Home / Browse projects / Aurangabad, Maharashtra / 10 PEARLS
10 PEARLS
By MOHAMMAD ASHFAQUE MOHAMMAD SIDDIQUE MOTIWALA
RG-MH-79377 · RERA P51500032806 · Last updated on MahaRERA portal: 31 Dec 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
10 PEARLS is a Residential / Group Housing project by MOHAMMAD ASHFAQUE MOHAMMAD SIDDIQUE MOTIWALA in Aurangabad, Maharashtra, registered with MahaRERA as P51500032806 on 29 Jan 2022. Possession was promised by 31 Dec 2025 and is now 10 months past that date. 0 of the 10 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.
At a glance
Project
- Name10 PEARLS
- TypeResidential / Group Housing
- Location
- Motiwala Nagar
- Byjipura
- Aurangabad (M Corp.)
- Aurangabad
- 431001
- Pincode431001
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51500032806
- ReraGenie IDRG-MH-79377
Builder
- NameMOHAMMAD ASHFAQUE MOHAMMAD SIDDIQUE MOTIWALA
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on29 Jan 2022
- Promised completion31 Dec 2025
- Revised completionNone
- Buildings1 building record
- Documents filed114 files
Current status
Figures as on 31 Dec 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| 10 Pearls | NA | 3 | 3 | 10 | 0 | 10 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 31 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.
10 Pearls: 66% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 65% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 30% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 40% |
Progress on shared amenities15
As on 31 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 75% |
| Water Supply | Yes | 75% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 85% |
| Storm Water Drains | Yes | 75% |
| Landscaping & Tree Planting | Yes | 45% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 90% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Samil Architects |
| Engineer | Icon Consultants |
| Chartered Accountant | Narendra Navandar |
| Partner | Role in project |
|---|---|
| MOHAMMAD ASHFAQUE MOHAMMAD SIDDIQUE MOTIWALA | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 17 Jan 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 20 Nov 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 20 Nov 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 Nov 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed114
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 114 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1.pdf | 31 Dec 2025 |
| Form 2File: Form 2.pdf | 31 Dec 2025 |
| Form 3File: Form 3 Dt-30-12-2025- sep-25.pdf | 31 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Dt-30-09-2025_0001.pdf | 31 Dec 2025 |
| OthersFile: Form 2A Dt -05-10-2025 Sep 25_0001.pdf | 31 Dec 2025 |
| Form 1File: fORM 1.pdf | 31 Dec 2025 |
| Form 2File: Form 2.pdf | 31 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Dt-30-06-2025_0001.pdf | 31 Dec 2025 |
| Form 3File: Form 3 Dt-30-12-2025- jun 25.pdf | 31 Dec 2025 |
| OthersFile: Quality Assurance Certificate Dt-05-07-2025_0001.pdf | 31 Dec 2025 |
| Form 1File: form 1.pdf | 31 Dec 2025 |
| Form 2File: form 2.pdf | 31 Dec 2025 |
| Form 3File: Form 3 Dt-30-12-2025- mar-25_0001.pdf | 31 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Dt-31-03-2025_0001.pdf | 31 Dec 2025 |
| OthersFile: Quality Assurance Certificate Dt-07-04-2025_0001.pdf | 31 Dec 2025 |
| Form 1File: fORM 1.pdf | 31 Dec 2025 |
| Form 2File: fORM 2.pdf | 31 Dec 2025 |
| Form 3File: Form 3 Dt-30-12-2025- Dec-24_0001.pdf | 31 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: 31-12-2024.pdf | 31 Dec 2025 |
| OthersFile: 2A.pdf | 31 Dec 2025 |
| Form 1File: fORM 1.pdf | 31 Dec 2025 |
| Form 2File: fORM 2.pdf | 31 Dec 2025 |
| Form 3File: Form 3 Dt-30-12-2025- sep 24_0001.pdf | 31 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: 30-09-2024.pdf | 31 Dec 2025 |
| OthersFile: 2A.pdf | 31 Dec 2025 |
| Form 1File: fORM 1.pdf | 31 Dec 2025 |
| Form 2File: fORM 2.pdf | 31 Dec 2025 |
| Form 3File: Form 3 Dt-30-12-2024- jun 24_0001.pdf | 31 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: 30-06-2024.pdf | 31 Dec 2025 |
| OthersFile: 2A.pdf | 31 Dec 2025 |
| Form 1File: fORM 1.pdf | 31 Dec 2025 |
| Form 2File: fORM 2.pdf | 31 Dec 2025 |
| Form 3File: Form 3 Dt-30-12-2025- mar-24_0001.pdf | 31 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: 31-03-2024.pdf | 31 Dec 2025 |
| OthersFile: 2A.pdf | 31 Dec 2025 |
| Form 5 (FY 2024-2025)File: Form 5 Dt-30-12-2025- March-25_0001.pdf | 31 Dec 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Dt-03-01-2025_0001.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-Dt-03-01-2025_0001.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: 31-03-2024.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: 30-06-2024.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: 30-09-2024.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: 31-12-2024.pdf | 20 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 05 01 2025.pdf | 20 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Dt-03-04-2024_0001.pdf | 27 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Dt-05-07-2024_0001.pdf | 27 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1-Dt-03-10-2024.pdf | 27 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-Dt-03-04-2024_0001.pdf | 27 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-Dt-05-07-2024_0001.pdf | 27 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2-Dt-03-10-2024_0001.pdf | 27 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 5-4-2024.pdf | 27 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 04 05 2024.pdf | 27 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 05 10 2024.pdf | 27 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered certificate Form 3.pdf | 8 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Ashfaque Motiwala Dt31-03-22_0001.pdf | 4 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Ashfaque Motiwala Dt 30-06-22_0001.pdf | 4 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Ashfaque Motiwala Dt30-09-22_0001.pdf | 4 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Ashfaque Motiwala Dt31-12-22_0001.pdf | 4 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Ashfaque Motiwala Dt31-03-23_0001.pdf | 4 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Ashfaque Motiwala Dt30-09-23_0001.pdf | 4 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Ashfaque Motiwala Dt 30-06-23_0001.pdf | 4 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form no-2 A Dt-05-10-2023_0001.pdf | 16 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form-2A Dt-05-01-2024_0001.pdf | 16 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Sold - booked inventory 31-03-2022_0001.pdf | 16 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Sold - booked inventory 30-06-2022_0001.pdf | 16 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Sold - booked inventory 30-09-2022_0001.pdf | 16 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Sold - booked inventory 31-12-2022_0001.pdf | 16 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Booked Inventory 31-03-2023.pdf | 16 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Sold - booked inventory 30-06-2023_0001.pdf | 16 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Sold - booked inventory 30-09-2023_0001.pdf | 16 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Sold - booked inventory 31-12-2023_0001.pdf | 16 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form no-1 Dt-05-07-2023.pdf | 5 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form no-1 Dt-03-10-2023.pdf | 5 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form no-1 Dt-01-01-2024.pdf | 5 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Dt-05-07-2023.pdf | 5 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form no-2 Dt-23-10-2023.pdf | 5 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form no-2 Dt-01-01-2024.pdf | 5 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form no-5 Dt-01-11-2023.pdf | 5 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate (2).pdf | 14 Sep 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer certificate.pdf | 14 Sep 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A SEP 22.pdf | 14 Sep 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Aurangabad
Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 114 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep 10 PEARLS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Byjipura1,400+ in Aurangabad
Filed coordinates, straight-line distance. 82 registered projects within 2 km.
Capital Trade Centre
KRK Landmark LLP
AQ TOWN
AQ INFRASTRUCTURE PRIVATE LIMITED
KALYANI SAI VISHWA
RAJASHREE UDYOG
AMRUT SAI PLAZA PH 2
Shree Amrut Sai Developer Pvt.Ltd
PRASSANA HIGH CLASS CITY PHASE - I
SHRI KRISHNA NAGAR SAHAKARI GRAH NIRMAN SA
SHRIRAM RESIDENCY
UNIQUE BUILDCON
See every Aurangabad project, with the district possession charts
Builder: MOHAMMAD ASHFAQUE MOHAMMAD SIDDIQUE MOTIWALA
MOHAMMAD ASHFAQUE MOHAMMAD SIDDIQUE MOTIWALA has 1 registration on MahaRERA, including 10 PEARLS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Aurangabad district page.
Frequently asked questions
What does it mean that 10 PEARLS shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if 10 PEARLS is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of 10 PEARLS?
The registered promoter entity is MOHAMMAD ASHFAQUE MOHAMMAD SIDDIQUE MOTIWALA, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in 10 PEARLS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for 10 PEARLS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at 10 PEARLS?
The professionals named in the filing: Architect: Samil Architects; Engineer: Icon Consultants; Chartered Accountant: Narendra Navandar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in 10 PEARLS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback