Registration lapsed No litigation declared Residential / Group Housing project

31 Shivalay

By Mahendra Dharamchand Phulfagar

RG-MH-64472 · RERA P52100035105 · Last updated on MahaRERA portal: 27 Jul 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 18 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Apr 2025Possession promised18 months past this date
0 of 44Construction stages doneacross 4 buildings; furthest along: Excavation, 80%
0Complaints at MahaRERAon this registration
Jump to the 53 documents Report an error

31 Shivalay is a Residential / Group Housing project by Mahendra Dharamchand Phulfagar in Pune, Maharashtra, registered with MahaRERA as P52100035105 on 10 May 2022. Possession was promised by 7 Apr 2025 and is now 18 months past that date.

At a glance

Project

  • Name31 Shivalay
  • TypeResidential / Group Housing
  • Location
    • Shirur
    • Pune
    • 412210
  • Pincode412210
  • RERA no.P52100035105
  • ReraGenie IDRG-MH-64472

Builder

  • NameMahendra Dharamchand Phulfagar
  • Entity typeIndividual
  • Declared earlier projects1 →

Key dates

18 months past promisethis monthRegisteredMay 2022PromisedApr 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on10 May 2022
  • Promised completion7 Apr 2025
  • Revised completionNone
  • Buildings4 building records
  • Documents filed53 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WingNA30000
B wingNA30000
C WingNA30000
D WingNA30000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 27 Jul 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Excavation, at 80%.

A Wing0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B wing0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C Wing7%
ActivityProgress
Excavation80%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
D Wing0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 27 Jul 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,438 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Madan Vyankati NarwadeShirurPune

Approvals and building plan

Permissible FSI1811.0
Proposed, not sanctioned1,811 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShirur

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRahul Sharad Shah
EngineerMahendra Dharamchand Phulfagar
Chartered AccountantAbhishek Gadiya
PartnerRole in project
Mahendra Dharamchand Phulfagar-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Apr 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Apr 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Apr 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed53

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A Quality Assurance FY 2023-24.pdf27 Jul 2024
Disclosure of sold/ booked inventoryFile: Sold Booked Inventory 30062023.pdf22 May 2024
Disclosure of sold/ booked inventoryFile: Sold Booked Inventory 30092023.pdf22 May 2024
Disclosure of sold/ booked inventoryFile: Sold Booked Inventory 31122023.pdf22 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Architect Certificate 30062023.pdf3 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Architect Certificate 30092023.pdf3 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Architect Certificate 31122023.pdf3 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Architect Certificate 31032024.pdf3 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Engineer Certificate 30092023.pdf3 May 2024
Details of encumbrances concerned to FinanceFile: No Encumbrances Legal 26052023.pdf27 Jun 2023
Details of encumbrances concerned to FinanceFile: No Encumbrances Finanace 26052023.pdf27 Jun 2023
Details of encumbrances concerned to LegalFile: No Encumbrances Legal 26052023.pdf27 Jun 2023
Details of encumbrances concerned to LegalFile: No Encumbrances Finanace 26052023.pdf27 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Architect Certificate 30062022.pdf27 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Architect Certificate 30092022.pdf27 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Architect Certificate 31122022.pdf27 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Architect Certificate 31032023.pdf27 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Engineer Certificate 30062022.pdf27 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Engineer Certificate 30092022.pdf27 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Engineer Certificate 31122022.pdf27 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Engineer Certificate 31032023.pdf27 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A Quality Assurance FY 2022-23.pdf27 Jun 2023
Disclosure of sold/ booked inventoryFile: Sold Booked Inventory 30062022.pdf27 Jun 2023
Disclosure of sold/ booked inventoryFile: Sold Booked Inventory 30092022.pdf27 Jun 2023
Disclosure of sold/ booked inventoryFile: Sold Booked Inventory 31122022.pdf27 Jun 2023
Disclosure of sold/ booked inventoryFile: Sold Booked Inventory 31032023.pdf27 Jun 2023
CERSAI detailsFile: CERSAI Undertaking 26052023.pdf27 Jun 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest Mahendra 27052023.pdf27 Jun 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Diclaration about Seperate bank Ac 22052023.pdf27 Jun 2023
Deviation Report with respect to Allotment letterFile: Deviation Of Allotment Letter 26052023.pdf27 Jun 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Of Agreement For Sale 26052023.pdf27 Jun 2023
Proforma of Allotment letterFile: Final Allotment Letter 31 SHIVALAY.pdf6 May 2022
Proforma of Allotment letterFile: FINAL MASTER DRAFT- 31 SHIVALAY.pdf6 May 2022
Layout approvalFile: LAYOUT1-3.pdf28 Apr 2022
Layout approvalFile: LAYOUT2-3.pdf28 Apr 2022
Layout approvalFile: LAYOUT 3-3.pdf28 Apr 2022
Building plan approvalFile: NA Order.pdf28 Apr 2022
PAN CardFile: Developer Pan Card.pdf28 Apr 2022
Copy of the legal title reportFile: Search Title Report.pdf28 Apr 2022
Details of encumbrancesFile: No Encumbrance Certificate.pdf28 Apr 2022
Copy of Layout Approval (in case of layout)File: LAYOUT1-3.pdf28 Apr 2022
Copy of Layout Approval (in case of layout)File: LAYOUT2-3.pdf28 Apr 2022
Copy of Layout Approval (in case of layout)File: LAYOUT 3-3.pdf28 Apr 2022
Building Plan Approval / NA Order for plotted developmentFile: NA Order.pdf28 Apr 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf28 Apr 2022
Declaration about Commencement CertificateFile: Declaration abt Commencement.pdf28 Apr 2022
Declaration in FORM BFile: Affidavit Form B Landowner.pdf28 Apr 2022
Declaration in FORM BFile: Affidavit -Form B Promotor.pdf28 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate v1 28042022.pdf28 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Enginner Certificate.pdf28 Apr 2022
CERSAI detailsFile: CERSAI_Search_Report_200235547503_For_Asset_Based_Search_21_04_2022_15_22_42_313.pdf28 Apr 2022
Disclosure of sold/ booked inventoryFile: Disclosure Of Inventory.pdf28 Apr 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Letter form 3 v1.pdf28 Apr 2022

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep 31 Shivalay on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Shirur13,700+ in Pune

Builder: Mahendra Dharamchand Phulfagar

Mahendra Dharamchand Phulfagar has 1 registration on MahaRERA, including 31 Shivalay. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that 31 Shivalay shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if 31 Shivalay is delayed beyond 7 Apr 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of 31 Shivalay?

The registered promoter entity is Mahendra Dharamchand Phulfagar, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in 31 Shivalay?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for 31 Shivalay?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at 31 Shivalay?

The professionals named in the filing: Architect: Rahul Sharad Shah; Engineer: Mahendra Dharamchand Phulfagar; Chartered Accountant: Abhishek Gadiya. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in 31 Shivalay?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About 31 Shivalay. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save 31 Shivalay to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.