ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / Wise City RZ8 Wing B1

De-registered No litigation declared Residential / Group Housing project

Wise City RZ8 Wing B1

By Wadhwa Construction and infrastructure Private Limited

RG-MH-05849 · RERA P52000051912 · Last updated on MahaRERA portal: 30 Jan 2026

Source: official MahaRERA filing

Red flags

  • De-registered

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2029Possession promisedno revision filed
0 of 11Construction stages donefurthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 81 documents Report an error

Wise City RZ8 Wing B1 is a Residential / Group Housing project by Wadhwa Construction and infrastructure Private Limited in Raigarh, Maharashtra, registered with MahaRERA as P52000051912 on 12 Jul 2023. Possession is promised by 31 Dec 2029.

At a glance

Project

  • NameWise City RZ8 Wing B1
  • TypeResidential / Group Housing
  • Location
    • 36 Mtr DP road
    • Wadhwa Wise City
    • Wardoli
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000051912
  • ReraGenie IDRG-MH-05849

Builder

  • NameWadhwa Construction and infrastructure Private Limited
  • Entity typeCompany
  • CINU70109MH2000PTC129871
  • GSTIN27AAACW5097J1ZU
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • DirectorsManohar Moolchand Chhabria, Navin Amarlal Makhija
  • Other registrations29 more →
  • Completed7 of 30
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredJul 2023PromisedDec 2029

Key facts

Registration and timeline

  • StatusDe-registered
  • Registered on12 Jul 2023
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed81 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wise City RZ8 Wing B1NA270000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 30 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

Wise City RZ8 Wing B1: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 30 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed217

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots217
Closed/Covered98
Open Space119

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area547 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Valuable Properties Private LimitedMumbai SuburbanMumbai Suburban

Approvals and building plan

Permissible FSI14504.83
Proposed, not sanctioned14,505 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPlot no 206 221, 27th Road, Crystal Building, Waterfield Road, Bandra W, Mumbai 400 050

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHiten Sethi Associates
EngineerMillion Jobs Private Limited
Chartered AccountantS.M.BHAT & ASSOCIATES
PartnerRole in project
Wadhwa Construction and infrastructure Private Limited-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Jun 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jun 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 May 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Jul 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2029

Documents filed81

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 81 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM 1-B1.pdf30 Jan 2026
Form 2File: Form 2-B1.pdf30 Jan 2026
Form 3File: Form 3- B1.pdf30 Jan 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold.pdf30 Jan 2026
Commencement Certificates / NA Order for plotted developmentFile: CIDCO_NAINA_Panvel_vardoli_ITP_BP-236_Amended perm_585_SAP_162_Amm4_Amm2_CCLetter.pdf22 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B1.pdf11 Jul 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: B1.pdf13 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: B1 FORM 2 DEC 24.pdf28 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: b1 form 1 signed.pdf15 Mar 2025
Disclosure of sold/ booked inventoryFile: B 1 march.pdf15 Feb 2025
Disclosure of sold/ booked inventoryFile: B 1 june24.pdf15 Feb 2025
Disclosure of sold/ booked inventoryFile: wing B 1 sep 24.pdf15 Feb 2025
Disclosure of sold/ booked inventoryFile: B1.pdf14 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: wing B1.pdf13 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: B1 FORM 2 JUN 24.pdf7 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: B1 FORM 2 SEP 24.pdf7 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - B1 FY 2023-24.pdf7 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: B1 Form 2 March 24.pdf16 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: B1 Form 2 March 24.pdf16 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: wing B1_001.pdf2 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: B 1 _001.pdf12 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: B1.pdf11 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: B1.pdf11 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: B1.pdf11 Jul 2024
Disclosure of sold/ booked inventoryFile: wing B 1_001.pdf14 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: wing B1_001.pdf11 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: B1.pdf10 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: B1.pdf10 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B1.pdf13 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RZ Wing B1_001.pdf15 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: B1.pdf11 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Wing B1_001.pdf4 Jan 2024
Layout approvalFile: Drawing - B1_1_compressed - ]Marking.pdf27 Jun 2023
Layout approvalFile: Drawing - B1_2_compressed - Marking.pdf27 Jun 2023
Copy of Layout Approval (in case of layout)File: Drawing - B1_1_compressed - ]Marking.pdf27 Jun 2023
Copy of Layout Approval (in case of layout)File: Drawing - B1_2_compressed - Marking.pdf27 Jun 2023
Copy of the legal title reportFile: 2_10 Title report _26 06 2023.pdf26 Jun 2023
Other - LegalFile: 24_Other _ Legal Declaration for Plot area in B1.pdf26 Jun 2023
Other - LegalFile: VPPL DA-WithAnnexures_Part-1_1-28.pdf26 Jun 2023
Other - LegalFile: VPPL DA-WithAnnexures_Part-2_29-41.pdf26 Jun 2023
Other - LegalFile: VPPL DA-WithAnnexures_Part-3_42-55.pdf26 Jun 2023
Other - LegalFile: VPPL DA-WithAnnexures_Part-4_56-67.pdf26 Jun 2023
Other - LegalFile: VPPL DA-WithAnnexures_Part-5_68-77.pdf26 Jun 2023
Other - LegalFile: VPPL DA-WithAnnexures_Part-6_78-86.pdf26 Jun 2023
Other - LegalFile: JDA _VPPL WCIPL_128_6.pdf26 Jun 2023
Other - LegalFile: Marathon DA_Registered-Part-1_1-24.pdf26 Jun 2023
Other - LegalFile: Marathon DA_Registered-Part-2_25-47.pdf26 Jun 2023
Other - LegalFile: Marathon DA_Registered-Part-3_48-66.pdf26 Jun 2023
Other - LegalFile: Marathon DA_Registered-55.pdf26 Jun 2023
Other - TechnicalFile: B1 Declaration - 29th May 2023.pdf16 Jun 2023
CERSAI detailsFile: 16 B1 CERSAI Report with undertaking.pdf13 Jun 2023
Proforma of Agreement for saleFile: 13_AFS - With Deviation in Yellow 13-06-23.pdf13 Jun 2023
Deviation Report with respect to model copy of AgreementFile: 30 Deviations Agreement For Sale-13-06-23 - B1.pdf13 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 17 FORM 3 (New Format) - B1_compressed.pdf9 Jun 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: 18 Disclosure of Interest in other Real Estate projects - Final - MMC.pdf9 Jun 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: 18 Disclosure of Interest in other Real Estate projects - Final - NM.pdf9 Jun 2023
Layout approvalFile: 05 Wadhwa ITP Rev Master Layout.pdf29 May 2023
Building plan approvalFile: Drawing - B1_3_compressed.pdf29 May 2023
Building plan approvalFile: Drawing - B1_4_compressed.pdf29 May 2023
Building plan approvalFile: Drawing - B1_5.pdf29 May 2023
Building plan approvalFile: Drawing - B1_6_compressed.pdf29 May 2023
Building plan approvalFile: Drawing - B1_7_compressed.pdf29 May 2023
Building plan approvalFile: Drawing - B1_8.pdf29 May 2023
Building plan approvalFile: Drawing - B1_9.pdf29 May 2023
Details of encumbrances concerned to FinanceFile: 3_ 4 Details of Encumbrances concerned to Legal and Finance - B1.pdf29 May 2023
Details of encumbrances concerned to LegalFile: 3_ 4 Details of Encumbrances concerned to Legal and Finance - B1.pdf29 May 2023
Copy of Layout Approval (in case of layout)File: 05 Wadhwa ITP Rev Master Layout.pdf29 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Drawing - B1_3_compressed.pdf29 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Drawing - B1_4_compressed.pdf29 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Drawing - B1_5.pdf29 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Drawing - B1_6_compressed.pdf29 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Drawing - B1_7_compressed.pdf29 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Drawing - B1_8.pdf29 May 2023
Building Plan Approval / NA Order for plotted developmentFile: Drawing - B1_9.pdf29 May 2023
Commencement Certificates / NA Order for plotted developmentFile: CIDCO_NAINA_Panvel_vardoli_ITP_BP-236_Amended perm_585_SAP_162_Amm4_CCLetter (1).pdf29 May 2023
Declaration about Commencement CertificateFile: 8 Declaration Commencement Certificate - format D - B1.pdf29 May 2023
Proforma of Allotment letterFile: 14 ALLOTMENT LETTER - B1.pdf29 May 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 29 Separate 70 Account - B1.pdf29 May 2023
Deviation Report with respect to Allotment letterFile: 31 Deviations Allotment Letter B1.pdf29 May 2023
PAN CardFile: 01 PAN Card.pdf24 May 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Wise City, South Block Phase I, Plot RZ8 Building 1 Wing A1Wadhwa Wise City253CompletedDec 2026Sep 2023

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Wise City RZ8 Wing B1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Wadhwa Wise City5,900+ in Raigarh

2 kmWise City RZ8 Wing B1Completed 5Lapsed / revoked 2Other 21Dot size: filed unitsN

Filed coordinates, straight-line distance. 28 registered projects within 2 km.

Builder: Wadhwa Construction and infrastructure Private Limited

Wadhwa Construction and Infrastructure Private Limited has 30 registrations on MahaRERA, including Wise City, South Block Phase I, Plot RZ8 Building 5 Wing D1 and Wise City, South Block Phase I, Plot RZ8 Building 1 Wing A1. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that Wise City RZ8 Wing B1 shows as de-registered on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Wise City RZ8 Wing B1 is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Wise City RZ8 Wing B1?

The registered promoter entity is Wadhwa Construction and infrastructure Private Limited, a company as per the filing. Its CIN U70109MH2000PTC129871 and GSTIN 27AAACW5097J1ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Wise City RZ8 Wing B1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Wise City RZ8 Wing B1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Wise City RZ8 Wing B1?

The professionals named in the filing: Architect: Hiten Sethi Associates; Engineer: Million Jobs Private Limited; Chartered Accountant: S.M.BHAT & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Wise City RZ8 Wing B1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Wise City RZ8 Wing B1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Wise City RZ8 Wing B1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.