Home / Browse projects / Thane, Maharashtra / Yuvan Prime

Registered No litigation declared Residential / Group Housing project

Yuvan Prime

By Ranjana Enterprises

RG-MH-33267 · RERA P51700080620 · Last updated on MahaRERA portal: 28 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
May 2028Possession promisedmoved 12 months from the original
2 of 33Construction stages doneacross 3 buildings; furthest along: Excavation, 0%
116 of 116Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 55 documents Report an error

Yuvan Prime is a Residential / Group Housing project by Ranjana Enterprises in Thane, Maharashtra, registered with MahaRERA as P51700080620 on 23 Jun 2025. Possession is promised by 31 May 2028. The completion date has moved by 12 months from the original filing. 0 of the 116 units on this registration are recorded sold or booked, and 2 of 33 construction stages are filed complete.

At a glance

Project

  • NameYuvan Prime
  • TypeResidential / Group Housing
  • Location
    • Kewani Dive
    • Bhiwandi
    • Kewani
    • Thane
    • 421302
  • Pincode421302
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700080620
  • ReraGenie IDRG-MH-33267

Builder

  • NameRanjana Enterprises
  • Entity typePartnership

Key dates

this monthRegisteredJun 2025First promiseMay 2027Revised toMay 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on23 Jun 2025
  • Promised completion31 May 2028
  • Revised completionRevised to 31 May 2028 (originally 31 May 2027)
  • Buildings3 building records
  • Documents filed55 files

Current status

0%0 of 116 units booked
1.4%Work done, per cost certificate

Figures as on 28 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Yuvan Prime -A wingNA8849756
Yuvan Prime- B wingNA8830030
Yuvan Prime-C wingNA8830030

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 28 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Excavation, at 0%.

Yuvan Prime -A wing0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Yuvan Prime- B wing9%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Yuvan Prime-C wing9%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 28 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed141

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots141
Closed/Covered2
Open Space139
BuildingClosed/CoveredOpen SpaceTotal
Yuvan Prime -A wing0139139
Yuvan Prime- B wing101
Yuvan Prime-C wing101

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,910 sq m
Land owned byNot the promoter
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on13 Aug 2025
LandownerVillageDistrict
Madhav MehendaleThane (M Corp.)Thane
Shriram MehendaleThane (M Corp.)Thane
Vandana Shriram MehendaleThane (M Corp.)Thane

Approvals and building plan

Sanctioning authorityMumbai Metropolitan Region Development Authority
Permissible FSI4302.1
Proposed, not sanctioned4,253 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchICICI Bank Ltd., Shop No.6, Pathare Building, Gokhale Road, Naupada, Thane W, Thane Maharashtra.400602
Estimated costRs 6.40 cr
Cost incurredRs 8.80 lakh
Work done1.38%
BuildingWingEstimatedIncurred
Yuvan Prime -A wingNARs 3.10 cr-
Yuvan Prime- B wingNARs 1.60 crRs 2.00 lakh
Yuvan Prime-C wingNARs 1.60 crRs 6.80 lakh
-NARs 10.00 lakh-

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRight Angle Architects & Interior Designer
EngineerAjay Mahale
Chartered AccountantAJRR & Associates LLP
PartnerRole in project
Ranjana Enterprises-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA07042620572May 2027 → May 2028

Reason as filed by the promoterThe project execution has been impacted due to ongoing discussions and negotiations with the landowners regarding revision in the agreed consideration structure, specifically in relation to allocation of additional flats under the development arrangement. The proposed changes necessitated mutual deliberations, alignment on commercial terms, and corresponding adjustments to the project configuration and documentation. This process, being critical to safeguarding the interests of all stakeholders and ensuring compliance with applicable regulatory provisions, has resulted in a delay in the planne

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Jul 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Jul 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Aug 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Jul 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 May 2028

