29 GOLD COAST PHASE 6
By MANTRA 29 GOLD COST DEVELOPERS LLP
RG-MH-17490 · RERA P52100029378 · Last updated on MahaRERA portal: 25 Jul 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
29 GOLD COAST PHASE 6 is a Others project by MANTRA 29 GOLD COST DEVELOPERS LLP in DHANORI, 411015, registered with MahaRERA as P52100029378 on 29 May 2021. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 12 months from the original filing.
At a glance
Project
- Name29 GOLD COAST PHASE 6
- TypeOthers
- Location
- DHANORI
- 411015
- Pincode411015
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100029378
- ReraGenie IDRG-MH-17490
Builder
- NameMANTRA 29 GOLD COST DEVELOPERS LLP
- Entity typePartnership
- PartnersKISHOR POPATLAL GADA, NILESH POPATLAL GADA, MUKESH POPATLAL GADA, SHYAMKUMAR DWARKADAS MAHESHWARI, MANTRA PROPERTIES AND DEVELOPERS PRIVATE LIMITED THROUGH ITS PARTNER ROHIT GHANSHYAM GUPTA, MUKESH POPATLAL GADA, KISHOR POPATLAL GADA, NILESH POPATLAL GADA, SHYAMKUMAR DWARKADAS MAHESHWARI, MANTRA PROPERTIES AND DEVELOPERS PRIVATE LIMITED THROUGH ITS PARTNER ROHIT GHANSHYAM GUPTA, MUKESH POPATLAL GADA, KISHOR POPATLAL GADA and 18 more
- Other registrations6 more →
- Completed5 of 7
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on29 May 2021
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2024)
- Buildings5 building records
- Documents filed161 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING D1 | NA | 6 | 0 | 0 | 0 | 0 |
| BUILDING D2 | NA | 6 | 0 | 0 | 0 | 0 |
| BUILDING D3 | NA | 6 | 0 | 0 | 0 | 0 |
| BUILDING D4 | NA | 6 | 0 | 0 | 0 | 0 |
| BUILDING D5 | NA | 6 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 25 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
55 of 55 construction stages are filed complete across 5 buildings.
BUILDING D1100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING D2100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING D3100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING D4100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUILDING D5100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 25 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 90% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 50% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 90% |
| Solid Waste Management And Disposal | Yes | 90% |
| Water conservation /Rain water harvesting | Yes | 90% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 80% |
| Electrical meter room, sub-station, receiving station | Yes | 80% |
| Aggregate area of recreational Open Space | Yes | 80% |
| Open Parking | Yes | 80% |
Parking filed128
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| BUILDING D1 | 31 | 31 |
| BUILDING D2 | 29 | 29 |
| BUILDING D3 | 23 | 23 |
| BUILDING D4 | 23 | 23 |
| BUILDING D5 | 22 | 22 |
Land and ownership3
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| MANGAL MILAN CO OP SOC | Pune (M Corp.) | Pune |
| MANTRA BUILDCON LLP | - | Pune |
| GANESH VITTHAL TINGARE | - | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | A design studio |
| Architect | Mitesh Siddhpura and Associates |
| Engineer | Design werkz |
| Engineer | Ravi Rawal |
| Chartered Accountant | SHRUTI AGARWAL |
| Chartered Accountant | R DEVENDRAKUMAR AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| MANTRA 29 GOLD COST DEVELOPERS LLP | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterLaunch of Project is Delayed and therefore applying for Extension.
Litigation declared4
| Case | Court | Status |
|---|---|---|
| 1363/2016/2016 | CIVIL JUDGE SENIOR DIVISION PUNE | Filling of Evidance affidavit by plaintiff Court has given next date |
| 1364/2016/2016 | CIVIL JUDGE SENIOR DIVISION PUNE | Filling of Evidance affidavit by plaintiff Court has given next date |
| 839/2017/2017 | CIVIL JUDGE SENIOR DIVISION PUNE | W S Filed by our side next date for hearing on Ex Court has given next date |
| 1507/2018/2017 | CIVIL JUDGE SENIOR DIVISION PUNE | W S Filed by our side next date for hearing on Ex Court has given next date |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 22 May 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 Jun 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 Jun 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 Dec 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed161
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 161 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Architect Ph 6_0001.pdf | 25 Jul 2025 |
| Form 2File: Engi Ph 6.pdf | 25 Jul 2025 |
| Form 3File: CA Certificate_29 GC_Phase 6_compressed.pdf | 25 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Ph 6.pdf | 25 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate 29 GC compressed.pdf | 24 Jun 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate 29 GC compressed.pdf | 24 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Ph 6.pdf | 24 Jun 2025 |
| Layout approvalFile: 01 Layout Plan compressed.pdf | 16 Jun 2025 |
| Building plan approvalFile: 02 Parking Layout.pdf | 16 Jun 2025 |
| Copy of Layout Approval (in case of layout)File: 01 Layout Plan compressed.pdf | 16 Jun 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 02 Parking Layout.pdf | 16 Jun 2025 |
| Form 1File: Archi Ph 6.pdf | 3 Jun 2025 |
| Form 2File: Engi Ph 6.pdf | 3 Jun 2025 |
| Form 3File: CA Ph 6.pdf | 3 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Ph 6.pdf | 3 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Archi Ph 6.pdf | 19 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Ph 6.pdf | 19 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engi Ph 6.pdf | 19 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Ph 6.pdf | 19 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Archi Ph 6.pdf | 20 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Cert Ph 6.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engi Ph 6.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD PHASE 6.pdf | 20 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 29 GC Ph 6.pdf | 3 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Cert Ph 6.pdf | 19 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Ph 6.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engi Ph 6.pdf | 18 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Ph 6.pdf | 18 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD PH 6.pdf | 17 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 PH 6.pdf | 16 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 PH 6.pdf | 16 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 PH 6.pdf | 16 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Mantra 29 Gold Ph-6.pdf | 17 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch D1 to D5.pdf | 18 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC- D1 to D5 Ph6.pdf | 18 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Sold - D1 to D5.pdf | 18 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA - D1 to D5.pdf | 18 Apr 2024 |
| Building plan approvalFile: 03 Parking Layout compressed.pdf | 25 Jan 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 03 Parking Layout compressed.pdf | 25 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Cert Ph 6.pdf | 16 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arc Cert Ph 6.pdf | 10 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Cert Ph 6.pdf | 10 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Ph 6.pdf | 10 Jan 2024 |
| Layout approvalFile: Layout Plan_compressed.pdf | 21 Dec 2023 |
| Layout approvalFile: Parking Layout.pdf | 21 Dec 2023 |
| Layout approvalFile: Parking Layout (2).pdf | 21 Dec 2023 |
| Building plan approvalFile: 1 Bldg D1 D1A.pdf | 21 Dec 2023 |
| Building plan approvalFile: 2 Bldg D1 D1A.pdf | 21 Dec 2023 |
| Building plan approvalFile: 3 Bldg D1 D1A.pdf | 21 Dec 2023 |
| Building plan approvalFile: 4 Bldg D1 D1A.pdf | 21 Dec 2023 |
| Building plan approvalFile: 5 Bldg D2 D2A.pdf | 21 Dec 2023 |
| Building plan approvalFile: 6 Bldg D2 D2A.pdf | 21 Dec 2023 |
| Building plan approvalFile: 7 Bldg D2 D2A.pdf | 21 Dec 2023 |
| Building plan approvalFile: 8 Bldg D3.pdf | 21 Dec 2023 |
| Building plan approvalFile: 9 Bldg D3.pdf | 21 Dec 2023 |
| Building plan approvalFile: 10 Bldg D3.pdf | 21 Dec 2023 |
| Building plan approvalFile: 11 Bldg D4.pdf | 21 Dec 2023 |
| Building plan approvalFile: 12 Bldg D4.pdf | 21 Dec 2023 |
| Building plan approvalFile: 13 Bldg D4.pdf | 21 Dec 2023 |
| Building plan approvalFile: 14 Bldg D5.pdf | 21 Dec 2023 |
| Building plan approvalFile: 15 Bldg D5.pdf | 21 Dec 2023 |
| Building plan approvalFile: 16 Bldg D5.pdf | 21 Dec 2023 |
| Copy of Layout Approval (in case of layout)File: Layout Plan_compressed.pdf | 21 Dec 2023 |
| Copy of Layout Approval (in case of layout)File: Parking Layout.pdf | 21 Dec 2023 |
| Copy of Layout Approval (in case of layout)File: Parking Layout (2).pdf | 21 Dec 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 1 Bldg D1 D1A.pdf | 21 Dec 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 2 Bldg D1 D1A.pdf | 21 Dec 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 3 Bldg D1 D1A.pdf | 21 Dec 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 4 Bldg D1 D1A.pdf | 21 Dec 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 5 Bldg D2 D2A.pdf | 21 Dec 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 6 Bldg D2 D2A.pdf | 21 Dec 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 7 Bldg D2 D2A.pdf | 21 Dec 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 8 Bldg D3.pdf | 21 Dec 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 9 Bldg D3.pdf | 21 Dec 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 10 Bldg D3.pdf | 21 Dec 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 11 Bldg D4.pdf | 21 Dec 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 12 Bldg D4.pdf | 21 Dec 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 13 Bldg D4.pdf | 21 Dec 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 14 Bldg D5.pdf | 21 Dec 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 15 Bldg D5.pdf | 21 Dec 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 6 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 161 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep 29 GOLD COAST PHASE 6 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near DHANORI
Filed coordinates, straight-line distance. 75 registered projects within 2 km.
Kohinoor Viva Pixel- Phase II
RISING ASSOCIATES
VIVACITY
REALCON LANDMARKS LLP
TRIAA VASANTAM CITY CENTER PHASE 1
Triaa Realtors LLP
QUE 101 PHASE I
ANNR Unique Realty LLP
NYATI ERA I
NYATI CONSTRUCTION PRIVATE LIMITED
ONE ARETHA PHASE 1
Triaa Landmarks LLP
Builder: MANTRA 29 GOLD COST DEVELOPERS LLP
MANTRA 29 GOLD COST DEVELOPERS LLP has 7 registrations on MahaRERA, including 29 GOLD COAST PHASE 1 and 29 GOLD COAST PHASE 2. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record.
Frequently asked questions
What does it mean that 29 GOLD COAST PHASE 6 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if 29 GOLD COAST PHASE 6 is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of 29 GOLD COAST PHASE 6?
The registered promoter entity is MANTRA 29 GOLD COST DEVELOPERS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in 29 GOLD COAST PHASE 6?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for 29 GOLD COAST PHASE 6?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at 29 GOLD COAST PHASE 6?
The professionals named in the filing: Architect: A design studio; Architect: Mitesh Siddhpura and Associates; Engineer: Design werkz; Engineer: Ravi Rawal; Chartered Accountant: SHRUTI AGARWAL; Chartered Accountant: R DEVENDRAKUMAR AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in 29 GOLD COAST PHASE 6?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback