153 SKYE
RG-MH-62951 · RERA P51900047692 · Last updated on MahaRERA portal: 30 Apr 2025
Source: official MahaRERA filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
153 SKYE is a Residential / Group Housing project by NITIN SHANTILAL GADA in MATUNGA WEST, 400016, registered with MahaRERA as P51900047692 on 21 Nov 2022. The registration is recorded completed; possession was promised by 31 Aug 2025. The completion date has moved by 12 months from the original filing.
At a glance
Project
- Name153 SKYE
- TypeResidential / Group Housing
- Location
- T H KATARIA MARG
- MATUNGA WEST
- 400016
- Pincode400016
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900047692
- ReraGenie IDRG-MH-62951
Builder
- NameNITIN SHANTILAL GADA
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on21 Nov 2022
- Promised completion31 Aug 2025
- Revised completionRevised to 31 Aug 2025 (originally 31 Aug 2024)
- Buildings1 building record
- Documents filed78 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| 153 SKYE | NA | 11 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 30 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
153 SKYE: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 30 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
Parking filed20
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| NALINI NITIN GADA | - | Mumbai City |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sheetal Nikhare |
| Engineer | Bhavesh K Dewani |
| Chartered Accountant | Taral Vasanji Dedhia |
| Partner | Role in project |
|---|---|
| NITIN SHANTILAL GADA | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe are the co-owners of above said project, hereby request you to kindly extend the project completion date upto 31-08-2025. Our building Civil Works were Completed in all respect, due to final completion work / Finishing work of flats, External Plumbing Work, Fire Fighting Work are going on and it will be completed within 4 to 5 months in all respect. Due to rainy season started we cannot do the external painting work of the building for safety purpose. Further to inform you that, after completion of finishing work of building, it will take further 2 to 3 months for getting Occupation Certifi
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 17 Oct 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 17 Oct 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Jan 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 May 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 30 Apr 2025
Documents filed78
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert Form 1.pdf | 30 Apr 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate.pdf | 30 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Cert.pdf | 18 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate.pdf | 18 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate.pdf | 18 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Cert.pdf | 20 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2 Engineer Certificate.pdf | 20 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf | 19 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate.pdf | 19 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate.pdf | 19 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA FORM 5.pdf | 19 Oct 2024 |
| Declaration in FORM BFile: Form B (8).pdf | 18 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf | 18 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 mayur jani.pdf | 18 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Engineer's Certificate Quality Assurance.pdf | 18 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory.pdf | 18 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE_compressed.pdf | 18 Jul 2024 |
| Home Buyer /Allottee Grievance Redressal CellFile: grivance redressal.pdf | 18 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate.pdf | 19 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf | 19 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf | 19 Apr 2024 |
| Building plan approvalFile: Amended Approved Drawing.pdf | 18 Jan 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Amended Approved Drawing.pdf | 18 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FROM 1 Architect Certificate.pdf | 18 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2 Engineer Certificate.PDF | 18 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate.pdf | 18 Jan 2024 |
