ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / 66 AVENUE A B C BUILDING

Registration lapsed No litigation declared Residential / Group Housing project

66 AVENUE A B C BUILDING

By R R LUNKAD LANDMARKS LLP

RG-MH-27654 · RERA P52100035034 · Last updated on MahaRERA portal: 19 Sep 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 16 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2025Possession promised16 months past this date
28 of 33Construction stages doneacross 3 buildings; furthest along: Sanitary Fittings within the flats /..., 75%
44 of 179Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 121 documents Report an error

66 AVENUE A B C BUILDING is a Residential / Group Housing project by R R LUNKAD LANDMARKS LLP in Pune, Maharashtra, registered with MahaRERA as P52100035034 on 29 Apr 2022. Possession was promised by 30 Jun 2025 and is now 16 months past that date. 135 of the 179 units on this registration are recorded sold or booked, and 28 of 33 construction stages are filed complete.

At a glance

Project

  • Name66 AVENUE A B C BUILDING
  • TypeResidential / Group Housing
  • Location
    • Pimple nilakh Baner Road
    • Near mahadev temple
    • Pimple Nilakh
    • Haveli
    • Pune
    • 411027
  • Pincode411027
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100035034
  • ReraGenie IDRG-MH-27654

Builder

  • NameR R LUNKAD LANDMARKS LLP
  • Entity typeOthers
  • Named personsRAJENDRA RAMANLAL LUNKAD, POOJA AJAY CHOPDA
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

16 months past promisethis monthRegisteredApr 2022PromisedJun 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on29 Apr 2022
  • Promised completion30 Jun 2025
  • Revised completionNone
  • Buildings3 building records
  • Documents filed121 files

Current status

75%135 of 179 units booked
81.4%Work done, per cost certificate

Figures as on 19 Sep 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A BUILDINGNA8630030
B BUILDINGNA151478482
C BUILDINGNA151463467

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 19 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

28 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 75%.

A BUILDING78%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%
B BUILDING100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
C BUILDING100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 19 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes90%
Street LightingYes90%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes75%
Energy managemcntYes75%
Fire protection and fire safety requirementsYes75%
Electrical meter room, sub-station, receiving stationYes75%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed208

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots208
Closed/Covered208
BuildingClosed/CoveredTotal
A BUILDING6565
B BUILDING7878
C BUILDING6565

Land and ownership33

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,969 sq m
Land owned byThe promoter, with other names on the file
Named landowners33
LandownerVillageDistrict
NEMICHAND BHANDARI ASSOCIATES (SPACE PROPERTIES)Chikhali Bk.Pune
HARIBHAU KALURAM SATHEPune (M Corp.)Pune
MANDAKANI HARIBHAU SATHEPune (M Corp.)Pune
YASHODHAN HARIBHAU SATHEPune (M Corp.)Pune
YUVRAJ HARIBHAU SATHEPune (M Corp.)Pune
PRANOTI PRASHANT KOKANEPune (M Corp.)Pune
PRATIMA PRADIP CHANDHAREPune (M Corp.)Pune
RUPALI YASHODHAN SATHEPune (M Corp.)Pune
DNYANOBA KALURAM SATHEPune (M Corp.)Pune
MANGALA DNYANOBA SATHEPune (M Corp.)Pune
PRADIP MANGALA SATHEPune (M Corp.)Pune
PRIYANKA GANESH KALBHORAkurdiPune
PRITAM GANESH JAGTAPPimpale GuravPune
SUDAM KONDIBA KAMATHEPune (M Corp.)Pune
DWARAKABAI SUDAM KAMATHEPune (M Corp.)Pune
BALASAHEB SUDAM KAMATHEPune (M Corp.)Pune
NAINA BALASAHEB KAMATHEPune (M Corp.)Pune
SOHAM BALASAHEB KAMATHEPune (M Corp.)Pune
DILIP SUDAM KAMATHEPune (M Corp.)Pune
HEMA DILIP KAMATHEPune (M Corp.)Pune
ADITYA DILIP KAMATHEPune (M Corp.)Pune
SAYALI DILIP KAMATHEPune (M Corp.)Pune
LAXMAN KONDIBA KAMATHEPune (M Corp.)Pune
KANTA LAXMAN KAMATHEPune (M Corp.)Pune
SANDIP LAXMAN KAMATHEPune (M Corp.)Pune
VAISHALI SANDIP KAMATHEPune (M Corp.)Pune
SANTOSH LAXMAN KAMATHEPune (M Corp.)Pune
SARIKA SANTOSH KAMATHEPune (M Corp.)Pune
MAHESH LAXMAN KAMATHEPune (M Corp.)Pune
SUREKHA MAHESH KAMATHEPune (M Corp.)Pune
SUNANDA SUBHASH KAMATHEPune (M Corp.)Pune
AMOL SUBHASH KAMATHEPune (M Corp.)Pune
SHILPA AMOL KAMATHEPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPIMPRI CHINCHWAD MUNCIPAL CORPORATION
Permissible FSI23709.66
Proposed, not sanctioned9,768 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBHANDARKAR ROAD PUNE
Estimated costRs 48.29 cr
Cost incurredRs 39.29 cr
Work done81.36%
BuildingWingEstimatedIncurred
B BUILDINGNARs 16.65 crRs 13.68 cr
C BUILDINGNARs 16.18 crRs 13.27 cr
A BUILDINGNARs 8.47 crRs 7.09 cr
-NARs 6.99 crRs 5.24 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUNUSUAL SPACES
EngineerASHISH PRAKASH DAHAKE
Chartered AccountantMUTTHA AND LAHOTI CHARTERED ACCOUNTANT
Chartered AccountantMuttha and Lahoti
PartnerRole in project
R R LUNKAD LANDMARKS LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Apr 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Jan 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Jan 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed121

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 121 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: F1 Q1 FY 2024-25 66 Avenue Phase II_compressed.pdf19 Sep 2025
Withdrawal Update Form 1File: F1 Q1 FY 2024-25 66 Avenue Phase II_compressed.pdf19 Sep 2025
Withdrawal Update Form 1File: F1 Q1 FY 2024-25 66 Avenue Phase II_compressed.pdf19 Sep 2025
Withdrawal Update Form 2File: Form 2 66A2 Q1 2024-25 CMP.pdf19 Sep 2025
Withdrawal Update Form 2File: Form 2 66A2 Q1 2024-25 CMP.pdf19 Sep 2025
Withdrawal Update Form 2File: Form 2 66A2 Q1 2024-25 CMP.pdf19 Sep 2025
Withdrawal Update Form 3File: F3 Q1 FY 2024-25 66 Avenue Phase II_compressed.pdf19 Sep 2025
Withdrawal Update Form 3File: F3 Q1 FY 2024-25 66 Avenue Phase II_compressed.pdf19 Sep 2025
Withdrawal Update Form 3File: F3 Q1 FY 2024-25 66 Avenue Phase II_compressed.pdf19 Sep 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3 Q4 FY 2024-25 66 Avenue Phase II_compressed.pdf20 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2 Q4 FY 2024-25 66 Avenue Phase II.pdf20 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3 Q2 FY 2024-25 66 Avenue Phase II.pdf22 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3 Q3 FY 2024-25 66 Avenue Phase II_compressed.pdf22 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1 Q3 FY 2024-25 66 Avenue Phase II.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2 Q3 FY 2024-25 66 Avenue Phase II_compressed.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1 Q2 FY 2024-25 66 Avenue Phase II.pdf29 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2 Q2 FY 2024-25 66 Avenue Phase II.pdf29 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1 Q1 FY 2024-25 66 Avenue Phase II_compressed.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3 Q1 FY 2024-25 66 Avenue Phase II_compressed.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 66A2 Q1 2024-25 CMP.pdf19 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RRLL LLP Form 1.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RRLL LLP Form 2.pdf20 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RRLL LLP Form 2.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RRLL LLP Form 3 COMP.pdf20 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1 Q3 FY 2023-24 66 Avenue Phase II.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2 30102023 2023-24 66 Avenue Phase II.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2 12122023 2023-24 66 Aveneu Phase II.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2 Q3 FY 2023-24 66 Avenue Phase II.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3 301023 2023-24 66 Avenue Phase II_compressed.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3 131223 2023-24 66 Avenue Phase II_compressed.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3 Q3 FY 2023-24 66 Avenue Phase II_compressed.pdf20 Jan 2024
Building plan approvalFile: 66A GROUND.pdf9 Jan 2024
Building plan approvalFile: 66A MEZZ UPPER PARKING.pdf9 Jan 2024
Building plan approvalFile: 66A A BUILDING LGP GP UP TERRACE.pdf9 Jan 2024
Building plan approvalFile: 66A A BUILDING 1 2 3 4 5 6TH PART 2 FLATS.pdf9 Jan 2024
Building plan approvalFile: 66A B BUILDING LGP GROUND 1ST MEZZ FLOOR.pdf9 Jan 2024
Building plan approvalFile: 66A B BUILDING 2,3,5,7,9,11 FLOOR.pdf9 Jan 2024
Building plan approvalFile: 66A B BUILDING 4,6,8,10,12,14 FLOOR.pdf9 Jan 2024
Building plan approvalFile: 66A B BUILDING 13TH FLOOR AND TERRACE.pdf9 Jan 2024
Building plan approvalFile: 66A B BUILDING SECTION.pdf9 Jan 2024
Building plan approvalFile: 66A C BUILDING LGP, GROUND, 1ST MEZZ FLOOR.pdf9 Jan 2024
Building plan approvalFile: 66A C BUILDING 2,3,4,5,6,7,9,10,11,12,14 FLOOR.pdf9 Jan 2024
Building plan approvalFile: 66A C BUILDING 8,13 FLOOR.pdf9 Jan 2024
Building plan approvalFile: 66A C BUILDING SECTION.pdf9 Jan 2024
Layout approvalFile: 66A CC.pdf9 Jan 2024
Building plan approvalFile: 66A LOWER PARKING.pdf9 Jan 2024
Copy of Layout Approval (in case of layout)File: 66A CC.pdf9 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: 66A LOWER PARKING.pdf9 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: 66A GROUND.pdf9 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: 66A MEZZ UPPER PARKING.pdf9 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: 66A A BUILDING LGP GP UP TERRACE.pdf9 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: 66A A BUILDING 1 2 3 4 5 6TH PART 2 FLATS.pdf9 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: 66A B BUILDING LGP GROUND 1ST MEZZ FLOOR.pdf9 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: 66A B BUILDING 2,3,5,7,9,11 FLOOR.pdf9 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: 66A B BUILDING 4,6,8,10,12,14 FLOOR.pdf9 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: 66A B BUILDING 13TH FLOOR AND TERRACE.pdf9 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: 66A B BUILDING SECTION.pdf9 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: 66A C BUILDING LGP, GROUND, 1ST MEZZ FLOOR.pdf9 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: 66A C BUILDING 2,3,4,5,6,7,9,10,11,12,14 FLOOR.pdf9 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: 66A C BUILDING 8,13 FLOOR.pdf9 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: 66A C BUILDING SECTION.pdf9 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1 Q2 FY 2023-24 66 Avenue Phase II.pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2 Q2 2023-24 66 Avenue Phase II.pdf20 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3 Q2 2023-24 66 Avenue Phase II.pdf20 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 2022-23 66 Avenue Phase II.pdf30 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert Q2 2023-24 Phase II (1).pdf29 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Cert Q2 2023-24 Phase II.pdf29 Aug 2023
Layout approvalFile: LAYU.pdf10 Jun 2022
Building plan approvalFile: 1.pdf10 Jun 2022
Building plan approvalFile: 2.pdf10 Jun 2022
Building plan approvalFile: 3.pdf10 Jun 2022
Building plan approvalFile: 4.pdf10 Jun 2022
Building plan approvalFile: 5.pdf10 Jun 2022
Building plan approvalFile: 6.pdf10 Jun 2022
Building plan approvalFile: 7.pdf10 Jun 2022
Building plan approvalFile: 8.pdf10 Jun 2022
Building plan approvalFile: 9.pdf10 Jun 2022
Building plan approvalFile: 10.pdf10 Jun 2022
Copy of Layout Approval (in case of layout)File: LAYU.pdf10 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: 1.pdf10 Jun 2022

How this compares with Pune

75%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep 66 AVENUE A B C BUILDING on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Near mahadev temple13,700+ in Pune

2 km66 AVENUE A B C BUILDINGCompleted 100Lapsed / revoked 38Other 124Dot size: filed unitsN

Filed coordinates, straight-line distance. 262 registered projects within 2 km.

Builder: R R LUNKAD LANDMARKS LLP

R R LUNKAD LANDMARKS LLP has 2 registrations on MahaRERA, including 66 AVENUE and 66 AVENUE A B C BUILDING. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that 66 AVENUE A B C BUILDING shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if 66 AVENUE A B C BUILDING is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of 66 AVENUE A B C BUILDING?

The registered promoter entity is R R LUNKAD LANDMARKS LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in 66 AVENUE A B C BUILDING?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for 66 AVENUE A B C BUILDING?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at 66 AVENUE A B C BUILDING?

The professionals named in the filing: Architect: UNUSUAL SPACES; Engineer: ASHISH PRAKASH DAHAKE; Chartered Accountant: MUTTHA AND LAHOTI CHARTERED ACCOUNTANT; Chartered Accountant: Muttha and Lahoti. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in 66 AVENUE A B C BUILDING?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About 66 AVENUE A B C BUILDING. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save 66 AVENUE A B C BUILDING to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.