ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / AAIJI CRYSTAL PHASE I

Registered No litigation declared Residential / Group Housing project

AAIJI CRYSTAL PHASE I

By AAIJI DEVELOPERS

RG-MH-53787 · RERA P52100046177 · Last updated on MahaRERA portal: 2 Jun 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • All 2 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Oct 2026Possession promisedmoved 6 months from the original
8 of 22Construction stages doneacross 2 buildings; furthest along: Staircases, 90%
1Complaints at MahaRERAon this registration
Jump to the 144 documents Report an error

AAIJI CRYSTAL PHASE I is a Residential / Group Housing project by AAIJI DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100046177 on 20 Jun 2022. Possession is promised by 1 Oct 2026. The completion date has moved by 6 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameAAIJI CRYSTAL PHASE I
  • TypeResidential / Group Housing
  • Location
    • Tingre Nagar
    • WAGHOLI
    • Haveli
    • Pune
    • 411015
  • Pincode411015
  • RERA no.P52100046177
  • ReraGenie IDRG-MH-53787

Builder

  • NameAAIJI DEVELOPERS
  • Entity typePartnership
  • GSTIN27AAOFA2448J1Z7
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersHemant Jiwaram Choudhary, JIWARAM MAGAJI CHOUDHARY, SURESH JIWARAM CHOUDHARY
  • Other registrations8 more →
  • Completed3 of 9
  • No longer live3 lapsed, de-registered or revoked
  • Past their filed date2
  • Declared earlier projects2 →

Key dates

this monthRegisteredJun 2022First promiseApr 2026Revised toOct 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on20 Jun 2022
  • Promised completion1 Oct 2026
  • Revised completionRevised to 1 Oct 2026 (originally 1 Apr 2026)
  • Buildings2 building records
  • Documents filed144 files

Current status

97.1%Work done, per cost certificate

Figures as on 2 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WingNA160000
D WIng - MHADANA100000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 2 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 90%.

A Wing75%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
D WIng - MHADA56%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.65%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 2 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes75%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes25%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes90%
Water conservation /Rain water harvestingYes60%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes75%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed119

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots119
Closed/Covered119
BuildingClosed/CoveredTotal
A Wing104104
D WIng - MHADA1515

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,006 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Declared on25 Sep 2024
LandownerVillageDistrict
Mangesh DhadageLOHGAONPune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI16365.32
Proposed, not sanctioned14,465 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVishrantwadi, Pune-411015
Estimated costRs 49.47 cr
Cost incurredRs 48.03 cr
Work done97.1%
BuildingWingEstimatedIncurred
A WingNARs 40.70 crRs 39.89 cr
-NARs 5.37 crRs 4.82 cr
D WIng - MHADANARs 3.40 crRs 3.33 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShirish Dasnurkar & Associates
ArchitectSomanth I Kerur
EngineerMr Kanhu Katke
EngineerNitin Ananda Ovhal
Chartered AccountantPatel & Sharma
Chartered AccountantAnuj Sushil Agrawal
Chartered AccountantAgarwal Sarawgi and Associates Chartered Accountant
PartnerRole in project
AAIJI DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA17022619882Apr 2026 → Oct 2026

Reason as filed by the promoter1. Impact of the COVID-19 Pandemic The project commenced post to the outbreak of the COVID-19 pandemic. However, from March 2020 to February 2022, construction activities were severely affected due to nationwide lockdowns, movement restrictions, and mandatory safety protocols. The pandemic caused widespread disruption in the availability of skilled and unskilled labour, as well as in the supply chain for construction materials and equipment. These constraints resulted in prolonged inactivity and slow progress on site. Despite these unprecedented conditions, continuous efforts were made to sust

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12603263NITIN YASHWANT GAIKWADAAIJI DEVELOPERS31/05/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Jun 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Aug 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Aug 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Jun 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed144