Documents filed55

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf28 Jul 2026
Withdrawal Update Form 2File: Form 2.pdf28 Jul 2026
Withdrawal Update Form 3File: Yuvan Prime - Form 3 - April to June 2026.pdf28 Jul 2026
Withdrawal Update Form 1File: Ranjana Enterprises - Form 1 - Jan to March 26.pdf6 May 2026
Withdrawal Update Form 2File: Ranjana Enterprises - From 2 - Jan to March 26.pdf6 May 2026
Withdrawal Update Form 3File: Ranjana Enterprises - From 3 - Jan to March 26.pdf6 May 2026
Withdrawal Update Form 1File: Ranjana Enterprises - Form 1 - Dec 2025.pdf24 Mar 2026
Withdrawal Update Form 2File: Ranjana Enterprises - Form 2 - Dec 2025.pdf24 Mar 2026
Withdrawal Update Form 3File: Ranjana Enterprises Form 3 - Q3..pdf24 Mar 2026
Withdrawal Update Form 1File: Ranjana Enterprises - Form 1 - Sept 25.pdf12 Nov 2025
Withdrawal Update Form 2File: Ranjana Enterprises - Form 2 - Sept 2025.pdf12 Nov 2025
Withdrawal Update Form 3File: Ranjana Enterprises - Form 3 - Sept 2025.pdf12 Nov 2025
Withdrawal Update Form 1File: Ranjana Enterprises - form 1 - April to june 25.pdf3 Oct 2025
Withdrawal Update Form 2File: Ranjana Enterprises - Form 2 April to June 25.pdf3 Oct 2025
Withdrawal Update Form 3File: Ranjana Enterprises - Form 3 - April to June 25.pdf3 Oct 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ranjana Enterprises Form 3_compressed.pdf6 Jun 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Landowner Undertaking.pdf3 May 2025
Details of encumbrances concerned to FinanceFile: Finance_ No Encumbrances.pdf2 May 2025
Details of encumbrances concerned to FinanceFile: Legal _ No Encumbrances.pdf2 May 2025
Details of encumbrances concerned to LegalFile: Legal _ No Encumbrances.pdf2 May 2025
Details of encumbrances concerned to LegalFile: Finance_ No Encumbrances.pdf2 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ranjana Enterprises - Yuvan Prime Form 1 - Reg.pdf30 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Ranjana Enterprises Form 2 Engineer -Reg.pdf30 Apr 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf14 Nov 2024
Other - LegalFile: Declaration cum undertaking_ yuvan prime.pdf28 Oct 2024
Details of encumbrances concerned to FinanceFile: Yuvan Prime RERA NO ENCUMBRANCES.pdf26 Oct 2024
Details of encumbrances concerned to LegalFile: Yuvan Prime RERA NO ENCUMBRANCES.pdf26 Oct 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B Bank 08082024.pdf24 Oct 2024
Proforma of Allotment letterFile: ALLOTMENT LETTER pdF.pdf15 Oct 2024
Details of encumbrances concerned to FinanceFile: Declaration of No Encumbrances Concerned to Legal for project Yuvan Prime.pdf13 Aug 2024
CERSAI detailsFile: CERSAI- RERA YUVAN PRIME.pdf13 Aug 2024
Details of encumbrances concerned to LegalFile: Declaration of No Encumbrances Concerned to Legal for project Yuvan Prime.pdf13 Aug 2024
PAN CardFile: Swapnil Sir_PAN CARD.pdf9 Aug 2024
PAN CardFile: RANJANA ENT PAN CARD.pdf9 Aug 2024
PAN CardFile: Ranjit Sir Pan card.pdf8 Aug 2024
Building plan approvalFile: Yuvan Prime Plan Pg 2_compressed.pdf7 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: Yuvan Prime Plan Pg 2_compressed.pdf7 Aug 2024
Disclosure for secured/unsecured finance availed for the projectFile: No Loan Declaration _ Ranjana Enterprises.pdf7 Aug 2024
Declaration about Commencement CertificateFile: Declaration About Commencement Certificate.pdf6 Aug 2024
Deviation Report with respect to Allotment letterFile: Deviation Report For allotment letter.pdf6 Aug 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report for Agreement for sale.pdf6 Aug 2024
Proforma of Agreement for saleFile: Draft Flat Sell.pdf6 Aug 2024
Layout approvalFile: Yuvan Prime Plan Pg 1.pdf10 Jul 2024
Building plan approvalFile: Yuvan Prime Plan Pg 2.pdf10 Jul 2024
Building plan approvalFile: Yuvan Prime Plan Pg 3.pdf10 Jul 2024
Copy of the legal title reportFile: Title Certicate 1.pdf10 Jul 2024
Copy of the legal title reportFile: Title Certifcate 2.pdf10 Jul 2024
Copy of Layout Approval (in case of layout)File: Yuvan Prime Plan Pg 1.pdf10 Jul 2024
Declaration in FORM BFile: Affidavit cum Declaration landowners.pdf10 Jul 2024
Declaration in FORM BFile: Affidavit cum Declaration Swapnil Sir.pdf10 Jul 2024
Commencement Certificates / NA Order for plotted developmentFile: Yuvan Prime CC.pdf10 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: Yuvan Prime Plan Pg 3.pdf10 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: Yuvan Prime Plan Pg 2.pdf10 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate organizations.pdf10 Jul 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest - Swapnil Sir.pdf10 Jul 2024

How this compares with Thane

0%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 12 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Yuvan Prime on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bhiwandi7,600+ in Thane

2 kmYuvan PrimeCompleted 6Lapsed / revoked 6Other 12Dot size: filed unitsN

Filed coordinates, straight-line distance. 24 registered projects within 2 km.

Builder: Ranjana Enterprises

Ranjana Enterprises has 1 registration on MahaRERA, including Yuvan Prime. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Yuvan Prime is delayed beyond 31 May 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Yuvan Prime?

The registered promoter entity is Ranjana Enterprises, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Yuvan Prime?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Yuvan Prime?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Yuvan Prime?

The professionals named in the filing: Architect: Right Angle Architects & Interior Designer; Engineer: Ajay Mahale; Chartered Accountant: AJRR & Associates LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Yuvan Prime?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Yuvan Prime. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Yuvan Prime to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.