156-25 Dt 30-06-25.pdf5 Aug 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aaiji Crystal Phase II Form 3 CA Certificate Format 31-03-25 _organized.pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aaiji Crystal Phase II Form 2 Engineer Certificate Format 31-03-25.pdf18 Apr 2025
Disclosure of sold/ booked inventoryFile: Aaiji Crystal Phase II RERA Sold and Unsold B Buil.pdf18 Apr 2025
Disclosure of sold/ booked inventoryFile: Aaiji Crystal Phase II RERA Sold and Unsold C Buil.pdf18 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Aaiji Crystal Phase II Form 2A QAC Engineer Certificate Format.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aaiji Crystal Phase II Architect certificate Dec-24 .pdf24 Jan 2025
Disclosure of sold/ booked inventoryFile: Dec 2024 (1).pdf24 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aaiji Crystal Phase II Architect certificate Dec-24 .pdf24 Jan 2025
Disclosure of sold/ booked inventoryFile: Dec 2024 (1).pdf24 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aaiji Crystal Phase II Architect certificate Dec-24 .pdf24 Jan 2025
Disclosure of sold/ booked inventoryFile: Dec 2024 (1).pdf24 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aaiji Crystal Phase II Architect certificate Dec-24 .pdf24 Jan 2025
Disclosure of sold/ booked inventoryFile: Dec 2024 (1).pdf24 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aaiji Crystal Phase II Form 2 Engineer Certificate Format 31-12-24 .pdf23 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aaiji Crystal Phase II Form 3 CA Certificate Format 31-12-24 .pdf23 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aaiji Crystal Phase II Form 2 Engineer Certificate Format 31-12-24 .pdf23 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aaiji Crystal Phase II Form 3 CA Certificate Format 31-12-24 .pdf23 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aaiji Crystal Phase II Form 3 CA Certificate Format 31-12-24 .pdf23 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aaiji Crystal Phase II Form 2 Engineer Certificate Format 31-12-24 .pdf23 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aaiji Crystal Phase II Form 3 CA Certificate Format 31-12-24 .pdf23 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aaiji Crystal Phase II Form 2 Engineer Certificate Format 31-12-24 .pdf23 Jan 2025
Other - LegalFile: Landowner Declaration with Sign Latest.pdf16 Oct 2024
Other - FinanceFile: Landowner Declaration with Area Share Final.pdf16 Oct 2024
Other - TechnicalFile: CC verification latest.pdf14 Oct 2024
Copy of the legal title reportFile: Aaiji Crystal Phase II RERA Revised Title Search Report Dt 25-09-2024 .pdf6 Oct 2024
Proforma of Allotment letterFile: Model Form of Allotment Letter.pdf6 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf6 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - final.pdf6 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 signed Latest.pdf6 Oct 2024
Other - LegalFile: Landowner Declaration with Area Share Final.pdf6 Oct 2024
Other - LegalFile: Form B LO.pdf6 Oct 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf6 Oct 2024
Other - FinanceFile: Landowner Declaration with Sign Latest.pdf6 Oct 2024
Other - TechnicalFile: 1 Highlighted Final.pdf6 Oct 2024
Other - TechnicalFile: Final Order 50.pdf6 Oct 2024
Proforma of Agreement for saleFile: Model Agreement For Sale - Latest.pdf6 Oct 2024

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SOYAL PALACELOHEGAON31CompletedFeb 2017Feb 2017
AAIJI PALACESR NO 36-2-2 TINGRE NAGAR AIRPORT ROAD55CompletedJun 2016Jun 2016

Keep Aaiji Crystal Phase II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near pune

2 kmAaiji Crystal Phase IICompleted 11Lapsed / revoked 13Other 8Dot size: filed unitsN

Filed coordinates, straight-line distance. 32 registered projects within 2 km.

Builder: AAIJI DEVELOPERS

AAIJI DEVELOPERS has 9 registrations on MahaRERA, including AAIJI DHAM BUILDING B and AAIJI DHAM BUILDING A. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record.

Frequently asked questions

What are my rights if Aaiji Crystal Phase II is delayed beyond 1 Oct 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Aaiji Crystal Phase II?

The registered promoter entity is AAIJI DEVELOPERS, a partnership as per the filing. Its GSTIN 27AAOFA2448J1Z7 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Aaiji Crystal Phase II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Aaiji Crystal Phase II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Aaiji Crystal Phase II?

The professionals named in the filing: Architect: SOMNATH KERUR; Engineer: Mr Kanhu Katke; Engineer: Nitin Ovhal; Chartered Accountant: Patel & Sharma; Chartered Accountant: Agarwal Sarawgi and Associates Chartered Accountant. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Aaiji Crystal Phase II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Aaiji Crystal Phase II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Aaiji Crystal Phase II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.