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 144 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: ARCHITECTS CERTIFICATE AAIJI CRYSTAL PHASE I.pdf2 Jun 2026
Withdrawal Update Form 2File: FORM 2 ENGINEER CERTIFICATE AAIJI CRYSTAL PHASE I.pdf2 Jun 2026
Withdrawal Update Form 3File: Form 3 Phase I Mar 26.pdf2 Jun 2026
Withdrawal Update Form 1File: Aaiji Crystal Phase I Form 1 ArchitectCertificate 10-01-2026.pdf16 Feb 2026
Withdrawal Update Form 2File: Aaiji Crystal Phase I Form 2 Engineer Certificate 10-01-2026.pdf16 Feb 2026
Withdrawal Update Form 3File: Aaiji Crystal Phase I from 3 CA Certificate dt 10-01-2026.pdf16 Feb 2026
Form 1File: 5 Mar 2023 (Form 1).pdf14 Feb 2026
Form 2File: Form 2.pdf14 Feb 2026
Form 3File: 5 Mar 2023 (Form 3).pdf14 Feb 2026
Disclosure of Sold and Booked InventoryFile: 3 Mar 2023 Disclosure of sold_ booked inventory.pdf14 Feb 2026
Form 1File: 6 June 2023 (Form 1).pdf14 Feb 2026
Form 2File: Form 2.pdf14 Feb 2026
Form 3File: 6 June 2023 (Form 3).pdf14 Feb 2026
Disclosure of Sold and Booked InventoryFile: 4 June 2023 Disclosure of sold_ booked inventory.pdf14 Feb 2026
Form 1File: 7 Sep 2023 (Form 1).pdf14 Feb 2026
Form 2File: Form 2.pdf14 Feb 2026
Form 3File: 7 Sec 2023 (Form 3).pdf14 Feb 2026
Disclosure of Sold and Booked InventoryFile: 5 Sec 2023 Disclosure of sold_ booked inventory.pdf14 Feb 2026
Form 1File: 8 Dec 2023 (Form 1).pdf14 Feb 2026
Form 2File: Form 2.pdf14 Feb 2026
Form 3File: 8 Dec 2023 (Form 3).pdf14 Feb 2026
Disclosure of Sold and Booked InventoryFile: 2 DEc 2023 Disclosure of sold_ booked inventory.pdf14 Feb 2026
Form 1File: 9 mar 2024 (Form 1).pdf14 Feb 2026
Form 2File: Form 2.pdf14 Feb 2026
Form 3File: 9 Mar 2024 Form 3).pdf14 Feb 2026
Disclosure of Sold and Booked InventoryFile: 7 Mar 2024 Disclosure of sold_ booked inventory.pdf14 Feb 2026
Form 1File: Form 1.pdf14 Feb 2026
Form 2File: Form 2.pdf14 Feb 2026
Form 3File: Form 3.pdf14 Feb 2026
Disclosure of Sold and Booked InventoryFile: Final Sold unsold.pdf14 Feb 2026
Form 1File: 13 Mar- 2025 (Form 1).pdf12 Feb 2026
Form 2File: 7Mar 2025 (Form 2).pdf12 Feb 2026
Form 3File: 14 Mar - 2025 (Form 3).pdf12 Feb 2026
Disclosure of Sold and Booked InventoryFile: 12 Mar - 2025 Disclosure of sold_ booked inventory.pdf12 Feb 2026
Form 1File: 12 Dec-2024 (Form 1).pdf12 Feb 2026
Form 2File: 6DEc 2024 Form 2).pdf12 Feb 2026
Form 3File: 13 Dec - 2024 (Form 3).pdf12 Feb 2026
Disclosure of Sold and Booked InventoryFile: 11 Dec 2024 Disclosure of sold_ booked inventory.pdf12 Feb 2026
Form 1File: 11 Sep 2024 (Form 1).pdf12 Feb 2026
Form 2File: 5 Sep 2024(Form 2).pdf12 Feb 2026
Form 3File: 12 Sep 2024 (Form 3).pdf12 Feb 2026
Disclosure of Sold and Booked InventoryFile: 10 sep 2024 Disclosure of sold_ booked inventory.pdf12 Feb 2026
Form 1File: 10 June 2024 (Form 1).pdf12 Feb 2026
Form 2File: Aaiji Crystal Phase I From 2 rera Engineer certificate signed.pdf12 Feb 2026
Form 3File: 11 June 2024 (Form 3).pdf12 Feb 2026
Disclosure of Sold and Booked InventoryFile: 9 June 2024 Disclosure of sold_ booked inventory.pdf12 Feb 2026
Form 1File: 2 Sep 2022 (Form 1).pdf12 Feb 2026
Form 2File: 2 Sep 2022 (Form 2).pdf12 Feb 2026
Form 3File: 3 Sec 2022 (Form 3).pdf12 Feb 2026
Disclosure of Sold and Booked InventoryFile: 1 Sep 2022 Disclosure of sold_ booked inventory.pdf12 Feb 2026
Form 1File: 4Dec 2022 (Form 1).pdf12 Feb 2026
Form 2File: 3 Dec 2022 (Form 2).pdf12 Feb 2026
Form 3File: 4 Dec 2022 (Form 3).pdf12 Feb 2026
Disclosure of Sold and Booked InventoryFile: sold-unsold.pdf12 Feb 2026
Form 2A (FY 2022-2023)File: 1 (Form 2A FY 2022-23).pdf12 Feb 2026
Form 2A (FY 2023-2024)File: Final Form 2a 23-24.pdf12 Feb 2026
Form 5 (FY 2022-2023)File: Form 5 2022-23.pdf12 Feb 2026
Form 5 (FY 2023-2024)File: Form 5 2023-24.pdf12 Feb 2026
Withdrawal Update Form 1File: Aaiji Crystal Phase I Form 1 ArchitectCertificate 10-01-2026.pdf13 Jan 2026
Withdrawal Update Form 2File: Aaiji Crystal Phase I Form 2 Engineer Certificate 10-01-2026.pdf13 Jan 2026
Withdrawal Update Form 3File: Form 3_Compressed.pdf13 Jan 2026
Form 2A (FY 2024-2025)File: Aaiji Crystal Phase I Form 2A QAC Engineer Certificate Format F.Y. 24-25.pdf28 Nov 2025
Form 5 (FY 2024-2025)File: Aaiji Crystal Phase I From 5.pdf24 Nov 2025
Withdrawal Update Form 1File: Form1.pdf31 Oct 2025
Withdrawal Update Form 2File: Form 2.pdf31 Oct 2025
Withdrawal Update Form 3File: Form 3_Compressed.pdf31 Oct 2025
Layout approvalFile: Aaiji Crystal Revised Plan No 1-10 1156-25 Dt 30-06-25.pdf5 Aug 2025
Building plan approvalFile: Aaiji Crystal Revised Plan No 2-10 1156-25 Dt 30-06-25.pdf5 Aug 2025
Building plan approvalFile: Aaiji Crystal Revised Plan No 3-10 1156-25 Dt 30-06-25.pdf5 Aug 2025
Building plan approvalFile: Aaiji Crystal Revised Plan No 4-10 1156-25 Dt 30-06-25.pdf5 Aug 2025
Building plan approvalFile: Aaiji Crystal Revised Plan No 5-10 1156-25 Dt 30-06-25.pdf5 Aug 2025
Building plan approvalFile: Aaiji Crystal Revised Plan No 6-10 1156-25 Dt 30-06-25.pdf5 Aug 2025
Building plan approvalFile: Aaiji Crystal Revised Plan No 7-10 1156-25 Dt 30-06-25.pdf5 Aug 2025
Building plan approvalFile: Aaiji Crystal Revised Plan No 8-10 1156-25 Dt 30-06-25.pdf5 Aug 2025
Building plan approvalFile: Aaiji Crystal Revised Plan No 9-10 1156-25 Dt 30-06-25.pdf5 Aug 2025
Building plan approvalFile: Aaiji Crystal Revised Plan No 10-10 1156-25 Dt 30-06-25.pdf5 Aug 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Aaiji Crystal Phase I Form 3 CA Certificate Format 31-03-25 .pdf18 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Aaiji Crystal Phase I Form 2 Engineer Certificate Format 31-03-25.pdf18 Apr 2025
Disclosure of sold/ booked inventoryFile: Aaiji Crystal Phase I RERA Sold and Unsold Mar-2025 (1).pdf18 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Aaiji Crystal Phase I Form 2A QAC Engineer Certificate Format.pdf18 Apr 2025

