Home / Browse projects / Pune, Maharashtra / 45 BANER STREET
45 BANER STREET
By RAICHANDANI CONSTRUCTIONS AND DEVELOPERS
RG-MH-16100 · RERA P52100025160 · Last updated on MahaRERA portal: 3 Feb 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 27 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 8 months
- 4 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
45 BANER STREET is a Commercial project by RAICHANDANI CONSTRUCTIONS AND DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100025160 on 19 Mar 2020. Possession was promised by 31 Jul 2024 and is now 27 months past that date. The completion date has moved by 8 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- Name45 BANER STREET
- TypeCommercial
- Location
- MAHALUNGE MAIN ROAD
- OPP DMART
- MAHALUNGE MAIN ROAD BANER
- PUNE
- Baner
- Haveli
- Pune
- 411045
- Pincode411045
- RERA no.P52100025160
- ReraGenie IDRG-MH-16100
Builder
- NameRAICHANDANI CONSTRUCTIONS AND DEVELOPERS
- Entity typePartnership
- GSTIN27AAYFR1876R1ZU
- PartnersRAJKUMAR DOULATRAM RAICHANDANI, KUNAL RAJKUMAR RAICHANDANI, PRATIK ANIL RAICHANDANI, Karan Prakashlal Raichandani
- Other registrations2 more →
- Completed1 of 3
- No longer live2 lapsed, de-registered or revoked
- Declared earlier projects2 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on19 Mar 2020
- Promised completion31 Jul 2024
- Revised completionRevised to 31 Jul 2024 (originally 28 Nov 2023)
- Buildings1 building record
- Documents filed123 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| 45 BANER STREET | NA | 11 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 3 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
7 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.
45 BANER STREET: 79% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 30% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 50% |
Progress on shared amenities15
As on 3 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed178
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership8
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| M/s S. K. BUILDCON | Pune (M Corp.) | Pune |
| AMAR TATYASAHEB DESAI | Pune (M Corp.) | Pune |
| GAYATRI AMAR DESAI | Pune (M Corp.) | Pune |
| RAJVARDHAN AMAR DESAI | Pune (M Corp.) | Pune |
| PRALHAD MARUTI DESHMUKH | Pune (M Corp.) | Pune |
| SATISH BABULAL SURANA | Pune (M Corp.) | Pune |
| SANJAY SHANKARRAO INGALE | Mumbai City | Mumbai City |
| VIVEK NARU CHAVAN | Mumbai City | Mumbai City |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VILAS TARWADI |
| Engineer | Siddharth Bharat Sawant |
| Chartered Accountant | SPAK & Co |
| Partner | Role in project |
|---|---|
| RAICHANDANI CONSTRUCTIONS AND DEVELOPERS | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThere is delay in obtaining Government approvals (i.e. Completion Certificate) so to comply with the same please allow us the extention till 15/5/2024. There is mismatch in Sold Disclosure, Portal and Form 3 because only the share of Devlopers is disclosed in Form 3.
Reason as filed by the promoterthere is a delay in obtaining Government Approvals ( ie completion certificate ) so to comply with the same we require extension
Reason as filed by the promoterthere is delay in obatining Goverment approvals ( ie completetion certificate ). so to comply with the same we required extension.