| Other - LegalFile: Amended MOU Dec 2023.pdf | 18 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf | 19 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 Eng Cert.pdf | 19 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA CERTIFICATE.pdf | 19 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Annual Report Statement of Accounts.pdf | 3 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form - 2A - Engineer's Certificate (Quality Assurance).pdf | 29 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate form comp.pdf | 19 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2 Eng certificate.pdf | 19 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate.pdf | 19 Jul 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Further Commecement Certificate.pdf | 16 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf | 16 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2 Engineer Certificate.pdf | 16 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate.pdf | 16 May 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A Declaration about Separate Bank Account.pdf | 16 May 2023 |
| Other - FinanceFile: self declaration for change of designated bank account.pdf | 16 May 2023 |
| Other - FinanceFile: Declaration Cum Undertaking.pdf | 16 May 2023 |
| Other - FinanceFile: Declaration Cum Undertaking for change of designated bank account1.pdf | 16 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf | 20 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form - 2 Engineer Certificate.pdf | 20 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate1.pdf | 20 Apr 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about separate bank account.pdf | 20 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Arch Certificate.pdf | 20 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate.pdf | 20 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate.pdf | 20 Jan 2023 |
| Other - LegalFile: Property Purchase Conveyance Deed.pdf | 14 Nov 2022 |
| Other - LegalFile: Property Card F Plot no 153 TPS III.pdf | 14 Nov 2022 |
| Proforma of Allotment letterFile: Letter of Allotment_Nalini.pdf | 28 Oct 2022 |
| Proforma of Agreement for saleFile: Agreement for Sale_Nitin.pdf | 28 Oct 2022 |
| Proforma of Agreement for saleFile: Agreement for Sale _Nalini.pdf | 28 Oct 2022 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report of Agr for sale_Nitin.pdf | 28 Oct 2022 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report of Agr for sale_Nalini.pdf | 28 Oct 2022 |
| PAN CardFile: Pan Card_Nalini Gada.pdf | 20 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 20 Oct 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: REVISED CA CERTIFICATE.pdf | 20 Oct 2022 |
| Proforma of Allotment letterFile: Letter of Allotment_Nitin.pdf | 20 Oct 2022 |
| Layout approvalFile: Declaration for no layout.pdf | 17 Oct 2022 |
| Building plan approvalFile: DRAWING BK.pdf | 17 Oct 2022 |
| PAN CardFile: PAN CARD.pdf | 17 Oct 2022 |
| Copy of the legal title reportFile: Title Certificate.pdf | 17 Oct 2022 |
| Details of encumbrances concerned to FinanceFile: No Encumbraces ltr.pdf | 17 Oct 2022 |
| Details of encumbrances concerned to LegalFile: No Encumbraces ltr.pdf | 17 Oct 2022 |
| Copy of Layout Approval (in case of layout)File: Declaration for no layout.pdf | 17 Oct 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: DRAWING BK.pdf | 17 Oct 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 17 Oct 2022 |
| Declaration about Commencement CertificateFile: Declaration about CC.pdf | 17 Oct 2022 |
| Declaration in FORM BFile: Revised Form B.pdf | 17 Oct 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf | 17 Oct 2022 |
| CERSAI detailsFile: CERSAI Report.pdf | 17 Oct 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration Sepreate Bank Account.pdf | 17 Oct 2022 |
| Deviation Report with respect to Allotment letterFile: Deviation Report of Ltr of Allot_Nitin.pdf | 17 Oct 2022 |
| Deviation Report with respect to Allotment letterFile: Deviation Report of Ltr of Allot_Nalini.pdf | 17 Oct 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 78 filed documents as one ZIP, foldered, with a manifest
Keep 153 SKYE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MATUNGA WEST
Filed coordinates, straight-line distance. 60 registered projects within 2 km.
Island Cove
LH Residential Housing Private Limited
Midtown Bay
Rising Sun Impex Private Limited
Island Cove Tower 4
LH Residential Housing Private Limited, Sh
Bayline Residences
HRUB Infra Projects Pvt Ltd
VITALIS
SURAJ ESTATE DEVELOPERS LTD
Suraj One Business Bay
ICONIC PROPERTY DEVELOPERS PVT LTD
Builder: NITIN SHANTILAL GADA
NITIN SHANTILAL GADA has 1 registration on MahaRERA, including 153 SKYE. Its filings disclose no earlier MahaRERA projects. Read the full track record.
Frequently asked questions
What are my rights if 153 SKYE is delayed beyond 31 Aug 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of 153 SKYE?
The registered promoter entity is NITIN SHANTILAL GADA, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in 153 SKYE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for 153 SKYE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at 153 SKYE?
The professionals named in the filing: Architect: Sheetal Nikhare; Engineer: Bhavesh K Dewani; Chartered Accountant: Taral Vasanji Dedhia. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in 153 SKYE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.