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
SOYAL PALACELOHEGAON31CompletedFeb 2017Feb 2017
AAIJI PALACESR NO 36-2-2 TINGRE NAGAR AIRPORT ROAD55CompletedJun 2016Jun 2016

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 6 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep AAIJI CRYSTAL PHASE I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Tingre Nagar13,700+ in Pune

Builder: AAIJI DEVELOPERS

AAIJI DEVELOPERS has 9 registrations on MahaRERA, including AAIJI DHAM BUILDING B and AAIJI DHAM BUILDING A. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if AAIJI CRYSTAL PHASE I is delayed beyond 1 Oct 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AAIJI CRYSTAL PHASE I?

The registered promoter entity is AAIJI DEVELOPERS, a partnership as per the filing. Its GSTIN 27AAOFA2448J1Z7 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AAIJI CRYSTAL PHASE I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against AAIJI CRYSTAL PHASE I?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for AAIJI CRYSTAL PHASE I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AAIJI CRYSTAL PHASE I?

The professionals named in the filing: Architect: Shirish Dasnurkar & Associates; Architect: Somanth I Kerur; Engineer: Mr Kanhu Katke; Engineer: Nitin Ananda Ovhal; Chartered Accountant: Patel & Sharma; Chartered Accountant: Anuj Sushil Agrawal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AAIJI CRYSTAL PHASE I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AAIJI CRYSTAL PHASE I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AAIJI CRYSTAL PHASE I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.