Reason as filed by the promoterWe “Raichandani Constructions And Developers” is developing a commercial project 45 BANER STREET, and we were due to complete the project on 28/11/2023. However, due to the COVID-19 pandemic, we faced several challenges that adversely affected the construction activities and the sales of the project. Some of these challenges were: • Lack of availability of labour contractors as many of them migrated back to their native places during the lockdown. • Disruption of supply chain of essential construction materials such as cement, steel, sand, etc. • Poor market condition reduced the demand and sa
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000471295 | Rohit Dattatray Gadsing | M/s.Raichandani Constructions and Developers, Through Authorized Partner Mr. Dinesh Raichandi | 19/07/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Feb 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 6 Dec 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 6 Dec 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 6 Dec 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 19 Dec 2024
Documents filed123
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 123 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 45 baner street FORM 3 Q3 2023-2024.pdf | 3 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 45 Baner Form 2 Q3.pdf | 23 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: 45 BANER STREET SOLD - UNSOLD Q3 2024-2025.pdf | 23 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q3 45 Baner.pdf | 22 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 45 baner form 3 2024-2025.pdf | 22 Jan 2025 |
| Declaration in FORM BFile: form b - 45 baner street_compressed.pdf | 23 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 45 Baner Form 5 23-24.pdf | 20 Dec 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 111 भोगवटा पत्र(1) 09-Oct-2024 15-51-03.pdf | 19 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_45 Baner Street_Sep24s.pdf | 7 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 45 B Form 1.pdf | 30 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 45 B Form 2.pdf | 30 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: 45 Baner Sold Unsold.pdf | 28 Oct 2024 |
| Declaration in FORM BFile: FORM B 45 BANER STREET EXTENSION.pdf | 9 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Scan2024-08-09_164709.pdf | 9 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 45 BANER FORM 3 Q1 2024-2025.pdf | 22 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 45 Baner Form 2 Q1 2024-25_compressed.pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: 45 Baner Street Sold Unsold Q1 2024-2025_compressed.pdf | 20 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 45 BANER Q4 FORM 1.pdf | 3 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 45 BANER STREET FORM 2 Q4 2023-2024.pdf | 3 Jul 2024 |
| Details of encumbrancesFile: No Encumbrances 45 Baner.pdf | 20 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 45 BANER FORM 5 Q4 2023-2024.pdf | 25 Apr 2024 |
| Proforma of Agreement for saleFile: 45 Baner Street RERA draft.pdf | 24 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 45 baner dec 23.pdf | 8 Apr 2024 |
| Declaration in FORM BFile: P52100025160_FileName_1.pdf | 3 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: 45 BANER SOLD -UNSOLD.pdf | 3 Apr 2024 |
| Declaration about Commencement CertificateFile: FORM B 45 BANER S.pdf | 16 Mar 2024 |
| Declaration in FORM BFile: FORM B 45 BANER S.pdf | 16 Mar 2024 |
| Declaration in FORM BFile: Form B of 45 baner Street.pdf | 26 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 45 baner ca certificate form 3 Q3 2023_compressed.pdf | 24 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 q3 - 45 baner.pdf | 8 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 q3 - 45 baner street.pdf | 8 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: sold booked q3 - 45 baner.pdf | 8 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: 45 baner sold booked.pdf | 29 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: 45 baner developer units.pdf | 15 Dec 2023 |
| Layout approvalFile: HPSC0608_compressed.pdf | 6 Dec 2023 |
| Building plan approvalFile: HPSC0609_compressed.pdf | 6 Dec 2023 |
| Building plan approvalFile: HPSC0610_compressed.pdf | 6 Dec 2023 |
| Building plan approvalFile: HPSC0611_compressed.pdf | 6 Dec 2023 |
| Building plan approvalFile: HPSC0612_compressed.pdf | 6 Dec 2023 |
| Building plan approvalFile: HPSC0613_compressed.pdf | 6 Dec 2023 |
| Copy of Layout Approval (in case of layout)File: HPSC0608_compressed.pdf | 6 Dec 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: HPSC0609_compressed.pdf | 6 Dec 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: HPSC0610_compressed.pdf | 6 Dec 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: HPSC0611_compressed.pdf | 6 Dec 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: HPSC0612_compressed.pdf | 6 Dec 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: HPSC0613_compressed.pdf | 6 Dec 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: 45 Baner Commencement Certificate Of Revised Sanction Plan_compressed.pdf | 6 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 45 baner form 5 2022-2023_compressed.pdf | 31 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 45 BANER CA CERTIFICATE Q1 2023-2024.pdf | 27 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 45 BANER CA CERTIICATE Q2 2023-2024.pdf | 27 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD BOOKED 45 BANER Q2.pdf | 20 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 45 Baner street.pdf | 18 Oct 2023 |
| Declaration in FORM BFile: 45 baner - form b.pdf | 13 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: sold booked - 45 baner.pdf | 27 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A - 45 BANER 2021.pdf | 18 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A - 45 BANER 2022.pdf | 18 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A - 45 BANER 2023.pdf | 18 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 45 baner architect certificate.pdf | 5 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 45 BANER ENGINEER CERTIFICATE Q1 2023-2024.pdf | 1 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 45 BANER ARCHITECT CERTIFICATE Q4 2022-2023.pdf | 29 Jun 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 45 Baner Engineer Certificate Q4 2022-2023_compressed.pdf | 29 Jun 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 CA Certificate 45 Baner Street Mar - 23 SC_compressed.pdf | 29 Jun 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q 4 - FY 2019-20 - 45 BANER - ARCHITECT CERTIFICATE.pdf | 23 Jun 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q 4 - FY 2020-21 - 45 BANER - ARCHITEC CERTIFICATE.pdf | 23 Jun 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q 1 - FY 2021-22 - 45 BANER - ARCHITECT CERTIFICATE.pdf | 23 Jun 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q 2 - FY 2021-22 - 45 BANER - ARCHITECT CERTIFICATE.pdf | 23 Jun 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q 1 - FY 2022-23 - 45 BANER - ARCHITCT CERTIFICATE.pdf | 23 Jun 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q 4 - FY 2019-20 - 45 BANER - ENGINEER CERTIFICATE.pdf | 23 Jun 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q 4 - FY 2020-21 - 45 BANER - ENGINEER CERTIFICATE.pdf | 23 Jun 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q 1 - FY 2021-22 - 45 BANER - ENGINEER CERTIFICATE.pdf | 23 Jun 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q 2 - FY 2021-22 - 45 BANER - ENGINEER CERTIFICATE.pdf | 23 Jun 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Q 1 - FY 2022-23 - 45 BANER - ENGINEER CERTIFICATE.pdf | 23 Jun 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 45 Baner Mar 20.pdf | 23 Jun 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 45 Baner Mar 21.pdf | 23 Jun 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 45 Baner June 21.pdf | 23 Jun 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4 45 Baner Sept 21.pdf | 23 Jun 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5 CA Certificate 45 Baner Street June 22.pdf | 23 Jun 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERT 45 BANER Q-DEC.pdf | 8 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGREERING CERT 45-BANER Q-DEC.pdf | 8 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 45 baner street art cr.pdf | 16 Mar 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| TEN SQUAREP52100021256 | BIBVEWADI MUNJERI, LULLANAGAR, Pune | 34 | Jun 2019 | Completed | Mar 2022 | Mar 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations, which the RERA portal never shows together
- All 123 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep 45 BANER STREET on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near OPP DMART, MAHALUNGE MAIN ROAD BANER, PUNE13,700+ in Pune
EARTH 1 BY VTP LUXE PHASE 1
MAHALUNGE REAL ESTATE DEVELOPERS PVT. LTD.
Godrej Meadows
Mahalunge Township Developers Private Limi
Godrej Green Vistas
Mahalunge Township Developers Private Limi
Godrej Hill Retreat
Mahalunge Township Developers Private Limi
Godrej Green Cove
Mahalunge Township Developers Private Limi
NYATI EMERALD I
NYATI BUILDERS PRIVATE LIMITED
Builder: RAICHANDANI CONSTRUCTIONS AND DEVELOPERS
RAICHANDANI CONSTRUCTIONS AND DEVELOPERS has 3 registrations on MahaRERA, including SWARNA VATIKA and 45 BANER STREET. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that 45 BANER STREET shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if 45 BANER STREET is delayed beyond 31 Jul 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of 45 BANER STREET?
The registered promoter entity is RAICHANDANI CONSTRUCTIONS AND DEVELOPERS, a partnership as per the filing. Its GSTIN 27AAYFR1876R1ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in 45 BANER STREET?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against 45 BANER STREET?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for 45 BANER STREET?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at 45 BANER STREET?
The professionals named in the filing: Architect: VILAS TARWADI; Engineer: Siddharth Bharat Sawant; Chartered Accountant: SPAK & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in 45 BANER STREET?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback