Raheja Universal (Pvt.) Ltd. has 17 registrations in this build, including Raheja Imperia - I and Raheja Exotica Verona. Its filings disclose 13 earlier MahaRERA projects: 6 of 12 past projects completed on time.

17Registrations in this build
13Past projects disclosed
on timeMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
Raheja Imperia - IMaharashtra--Completed
Raheja Exotica VeronaMumbai Suburban, Maharashtra13689%Registered
Tesla - Building No.2Thane, Maharashtra324100%Completed
Raheja Exotica DowntownMumbai Suburban, Maharashtra100%Registered
Raheja Solaris-1Thane, Maharashtra441100%Registered
Raheja Imperia IIMaharashtra1100%Registered
Raheja Solaris-2Thane, Maharashtra27699%Registered
Raheja Prime-1Thane, Maharashtra54894%Registered
Raheja Exotica SienaMumbai Suburban, Maharashtra394100%Registered
Raheja Solaris-3Thane, Maharashtra268100%Registered
Raheja Exotica CyprusMumbai Suburban, Maharashtra26681%Registered
Raheja Lunaris-1 - CallistoThane, Maharashtra59859%Registered
Raheja Prime-2Thane, Maharashtra89541%Registered
Raheja Tesla-3 (Synova)Thane, Maharashtra2818%Registered
Raheja Atlantis-1Thane, Maharashtra14612%Registered
Raheja Lunaris-2Thane, Maharashtra7600%Registered
Raheja Lunaris-4Thane, Maharashtra3360%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Raheja Reflection Plaza
23 Feb 201223 Feb 2012On time
Raheja Xion
30 Apr 201317 Apr 2013On time
Raheja Exotica - Amalfi Sicily and Capri - Phase - III
30 Apr 201327 Jun 2014+14 months
Raheja Reflections - Serenity
31 May 20141 Oct 2014+4 months
Raheja Waterfront - Atlantic
31 Dec 20142 Mar 2016+14 months
Raheja Waterfront - Pacific
31 Dec 201426 Apr 2017+28 months
Raheja Reflections - Eternity
31 Mar 201623 Mar 2016On time
Raheja Reflections - Odyssey
31 Jan 201711 Apr 2017+2 months
Raheja Ridgewood
31 Mar 201724 Apr 2017+1 months
Raheja Exotica - Sorento 5A
31 Oct 201727 Apr 2017On time
Raheja Exotica - Sorento 5B
31 Oct 201727 Apr 2017On time
Tesla Building No 1 - Formerly known as EDISON
20 Apr 201820 Apr 2018On time

Frequently asked questions

How do I verify Raheja Universal (Pvt.) Ltd. as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN L17110MH1973PLC019786 and GSTIN 22AAAAA0000A1Z5 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Raheja Universal (Pvt.) Ltd.?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.