ReraGenieLog inGet a buyer report

Home / Browse projects / Aurangabad, Maharashtra / A CUBE RESIDENCY

Registration lapsed No litigation declared Residential / Group Housing project

A CUBE RESIDENCY

By MOHD ARIF HAJI ABOBAKAR TIKKI

RG-MH-41146 · RERA P51500027618 · Last updated on MahaRERA portal: 15 Apr 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 19 months past the filed date
  • Completion date moved by 11 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Mar 2025Possession promised19 months past this date
20 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 60 documents Report an error

A CUBE RESIDENCY is a Residential / Group Housing project by MOHD ARIF HAJI ABOBAKAR TIKKI in Aurangabad, Maharashtra, registered with MahaRERA as P51500027618 on 23 Dec 2020. Possession was promised by 31 Mar 2025 and is now 19 months past that date. The completion date has moved by 11 months from the original filing.

At a glance

Project

  • NameA CUBE RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • Plot No 170
    • 171 and 172
    • Motiwala Nagar
    • Aurangabad (M Corp.)
    • Aurangabad
    • 431001
  • Pincode431001
  • RERA no.P51500027618
  • ReraGenie IDRG-MH-41146

Builder

  • NameMOHD ARIF HAJI ABOBAKAR TIKKI
  • Entity typeIndividual

Key dates

19 months past promisethis monthRegisteredDec 2020First promiseApr 2024Revised toMar 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on23 Dec 2020
  • Promised completion31 Mar 2025
  • Revised completionRevised to 31 Mar 2025 (originally 30 Apr 2024)
  • Buildings2 building records
  • Documents filed60 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A CUBE RESIDENCYNA50000
A CUBE RESIDENCYNA30000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 15 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

A CUBE RESIDENCY91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
A CUBE RESIDENCY91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 15 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed22

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots22
Closed/Covered22
BuildingClosed/CoveredTotal
A CUBE RESIDENCY1212
A CUBE RESIDENCY1010

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,080 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1118.55
Proposed, not sanctioned1,119 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCIDCO AURANGABAD

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMD YUNUS & ASSOCIATE
EngineerMD YUNUS & ASSOCIATE
Chartered AccountantCA YASH NAGAR
PartnerRole in project
MOHD ARIF HAJI ABOBAKAR TIKKI-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51500019583Apr 2024 → Mar 2025

Reason as filed by the promoterCompletion Certificate not yet received and some units are under construction.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 12 Dec 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Dec 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Dec 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Dec 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed60

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FINAL FORM 1.pdf15 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 UPLOAD.pdf15 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 FINAL.pdf15 Apr 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD UPLOAD_1.pdf15 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A_compressed.pdf15 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 2024-25 Q2.pdf9 Nov 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold 2024-25 Q2.pdf9 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 24-25 Q2.pdf21 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 24-25 Q2.pdf21 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 24-25 Q2.pdf21 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 24-25 Q1.pdf11 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 24-25 Q1.pdf11 Jul 2024
Disclosure of sold/ booked inventoryFile: Dislosure of sold-Unsold Inventory 24-25 Q2.pdf11 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 24-25 Q1.pdf11 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf3 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 _Signed.pdf24 May 2024
Declaration in FORM BFile: Tikki Infra Form B.pdf24 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 20-21_s_m.pdf24 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 22-23_s.pdf24 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 21-22_s.pdf24 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate_1.pdf13 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate_1.pdf13 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quility assurance certificate 2021.pdf13 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Disclosure of sold booked inventory (2).pdf13 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quility assurance certificate 2023.pdf13 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory (2).pdf13 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory.pdf13 Apr 2024
Details of encumbrances concerned to FinanceFile: 1 Encumbarences Merged.pdf30 Mar 2024
Details of encumbrances concerned to LegalFile: 1 Encumbarences Merged.pdf30 Mar 2024
Declaration in FORM BFile: Form B.pdf30 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9 Form 1 Architect Cert.pdf30 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 10 Form 2 Engineer Cert.pdf30 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: 5 Disclosure of Interest.pdf30 Mar 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 6 Seprate Bank Account Declaration.pdf30 Mar 2024
Deviation Report with respect to Allotment letterFile: 3 Deviation Report with respect to Allotment letter ok.pdf30 Mar 2024
Deviation Report with respect to model copy of AgreementFile: 4 Deviation Report with respect to model copy of Agreement ok.pdf30 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_11zon.pdf25 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_11zon.pdf25 Nov 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf25 Nov 2023
Disclosure of sold/ booked inventoryFile: Tikki Infra Sold Unsold pdf_compressed.pdf18 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's certificate_1_compressed.pdf16 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's certificate_1_compressed.pdf16 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's certificate_compressed.pdf16 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's certificate pdf_compressed.pdf16 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf14 Dec 2020
Declaration in FORM BFile: Form B.pdf13 Dec 2020
Building plan approvalFile: Building Plan_compressed.pdf12 Dec 2020
Building plan approvalFile: Building Plan 2_compressed.pdf12 Dec 2020
Layout approvalFile: Final Layout Plan.pdf12 Dec 2020
PAN CardFile: PAN Card.pdf12 Dec 2020
Copy of the legal title reportFile: Search Report 1.pdf12 Dec 2020
Copy of the legal title reportFile: Search Report 2.pdf12 Dec 2020
Copy of the legal title reportFile: Search Report 3.pdf12 Dec 2020
Details of encumbrancesFile: Encumbrances Cert.pdf12 Dec 2020
Copy of Layout Approval (in case of layout)File: Final Layout Plan.pdf12 Dec 2020
Building Plan Approval / NA Order for plotted developmentFile: Building Plan_compressed.pdf12 Dec 2020
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 2_compressed.pdf12 Dec 2020
Commencement Certificates / NA Order for plotted developmentFile: Commencement Cert.pdf12 Dec 2020
Proforma of Allotment letterFile: Agreement_for_Sale_Format.pdf12 Dec 2020
Proforma of Allotment letterFile: proforma_allotment_letter.pdf12 Dec 2020

How this compares with Aurangabad

14%of Aurangabad projects moved their completion datethis one moved by 11 months
32%of Aurangabad registrations have lapsed or been cancelledthis one is among them

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep A CUBE RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Motiwala Nagar1,400+ in Aurangabad

Builder: MOHD ARIF HAJI ABOBAKAR TIKKI

MOHD ARIF HAJI ABOBAKAR TIKKI has 1 registration on MahaRERA, including A CUBE RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What does it mean that A CUBE RESIDENCY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if A CUBE RESIDENCY is delayed beyond 31 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of A CUBE RESIDENCY?

The registered promoter entity is MOHD ARIF HAJI ABOBAKAR TIKKI, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in A CUBE RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for A CUBE RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at A CUBE RESIDENCY?

The professionals named in the filing: Architect: MD YUNUS & ASSOCIATE; Engineer: MD YUNUS & ASSOCIATE; Chartered Accountant: CA YASH NAGAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in A CUBE RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About A CUBE RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save A CUBE RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.