ReraGenieLog inGet a buyer report

Home / Browse projects / Raigarh, Maharashtra / Wise City RZ-03 Plotted Development

Registration lapsed No litigation declared Plotted project

Wise City RZ-03 Plotted Development

By Wadhwa Construction and Infrastructure Private Limited

RG-MH-93868 · RERA P52000048906 · Last updated on MahaRERA portal: 14 Jan 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 2 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
11 of 110Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 87 documents Report an error

Wise City RZ-03 Plotted Development is a Plotted project by Wadhwa Construction and Infrastructure Private Limited in Raigarh, Maharashtra, registered with MahaRERA as P52000048906 on 24 Jan 2023. Possession was promised by 31 Dec 2025 and is now 10 months past that date. 99 of the 110 units on this registration are recorded sold or booked. 2 complaints are on record with the regulator.

At a glance

Project

  • NameWise City RZ-03 Plotted Development
  • TypePlotted
  • Location
    • 36m DP road
    • Wise City ITP
    • Wardoli
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000048906
  • ReraGenie IDRG-MH-93868

Builder

  • NameWadhwa Construction and Infrastructure Private Limited
  • Entity typeCompany
  • CINU70109MH2000PTC129871
  • GSTIN27AAACW5097J1ZU
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • DirectorsNavin Amarlal Makhija, Manohar Moolchand Chhabria, Navin Amarlal Makhija, Manohar Moolchand Chhabria
  • Other registrations29 more →
  • Completed7 of 30
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

10 months past promisethis monthRegisteredJan 2023PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on24 Jan 2023
  • Promised completion31 Dec 2025
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed87 files

Current status

90%99 of 110 units booked
77.2%Work done, per cost certificate

Figures as on 14 Jan 2026, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 14 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes90%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes75%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area28,830 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Valuable Properties Private LimitedMumbai SuburbanMumbai Suburban

Approvals and building plan

Sanctioning authorityCIDCO-Navi Mumbai Airport Influence Notified Area(NAINA)
Permissible FSI32427.48

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKrystal Bldg, Waterfield road, Bandra west 400050
Estimated costRs 3.24 cr
Cost incurredRs 2.50 cr
Work done77.23%
BuildingWingEstimatedIncurred
-NARs 3.24 crRs 2.50 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSpaceage Consultant Devayani Khadilkar
ArchitectVisionary Design Architects
EngineerMahimtura Consultants
EngineerMillion Jobs Private Limited
Chartered AccountantSM Bhat and Associates
Chartered AccountantS M Bhat and associates
PartnerRole in project
Wadhwa Construction and Infrastructure Private Limited-

Litigation declared7

CaseCourtStatus
RCS 182/2014/2014Civil Judge PanvelMatter not related to this Project Inadvertently added here
RCS 259/2015/2015Civil Judge PanvelPending
SCS 40/2016/2016Civil Judge PanvelMatter not related to this Project Inadvertently added here
SCS 279/2016/2016Civil Judge PanvelMatter not related to this Project Inadvertently added here
SCS 48/2014/2014Civil Judge PanvelPending
SCS 421/2014/2014Civil Judge PanvelPending
SCS 227/2009/2009Civil Judge PanvelPending

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC12500572Shiv Shankar RahaWadhwa Construction and Infrastructure Private Limited19/02/2025
CC12501181Ganesh Shankar ShilimkarWadhwa Construction and Infrastructure Private Limited09/04/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 May 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Jan 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Jan 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed87

