ReraGenieLog inGet a buyer report

Home / Developers / Wadhwa Construction and Infrastructure Private Limited

Wadhwa Construction and Infrastructure Private Limited: RERA track record

CIN U70109MH2000PTC129871 · GSTIN 27AAACW5097J1ZU · Company · attribution by exact filing name, entity resolution in progress

Wadhwa Construction and Infrastructure Private Limited has 30 registrations on MahaRERA, including Wise City, South Block Phase I, Plot RZ8 Building 5 Wing D1 and Wise City, South Block Phase I, Plot RZ8 Building 1 Wing A1. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations.

30RERA registrations
1Past projects disclosed
on timeMedian delivery slip
1Registrations with litigation
Follow this developer. An email when Wadhwa Construction and Infrastructure Private Limited registers a new project on MahaRERA, and when the filings of their existing projects change: new sales, moved possession dates, extensions, complaints. Runs 12 months, no auto-renew. Follow · Rs 999 / 12 months

Projects by this developer

Showing all 30 projects.

Largest first, by the unit count in the filing.

ProjectLocationUnitsBookedRegisteredStatus
Wise City, South Block Phase I, Plot RZ8 Building 5 Wing D2P52000016583Wadhwa Wise City, Raigarh, 41020628866%23 May 2018Registered
Wise City, South Block Phase I, Plot RZ8 Building 5 Wing D1P52000016540Wadhwa Wise City, Raigarh, 41020628779%23 May 2018Registered
Wise City, South Block Phase I, Plot RZ8, Building 5 Wing D4P52000017051Wadhwa Wisecity, Raigarh, 41020627343%4 Jul 2018Registered
Wise City RZ8 Wing A2P52000053540Wadhwa Wise City, Raigarh, 4102062530%10 Nov 2023Registered
wise city, south Block, Phase I, Plot RZ8 Building 1 wing A3P52000021082Wadhwa Wise City, Raigarh, 41020625346%31 May 2019Registered
Wise City, South Block Phase I, Plot RZ8 Building 2 Wing B3P52000016594Wadhwa Wise City, Raigarh, 41020620293%23 May 2018Registered
Wise City, South Block Phase I, Plot RZ8, Building 3 Wing C3P52000020812Wadhwa Wise City, Raigarh, 41020620160%10 May 2019Registered
Wise City, South Block, Phase I,Plot RZ8 Building 4 Wing F2P52000021081Wadhwa Wise City, Raigarh, 41020619761%31 May 2019Registered
Wise City RZ-01 Plotted Development - Phase 1P52000052619Wadhwa Wise City, Raigarh, 41020614981%12 Sep 2023Registered
Wise City RZ8 Wing E2P52000051752Wadhwa Wise City, Raigarh, 41020611153%27 Jun 2023Registered
Wise City RZ-03 Plotted DevelopmentP52000048906Wise City ITP, Raigarh, 41020611090%24 Jan 2023Registration lapsed
Wise City RZ-01 Plotted Development - Phase 3P52000052569Wadhwa Wise City, Raigarh, 41020610475%11 Sep 2023Registered
Wise City RZ8 Wing D5P52000080955Wadhwa Wise City, Raigarh, 4102061030%1 Sep 2025Registered
Wise City RZ-01 Plotted Development - Phase 2P52000052572Wadhwa Wise City, Raigarh, 4102068872%11 Sep 2023Registered
Wise City CZ-05 Retail BuildingP52000053744Wadhwa Wise City, Raigarh, 410206850%28 Nov 2023Registered
Magnolia Cluster 1P52000021143Wise city, Raigarh, 4102066172%10 Jun 2019Registered
Wise City RZ-02 Plotted DevelopmentP52000048913Wise City ITP, Raigarh, 4102065891%24 Jan 2023Completed
Magnolia Cluster 2P52000021142Wise City, Raigarh, 4102065472%10 Jun 2019Registered
Magnolia Cluster 3P52000021144Wise City, Raigarh, 4102061100%10 Jun 2019Registered
Magnolia Cluster 4P52000021746Wise city, Raigarh, 410206--23 Jul 2019Registered
Wise City RZ8 Wing B1P52000051912Wadhwa Wise City, Raigarh, 410206--12 Jul 2023De-registered
Wise City, South Block Phase I, Plot RZ8 Building 1 Wing A1P52000016199Wadhwa Wise City, Raigarh, 410206--23 Apr 2018Completed
Wise City, South Block Phase I, Plot RZ8 Building 1 Wing A2P52000021106Wadhwa Wise City, Raigarh, 410206--31 May 2019De-registered
Wise City, South Block Phase I, Plot Rz8 Building 3 Wing C1P52000016549Wadhwa Wise City, Raigarh, 410206--23 May 2018Completed
Wise City, South Block Phase I, Plot RZ8 Building 4 Wing F3P52000016524Wadhwa Wise City, Raigarh, 410206--21 May 2018Completed
Wise City, South Block Phase I, Plot RZ8 Building 4 Wing F4P52000016274Wadhwa Wise City, Raigarh, 410206--2 May 2018Completed
Wise City, South Block Phase I, Plot RZ8 Building 5 Wing D3P52000016868Wadhwa Wise City, Raigarh, 410206--20 Jun 2018Registered
Wise City, South Block Phase I, Plot RZ8, Building 3 Wing C2P52000016560Wadhwa Wise City, Raigarh, 410206--23 May 2018Completed
Wise City, South Block, Phase I,Plot RZ8 Building 5 Wing D5P52000020858Wadhwa Wise City, Raigarh, 410206--15 May 2019De-registered
Wise City,South Block Phase I, Plot RZ8 Building 6 Wing A4P52000020776Wadhwa Wise City, Raigarh, 410206--9 May 2019Completed

What this promoter declares as its own experience

Wadhwa Construction and Infrastructure Private Limited declares experience on 1 earlier project. It carries no registration number we could match on MahaRERA, which is usual for work done before the register existed.

From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Wise City, South Block Phase I, Plot RZ8 Building 1 Wing A1
30 Dec 202630 Sep 2023On time

Frequently asked questions

How do I verify Wadhwa Construction and Infrastructure Private Limited as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U70109MH2000PTC129871 and GSTIN 27AAACW5097J1ZU on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Wadhwa Construction and Infrastructure Private Limited?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make Wadhwa Construction and Infrastructure Private Limited unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.

Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.

Report an errorShare feedback

Data from official MahaRERA filings. How we handle corrections is on the about page.

Report an error or share feedback

About the Wadhwa Construction and Infrastructure Private Limited developer page. Projects are grouped by the promoter name as filed, so a wrongly attributed project is the most useful thing to report.

We read every report. We cannot promise a reply to each one.