Home / Browse projects / Pune, Maharashtra / 18 East

Registered No litigation declared Commercial project

18 East

By MERLIN PROJECTS LIMITED

RG-MH-27453 · RERA P52100035065 · Last updated on MahaRERA portal: 23 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 6 months
  • 1 extension taken
  • Rs 40.00 crore secured on the land, in favour of BAJAJ HOUSING FINANCE LIMITED

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 6 months from the original
7 of 11Construction stages donefurthest along: Internal walls, 90%
38 of 88Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 144 documents Report an error

18 East is a Commercial project by MERLIN PROJECTS LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100035065 on 4 May 2022. Possession is promised by 31 Mar 2027. The completion date has moved by 6 months from the original filing. 50 of the 88 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.

At a glance

Project

  • Name18 East
  • TypeCommercial
  • Location
    • MUNDHWA
    • Keshavnagar-Mundwa
    • Pune City
    • Pune
    • 411036
  • Pincode411036
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100035065
  • ReraGenie IDRG-MH-27453

Builder

  • NameMERLIN PROJECTS LIMITED
  • Entity typeCompany
  • DirectorSAKET SUSHILKUMAR MOHTA

Key dates

this monthRegisteredMay 2022First promiseSep 2026Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on4 May 2022
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 30 Sep 2026)
  • Buildings1 building record
  • Documents filed144 files

Current status

57%50 of 88 units booked
59.0%Work done, per cost certificate

Figures as on 23 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
18 EastNA221808888

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

18 East: 75% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Progress on shared amenities15

As on 23 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed144

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots144
Closed/Covered144

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area2,000 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofBAJAJ HOUSING FINANCE LIMITED
Secured amountRs 40.00 crore
CERSAI search filedYes
Declared on16 Jul 2025

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI12274.94
Proposed, not sanctioned12,275 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPANCHSHIL TECH PARK, VIMAN NAGAR, PUNE 411014
Estimated costRs 65.13 cr
Cost incurredRs 38.44 cr
Work done59.03%
BuildingWingEstimatedIncurred
18 EastNARs 61.14 crRs 37.85 cr
-NARs 3.99 crRs 59.86 lakh

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANA Consortium PVT. LTD.
EngineerVIVEK MUDHALE
EngineerNilesh Chavan
EngineerShubham Ghatage
Chartered AccountantSAC & CO LLP
Chartered AccountantBogati & Company
Chartered AccountantPRIYANKA CHORDIYA & ASSOCIATES
Chartered AccountantK G Jhamvar & Company
PartnerRole in project
MERLIN PROJECTS LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA16032620241Sep 2026 → Mar 2027

Reason as filed by the promoterTo The Authority Maharashtra Real Estate Regulatory Authority (RERA) Maharashtra Subject: Request for Extension of Project Completion Date up to 31/03/2027 Respected Sir/Madam, We have obtained sanctions upto first floor from the Pune Municipal Corporation vide Commencement Certificate No. CC/3392/2021 dated 25/01/2022 to carry out construction of the project by maintaining a 10-meter marginal distance from the adjoining land owned by the Defence Authority. Subsequently, the Ministry of Defence, Government of India issued guidelines dated 23/12/2022 regarding the issuance of a “No Objection Ce

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Apr 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 May 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 May 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 May 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed144

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 144 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: 18 EAST Form 1 30062026.pdf23 Jul 2026
Withdrawal Update Form 2File: 18 east - Form 2 - Engg certificate.pdf23 Jul 2026
Withdrawal Update Form 3File: Form 3 18 East.pdf23 Jul 2026
Withdrawal Update Form 1File: 18 EAST Form 01.pdf27 Apr 2026
Withdrawal Update Form 2File: 18 East Form 2.pdf27 Apr 2026
Withdrawal Update Form 3File: Form 3 18 East Mar 26.pdf27 Apr 2026
Form 2A (FY 2023-2024)File: Form 2A 202324.pdf1 Apr 2026
Withdrawal Update Form 1File: Form 1 Q3 .pdf17 Mar 2026
Withdrawal Update Form 2File: Engineer Cert 18 East .pdf17 Mar 2026
Withdrawal Update Form 3File: Form 3 Q3 .pdf17 Mar 2026
Withdrawal Update Form 1File: Form 1 Q3 .pdf2 Feb 2026
Withdrawal Update Form 2File: Engineer Cert 18 East .pdf2 Feb 2026
Withdrawal Update Form 3File: Form 3 Q3 .pdf2 Feb 2026
Form 5 (FY 2024-2025)File: Form 518 East FY 20242025.pdf17 Nov 2025
Withdrawal Update Form 1File: Arch 18 east Q2.pdf3 Nov 2025
Withdrawal Update Form 2File: FORM 2.pdf3 Nov 2025
Withdrawal Update Form 3File: Q2 Form 3 18 East..pdf3 Nov 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 18 EAST Architect certificate.pdf23 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3616_20250423155126_001.pdf23 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 18 East.pdf21 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Cert.pdf13 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 18-East 31-12-2024 sign copy_compressed (1).pdf13 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Cert.pdf13 Feb 2025
Deviation Report with respect to model copy of AgreementFile: Deviation of Rera Agreement draft.pdf16 Jan 2025
Proforma of Agreement for saleFile: Rera Agreement Draft.pdf16 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch cert.pdf5 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf5 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch cert.pdf14 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate .pdf14 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng cert.pdf14 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 .pdf14 Oct 2024
Details of encumbrancesFile: 0226_20240719164729_001.pdf24 Jul 2024
Layout approvalFile: 1 7.pdf21 May 2024
Building plan approvalFile: 2 7.pdf21 May 2024
Building plan approvalFile: 3 7.pdf21 May 2024
Building plan approvalFile: 4 6.pdf21 May 2024
Building plan approvalFile: 5 6.pdf21 May 2024
Building plan approvalFile: 6 6.pdf21 May 2024
Building plan approvalFile: 7 6.pdf21 May 2024
Building plan approvalFile: 8 5.pdf21 May 2024
Building plan approvalFile: 9 5.pdf21 May 2024
Building plan approvalFile: 10 6.pdf21 May 2024
Building plan approvalFile: 11 8.pdf21 May 2024
Building plan approvalFile: 12 6.pdf21 May 2024
Building plan approvalFile: 13 6.pdf21 May 2024
Building plan approvalFile: 14 6.pdf21 May 2024
Copy of Layout Approval (in case of layout)File: 1 7.pdf21 May 2024
Building Plan Approval / NA Order for plotted developmentFile: 2 7.pdf21 May 2024
Building Plan Approval / NA Order for plotted developmentFile: 3 7.pdf21 May 2024
Building Plan Approval / NA Order for plotted developmentFile: 4 6.pdf21 May 2024
Building Plan Approval / NA Order for plotted developmentFile: 5 6.pdf21 May 2024
Building Plan Approval / NA Order for plotted developmentFile: 6 6.pdf21 May 2024
Building Plan Approval / NA Order for plotted developmentFile: 7 6.pdf21 May 2024
Building Plan Approval / NA Order for plotted developmentFile: 8 5.pdf21 May 2024
Building Plan Approval / NA Order for plotted developmentFile: 9 5.pdf21 May 2024
Building Plan Approval / NA Order for plotted developmentFile: 10 6.pdf21 May 2024
Building Plan Approval / NA Order for plotted developmentFile: 11 8.pdf21 May 2024
Building Plan Approval / NA Order for plotted developmentFile: 12 6.pdf21 May 2024
Building Plan Approval / NA Order for plotted developmentFile: 13 6.pdf21 May 2024
Building Plan Approval / NA Order for plotted developmentFile: 14 6.pdf21 May 2024
Commencement Certificates / NA Order for plotted developmentFile: CC_BP_060623.pdf21 May 2024
Disclosure of sold/ booked inventoryFile: Sold-unsold inventory .pdf21 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate .pdf16 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate .pdf16 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 18 East FORM 3.pdf16 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch certificate.pdf24 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate.pdf24 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 .pdf24 Jan 2024
Disclosure of sold/ booked inventoryFile: sold-unsold-booked inventory.pdf10 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Cert 30 Sept 2023.pdf4 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate 30 Sept 2023.pdf4 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE 30 Sept 2023.pdf4 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of 30 Sept 2023.pdf4 Nov 2023
Foreclosure of the ProjectFile: application for correction under project.pdf14 Aug 2023
Disclosure of sold/ booked inventoryFile: Disclosure of inventory .pdf26 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 .pdf26 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE .pdf24 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE.pdf24 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate 31 Mar 2023.pdf27 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE Mar 2023.pdf27 May 2023

How this compares with Pune

57%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 6 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep 18 East on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MUNDHWA13,700+ in Pune

2 km18 EastCompleted 17Lapsed / revoked 9Other 51Dot size: filed unitsN

Filed coordinates, straight-line distance. 77 registered projects within 2 km.

Builder: MERLIN PROJECTS LIMITED

MERLIN PROJECTS LIMITED has 1 registration on MahaRERA, including 18 East. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if 18 East is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of 18 East?

The registered promoter entity is MERLIN PROJECTS LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in 18 East?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for 18 East?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at 18 East?

The professionals named in the filing: Architect: ANA Consortium PVT. LTD.; Engineer: VIVEK MUDHALE; Engineer: Nilesh Chavan; Engineer: Shubham Ghatage; Chartered Accountant: SAC & CO LLP; Chartered Accountant: Bogati & Company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in 18 East?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About 18 East. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save 18 East to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.