Home / Browse projects / Pune, Maharashtra / 45 BANER STREET

Registration lapsed No litigation declared Commercial project

45 BANER STREET

By RAICHANDANI CONSTRUCTIONS AND DEVELOPERS

RG-MH-16100 · RERA P52100025160 · Last updated on MahaRERA portal: 3 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 27 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 8 months
  • 4 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jul 2024Possession promised27 months past this date
7 of 11Construction stages donefurthest along: Internal walls, 90%
1Complaints at MahaRERAon this registration
Jump to the 123 documents Report an error

45 BANER STREET is a Commercial project by RAICHANDANI CONSTRUCTIONS AND DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100025160 on 19 Mar 2020. Possession was promised by 31 Jul 2024 and is now 27 months past that date. The completion date has moved by 8 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • Name45 BANER STREET
  • TypeCommercial
  • Location
    • MAHALUNGE MAIN ROAD
    • OPP DMART
    • MAHALUNGE MAIN ROAD BANER
    • PUNE
    • Baner
    • Haveli
    • Pune
    • 411045
  • Pincode411045
  • RERA no.P52100025160
  • ReraGenie IDRG-MH-16100

Builder

  • NameRAICHANDANI CONSTRUCTIONS AND DEVELOPERS
  • Entity typePartnership
  • GSTIN27AAYFR1876R1ZU
  • PartnersRAJKUMAR DOULATRAM RAICHANDANI, KUNAL RAJKUMAR RAICHANDANI, PRATIK ANIL RAICHANDANI, Karan Prakashlal Raichandani
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

27 months past promisethis monthRegisteredMar 2020First promiseNov 2023Revised toJul 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on19 Mar 2020
  • Promised completion31 Jul 2024
  • Revised completionRevised to 31 Jul 2024 (originally 28 Nov 2023)
  • Buildings1 building record
  • Documents filed123 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
45 BANER STREETNA110000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

45 BANER STREET: 79% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 3 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed178

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots178
Closed/Covered178

Land and ownership8

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,835 sq m
Land owned byThe promoter, with other names on the file
Named landowners8
LandownerVillageDistrict
M/s S. K. BUILDCONPune (M Corp.)Pune
AMAR TATYASAHEB DESAIPune (M Corp.)Pune
GAYATRI AMAR DESAIPune (M Corp.)Pune
RAJVARDHAN AMAR DESAIPune (M Corp.)Pune
PRALHAD MARUTI DESHMUKHPune (M Corp.)Pune
SATISH BABULAL SURANAPune (M Corp.)Pune
SANJAY SHANKARRAO INGALEMumbai CityMumbai City
VIVEK NARU CHAVANMumbai CityMumbai City

Approvals and building plan

Permissible FSI11530.98
Proposed, not sanctioned11,531 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDECCAN GYMKHANA BRANCH PUNE

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVILAS TARWADI
EngineerSiddharth Bharat Sawant
Chartered AccountantSPAK & Co
PartnerRole in project
RAICHANDANI CONSTRUCTIONS AND DEVELOPERS-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100019464Nov 2023 → May 2024

Reason as filed by the promoterThere is delay in obtaining Government approvals (i.e. Completion Certificate) so to comply with the same please allow us the extention till 15/5/2024. There is mismatch in Sold Disclosure, Portal and Form 3 because only the share of Devlopers is disclosed in Form 3.

EXT52100019780Nov 2023 → Jul 2024

Reason as filed by the promoterthere is a delay in obtaining Government Approvals ( ie completion certificate ) so to comply with the same we require extension

EXT52100024456Nov 2023 → Jul 2024

Reason as filed by the promoterthere is delay in obatining Goverment approvals ( ie completetion certificate ). so to comply with the same we required extension.

EXT52100017755Nov 2023 → Mar 2024

Reason as filed by the promoterWe “Raichandani Constructions And Developers” is developing a commercial project 45 BANER STREET, and we were due to complete the project on 28/11/2023. However, due to the COVID-19 pandemic, we faced several challenges that adversely affected the construction activities and the sales of the project. Some of these challenges were: • Lack of availability of labour contractors as many of them migrated back to their native places during the lockdown. • Disruption of supply chain of essential construction materials such as cement, steel, sand, etc. • Poor market condition reduced the demand and sa

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC005000000471295Rohit Dattatray GadsingM/s.Raichandani Constructions and Developers, Through Authorized Partner Mr. Dinesh Raichandi19/07/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Feb 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Dec 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Dec 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Dec 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 19 Dec 2024

Documents filed123

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 123 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 45 baner street FORM 3 Q3 2023-2024.pdf3 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 45 Baner Form 2 Q3.pdf23 Jan 2025
Disclosure of sold/ booked inventoryFile: 45 BANER STREET SOLD - UNSOLD Q3 2024-2025.pdf23 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q3 45 Baner.pdf22 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 45 baner form 3 2024-2025.pdf22 Jan 2025
Declaration in FORM BFile: form b - 45 baner street_compressed.pdf23 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 45 Baner Form 5 23-24.pdf20 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 111 भोगवटा पत्र(1) 09-Oct-2024 15-51-03.pdf19 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_45 Baner Street_Sep24s.pdf7 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 45 B Form 1.pdf30 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 45 B Form 2.pdf30 Oct 2024
Disclosure of sold/ booked inventoryFile: 45 Baner Sold Unsold.pdf28 Oct 2024
Declaration in FORM BFile: FORM B 45 BANER STREET EXTENSION.pdf9 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Scan2024-08-09_164709.pdf9 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 45 BANER FORM 3 Q1 2024-2025.pdf22 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 45 Baner Form 2 Q1 2024-25_compressed.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: 45 Baner Street Sold Unsold Q1 2024-2025_compressed.pdf20 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 45 BANER Q4 FORM 1.pdf3 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 45 BANER STREET FORM 2 Q4 2023-2024.pdf3 Jul 2024
Details of encumbrancesFile: No Encumbrances 45 Baner.pdf20 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 45 BANER FORM 5 Q4 2023-2024.pdf25 Apr 2024
Proforma of Agreement for saleFile: 45 Baner Street RERA draft.pdf24 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 45 baner dec 23.pdf8 Apr 2024
Declaration in FORM BFile: P52100025160_FileName_1.pdf3 Apr 2024
Disclosure of sold/ booked inventoryFile: 45 BANER SOLD -UNSOLD.pdf3 Apr 2024
Declaration about Commencement CertificateFile: FORM B 45 BANER S.pdf16 Mar 2024
Declaration in FORM BFile: FORM B 45 BANER S.pdf16 Mar 2024
Declaration in FORM BFile: Form B of 45 baner Street.pdf26 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 45 baner ca certificate form 3 Q3 2023_compressed.pdf24 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 q3 - 45 baner.pdf8 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 q3 - 45 baner street.pdf8 Jan 2024
Disclosure of sold/ booked inventoryFile: sold booked q3 - 45 baner.pdf8 Jan 2024
Disclosure of sold/ booked inventoryFile: 45 baner sold booked.pdf29 Dec 2023
Disclosure of sold/ booked inventoryFile: 45 baner developer units.pdf15 Dec 2023
Layout approvalFile: HPSC0608_compressed.pdf6 Dec 2023
Building plan approvalFile: HPSC0609_compressed.pdf6 Dec 2023
Building plan approvalFile: HPSC0610_compressed.pdf6 Dec 2023
Building plan approvalFile: HPSC0611_compressed.pdf6 Dec 2023
Building plan approvalFile: HPSC0612_compressed.pdf6 Dec 2023
Building plan approvalFile: HPSC0613_compressed.pdf6 Dec 2023
Copy of Layout Approval (in case of layout)File: HPSC0608_compressed.pdf6 Dec 2023
Building Plan Approval / NA Order for plotted developmentFile: HPSC0609_compressed.pdf6 Dec 2023
Building Plan Approval / NA Order for plotted developmentFile: HPSC0610_compressed.pdf6 Dec 2023
Building Plan Approval / NA Order for plotted developmentFile: HPSC0611_compressed.pdf6 Dec 2023
Building Plan Approval / NA Order for plotted developmentFile: HPSC0612_compressed.pdf6 Dec 2023
Building Plan Approval / NA Order for plotted developmentFile: HPSC0613_compressed.pdf6 Dec 2023
Commencement Certificates / NA Order for plotted developmentFile: 45 Baner Commencement Certificate Of Revised Sanction Plan_compressed.pdf6 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 45 baner form 5 2022-2023_compressed.pdf31 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 45 BANER CA CERTIFICATE Q1 2023-2024.pdf27 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 45 BANER CA CERTIICATE Q2 2023-2024.pdf27 Oct 2023
Disclosure of sold/ booked inventoryFile: SOLD BOOKED 45 BANER Q2.pdf20 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 45 Baner street.pdf18 Oct 2023
Declaration in FORM BFile: 45 baner - form b.pdf13 Oct 2023
Disclosure of sold/ booked inventoryFile: sold booked - 45 baner.pdf27 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A - 45 BANER 2021.pdf18 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A - 45 BANER 2022.pdf18 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A - 45 BANER 2023.pdf18 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 45 baner architect certificate.pdf5 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 45 BANER ENGINEER CERTIFICATE Q1 2023-2024.pdf1 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 45 BANER ARCHITECT CERTIFICATE Q4 2022-2023.pdf29 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 45 Baner Engineer Certificate Q4 2022-2023_compressed.pdf29 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 CA Certificate 45 Baner Street Mar - 23 SC_compressed.pdf29 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q 4 - FY 2019-20 - 45 BANER - ARCHITECT CERTIFICATE.pdf23 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q 4 - FY 2020-21 - 45 BANER - ARCHITEC CERTIFICATE.pdf23 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q 1 - FY 2021-22 - 45 BANER - ARCHITECT CERTIFICATE.pdf23 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q 2 - FY 2021-22 - 45 BANER - ARCHITECT CERTIFICATE.pdf23 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q 1 - FY 2022-23 - 45 BANER - ARCHITCT CERTIFICATE.pdf23 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q 4 - FY 2019-20 - 45 BANER - ENGINEER CERTIFICATE.pdf23 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q 4 - FY 2020-21 - 45 BANER - ENGINEER CERTIFICATE.pdf23 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q 1 - FY 2021-22 - 45 BANER - ENGINEER CERTIFICATE.pdf23 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q 2 - FY 2021-22 - 45 BANER - ENGINEER CERTIFICATE.pdf23 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q 1 - FY 2022-23 - 45 BANER - ENGINEER CERTIFICATE.pdf23 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 45 Baner Mar 20.pdf23 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 45 Baner Mar 21.pdf23 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 45 Baner June 21.pdf23 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4 45 Baner Sept 21.pdf23 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5 CA Certificate 45 Baner Street June 22.pdf23 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERT 45 BANER Q-DEC.pdf8 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGREERING CERT 45-BANER Q-DEC.pdf8 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 45 baner street art cr.pdf16 Mar 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
TEN SQUAREP52100021256BIBVEWADI MUNJERI, LULLANAGAR, Pune34Jun 2019CompletedMar 2022Mar 2022

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 8 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep 45 BANER STREET on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near OPP DMART, MAHALUNGE MAIN ROAD BANER, PUNE13,700+ in Pune

Builder: RAICHANDANI CONSTRUCTIONS AND DEVELOPERS

RAICHANDANI CONSTRUCTIONS AND DEVELOPERS has 3 registrations on MahaRERA, including SWARNA VATIKA and 45 BANER STREET. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that 45 BANER STREET shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if 45 BANER STREET is delayed beyond 31 Jul 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of 45 BANER STREET?

The registered promoter entity is RAICHANDANI CONSTRUCTIONS AND DEVELOPERS, a partnership as per the filing. Its GSTIN 27AAYFR1876R1ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in 45 BANER STREET?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against 45 BANER STREET?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for 45 BANER STREET?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at 45 BANER STREET?

The professionals named in the filing: Architect: VILAS TARWADI; Engineer: Siddharth Bharat Sawant; Chartered Accountant: SPAK & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in 45 BANER STREET?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About 45 BANER STREET. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save 45 BANER STREET to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.