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 87 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 SIGNED.pdf14 Jan 2026
Withdrawal Update Form 1File: RZ-03.pdf14 Jan 2026
Withdrawal Update Form 1File: RZ-03.pdf14 Jan 2026
Withdrawal Update Form 2File: RZ-03 FORM 2 JUN 24.pdf14 Jan 2026
Withdrawal Update Form 2File: RZ - 03.pdf14 Jan 2026
Withdrawal Update Form 2File: RZ - 03.pdf14 Jan 2026
Withdrawal Update Form 3File: Form_3_RZ03 - Final.pdf14 Jan 2026
Withdrawal Update Form 3File: Form_3_RZ03 - Final.pdf14 Jan 2026
Withdrawal Update Form 3File: Form_3_RZ03 - Final.pdf14 Jan 2026
Commencement Certificates / NA Order for plotted developmentFile: CIDCO_NAINA_LT-00594_2023_Amm1_CCLetter.pdf10 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: RZ-02-03_CC Letter.pdf10 Mar 2025
Architect’s Certificate on Completion of Project (Form 4)File: RZ-03 FORM 4.pdf23 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RZ - 03.pdf14 Nov 2024
Disclosure of sold/ booked inventoryFile: RZ-03.pdf13 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form_3_RZ03 - Final.pdf12 Nov 2024
Disclosure of sold/ booked inventoryFile: RZ-03.pdf12 Nov 2024
Disclosure of sold/ booked inventoryFile: RZ-03.pdf12 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RZ-03-compressed.pdf9 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form_3_RZ03 - Final.pdf7 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RZ-03 FORM 2 JUN 24.pdf7 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form-5 RZ03 FY 2023-24.pdf7 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RZ-03 FORM 2 MARCH - 24.pdf14 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 MAR-24 RZ-03.pdf10 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SIGNED.pdf2 Aug 2024
Disclosure of sold/ booked inventoryFile: RZ 03_001 sold inventory.pdf24 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RZ 03 _001 FORM 2.pdf10 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RZ 03_001 Form 3.pdf10 Jul 2024
Disclosure of sold/ booked inventoryFile: RZ 03_001.pdf14 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: RZ 03_001.pdf11 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RZ-03.pdf10 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: wise city RZ 03_001.pdf9 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RZ 03 signed form 1.pdf15 Apr 2024
Details of encumbrances concerned to FinanceFile: RZ03_Plotted Development.pdf14 Feb 2024
Details of encumbrances concerned to LegalFile: RZ03_Plotted Development.pdf14 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RZ 03 Form 5 (2022-23).pdf12 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RZ-03_001.pdf11 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RZ-03_001.pdf4 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Architect Certificate_RZ-03 Jul-23.pdf11 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 EngineerCert_RZ-03_Jul 23.pdf11 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Revised Budget RZ03 Signed.pdf11 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 RZ- 3 Plotted Development - 31st May 2023.pdf17 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RZ-3 ENGINEER CERTIFICATE FORM 2.pdf17 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 RZ 3 - May - 2023_new.pdf17 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: RZ-03_001.pdf11 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RZ-03.pdf19 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 RZ-3.pdf19 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Completion certificate RZ-3.pdf16 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: RZ-02.pdf16 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: RZ-03.pdf16 May 2023
Disclosure of sold/ booked inventoryFile: RZ-03.pdf16 May 2023
Copy of the legal title reportFile: RZ-03 Litigation letter with Plaints.pdf2 May 2023
Proforma of Agreement for saleFile: AFS Plotted Development RERA Format with Annexures _8Feb23_compressed.pdf13 Feb 2023
Details of encumbrances concerned to FinanceFile: Declaration of Encumbrances for Legal and Finance RZ-03.pdf6 Feb 2023
Details of encumbrances concerned to LegalFile: Declaration of Encumbrances for Legal and Finance RZ-03.pdf6 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other Real Estate projects.pdf18 Jan 2023
Layout approvalFile: RZ-02-03 Layout Approval 1-2.pdf17 Jan 2023
Building plan approval or NA orderFile: NA not required 12-12-22_compressed.pdf17 Jan 2023
Copy of Layout Approval (in case of layout)File: RZ-02-03 Layout Approval 1-2.pdf17 Jan 2023
Building Plan Approval / NA Order for plotted developmentFile: NA not required 12-12-22_compressed.pdf17 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: CIDCO_NAINA_LT-00594_2023_CCLetter.pdf17 Jan 2023
Declaration about Commencement CertificateFile: Declaration for CC RZ-03.pdf17 Jan 2023
Other - LegalFile: VPPL DA-WithAnnexures_Part-1_1-28.pdf22 Dec 2022
Other - LegalFile: VPPL DA-WithAnnexures_Part-2_29-41.pdf22 Dec 2022
Other - LegalFile: VPPL DA-WithAnnexures_Part-3_42-55.pdf22 Dec 2022
Other - LegalFile: VPPL DA-WithAnnexures_Part-4_56-67.pdf22 Dec 2022
Other - LegalFile: VPPL DA-WithAnnexures_Part-5_68-77.pdf22 Dec 2022
Other - LegalFile: VPPL DA-WithAnnexures_Part-6_78-86.pdf22 Dec 2022
Other - LegalFile: RZ03 Plot Numbers highlighted.pdf22 Dec 2022
Other - LegalFile: Marathon DA_Registered-Part-1_1-24.pdf22 Dec 2022
Other - LegalFile: Marathon DA_Registered-Part-2_25-47.pdf22 Dec 2022
Other - LegalFile: Marathon DA_Registered-Part-3_48-66.pdf22 Dec 2022
Copy of the legal title reportFile: TITLE REPORT PANVEL IN RERA FORMAT-FurtherRevised.pdf21 Dec 2022
Details of encumbrances concerned to FinanceFile: Details of Encumbrance related to Legal and Finance for RZ-03.pdf12 Dec 2022
Details of encumbrances concerned to LegalFile: Details of Encumbrance related to Legal and Finance for RZ-03.pdf12 Dec 2022
Proforma of Agreement for saleFile: AFS Plotted Development RERA Format-12Dec2022.pdf12 Dec 2022
Deviation Report with respect to model copy of AgreementFile: Deviation to AFS 12-12-22.pdf12 Dec 2022
Other - LegalFile: VPPL Letter RZ03.pdf12 Dec 2022
CERSAI detailsFile: CERSAI merged.pdf7 Dec 2022
Proforma of Allotment letterFile: ALLOTMENT LETTER-RZ03.pdf7 Dec 2022
Deviation Report with respect to Allotment letterFile: Deviation Allotment.pdf7 Dec 2022

How this compares with Raigarh

90%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is among them

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Wise City RZ-03 Plotted Development on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Wise City ITP5,900+ in Raigarh

2 kmWise City RZ-03 Plotted Completed 10Lapsed / revoked 9Other 19Dot size: filed unitsN

Filed coordinates, straight-line distance. 38 registered projects within 2 km.

Builder: Wadhwa Construction and Infrastructure Private Limited

Wadhwa Construction and Infrastructure Private Limited has 30 registrations on MahaRERA, including Wise City, South Block Phase I, Plot RZ8 Building 5 Wing D1 and Wise City, South Block Phase I, Plot RZ8 Building 1 Wing A1. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What does it mean that Wise City RZ-03 Plotted Development shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Wise City RZ-03 Plotted Development is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Wise City RZ-03 Plotted Development?

The registered promoter entity is Wadhwa Construction and Infrastructure Private Limited, a company as per the filing. Its CIN U70109MH2000PTC129871 and GSTIN 27AAACW5097J1ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Wise City RZ-03 Plotted Development?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Wise City RZ-03 Plotted Development?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Wise City RZ-03 Plotted Development?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Wise City RZ-03 Plotted Development?

The professionals named in the filing: Architect: Spaceage Consultant Devayani Khadilkar; Architect: Visionary Design Architects; Engineer: Mahimtura Consultants; Engineer: Million Jobs Private Limited; Chartered Accountant: SM Bhat and Associates; Chartered Accountant: S M Bhat and associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Wise City RZ-03 Plotted Development?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Wise City RZ-03 Plotted Development. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Wise City RZ-03 Plotted Development to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.