Home / Browse projects / Pune, Maharashtra / YOOVIE HOMES

Registered No litigation declared Mixed project

YOOVIE HOMES

By ROHAN SUBHASH DESHMUKH

RG-MH-60946 · RERA P52100049608 · Last updated on MahaRERA portal: 13 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 21 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 21 months from the original
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 95%
13 of 17Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 101 documents Report an error

YOOVIE HOMES is a Mixed project by ROHAN SUBHASH DESHMUKH in Pune, Maharashtra, registered with MahaRERA as P52100049608 on 22 Feb 2023. Possession is promised by 31 Mar 2027. The completion date has moved by 21 months from the original filing. 4 of the 17 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameYOOVIE HOMES
  • TypeMixed
  • Location
    • PALLOD FARMS
    • BANER
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411045
  • Pincode411045
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100049608
  • ReraGenie IDRG-MH-60946

Builder

  • NameROHAN SUBHASH DESHMUKH
  • Entity typeIndividual

Key dates

this monthRegisteredFeb 2023First promiseJun 2025Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Feb 2023
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 30 Jun 2025)
  • Buildings1 building record
  • Documents filed101 files

Current status

24%4 of 17 units booked
88.5%Work done, per cost certificate

Figures as on 13 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
YOOVIE HOMESNA181617017

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 13 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 95%.

YOOVIE HOMES: 66% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 13 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes10%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes10%
Fire protection and fire safety requirementsYes10%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed108

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots108
Closed/Covered108

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,350 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityPUNE MUNICIPAL CORPORATION
Permissible FSI11406.2
Proposed, not sanctioned11,404 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch1194/8, RAMCHANDRA SABHA MANDAP, GHOLE ROAD, SHIVAJI NAGAR, PUNE 411005
Estimated costRs 46.80 cr
Cost incurredRs 41.40 cr
Work done88.46%
BuildingWingEstimatedIncurred
YOOVIE HOMESNARs 46.00 crRs 41.40 cr
-NARs 80.00 lakh-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSAMEER VALIMBE
EngineerVISHAL KATE
Chartered AccountantSUHAS SURESH SATHE
Chartered AccountantSHEETAL SATHE
PartnerRole in project
ROHAN SUBHASH DESHMUKH-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA16072502081Jun 2025 → May 2026

Reason as filed by the promoterDue to a shortage of labour and ongoing manpower issues, the construction progress has been slower than expected. Additionally, we have made upgrades to the development plan, including an increase in the number of flats, which required revisions in architectural drawings and approvals. These changes have impacted the overall timeline. In light of these factors, we kindly request an extension for the necessary compliance and submission under RERA.

EA29052621157Jun 2025 → Mar 2027

Reason as filed by the promoterThe project work has been completed up to 95%. However, due to slow market response and lower sales realization, the project faced temporary financial constraints. Further, shortage of skilled labour and delays in availability of construction manpower affected the progress of the remaining finishing and ancillary work. Therefore, the remaining work could not be completed within the stipulated timeline. The promoter is actively taking necessary steps to complete the balance work and is seeking an extension of 9 months to complete the entire project and obtain the Occupancy Certificate.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Feb 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Feb 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Apr 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed101

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 101 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect Certificate.pdf13 Jul 2026
Withdrawal Update Form 2File: Engg Certificate.pdf13 Jul 2026
Withdrawal Update Form 3File: Q 1 FORM 3.pdf13 Jul 2026
Withdrawal Update Form 1File: Arc Certificate form 1.pdf29 May 2026
Withdrawal Update Form 2File: Q 4Engineer Certificate Jan- March 2026.pdf29 May 2026
Withdrawal Update Form 3File: CA Certificate - form 3 - jan-feb-mar.pdf29 May 2026
Withdrawal Update Form 1File: Arc Certificate form 1.pdf27 May 2026
Withdrawal Update Form 2File: Q 4Engineer Certificate Jan- March 2026.pdf27 May 2026
Withdrawal Update Form 3File: CA Certificate - form 3.pdf27 May 2026
Building plan approvalFile: Sanction Plan - 1-8.pdf5 Apr 2026
Building plan approvalFile: Sanction Plan - 2-8.pdf5 Apr 2026
Building plan approvalFile: Sanction Plan - 3-8.pdf5 Apr 2026
Building plan approvalFile: Sanction Plan - 4-8.pdf5 Apr 2026
Building plan approvalFile: Sanction Plan - 5-8.pdf5 Apr 2026
Building plan approvalFile: Sanction Plan - 6-8.pdf5 Apr 2026
Building plan approvalFile: Sanction Plan - 7-8.pdf5 Apr 2026
Building plan approvalFile: Sanction Plan - 8-8.pdf5 Apr 2026
Withdrawal Update Form 1File: FORM 1 YOOVIE HOMES.pdf16 Jan 2026
Withdrawal Update Form 1File: FORM 1 YOOVIE HOMES.pdf16 Jan 2026
Withdrawal Update Form 2File: FORM 2 YOOVIE HOMES.pdf16 Jan 2026
Withdrawal Update Form 2File: FORM 2 YOOVIE HOMES.pdf16 Jan 2026
Withdrawal Update Form 3File: FORM 3 YOOVIE HOME.pdf16 Jan 2026
Withdrawal Update Form 3File: FORM 3 YOOVIE HOME.pdf16 Jan 2026
Withdrawal Update Form 1File: ARC Certificate WPC (1).pdf10 Oct 2025
Withdrawal Update Form 2File: FORM 2.pdf10 Oct 2025
Withdrawal Update Form 3File: CA Certificate.pdf10 Oct 2025
Form 2A (FY 2024-2025)File: ENGG FORM 2A 2025.pdf2 Sep 2025
Withdrawal Update Form 1File: ARC Certificate WPC (1).pdf29 Aug 2025
Withdrawal Update Form 2File: Engineer certificate.pdf29 Aug 2025
Withdrawal Update Form 3File: FORM 3 YOOVIE NEW.pdf29 Aug 2025
Form 1File: Architect Certificate_compressed (1).pdf30 Jul 2025
Form 2File: Engineer certificate.pdf30 Jul 2025
Form 3File: YOOVIE _page-0001.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Q 4 JAN TO MARCH.pdf30 Jul 2025
Form 5 (FY 2024-2025)File: 5 yoovie new.pdf30 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate_compressed.pdf17 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: YOOVIE _page-0001.pdf17 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate.pdf17 Apr 2025
Disclosure of sold/ booked inventoryFile: Q3 OCT TO DEC.pdf17 Apr 2025
Disclosure of sold/ booked inventoryFile: Q 4 JAN TO MARCH.pdf17 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: LATEST_page-0001.pdf30 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arch cert.pdf29 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca cert_compressed.pdf29 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: eng cert.pdf29 Jan 2025
Details of encumbrances concerned to FinanceFile: No Encombrances VSBL_0001 yoovie homes_page-0001 (1).pdf16 Jan 2025
Details of encumbrances concerned to LegalFile: No Encombrances VSBL_0001 yoovie homes_page-0001 (1).pdf16 Jan 2025
Building plan approvalFile: YOOVIE PLAN 1 NO_compressed.pdf28 Dec 2024
Building plan approvalFile: YOOVIE PLAN 2NO_compressed.pdf28 Dec 2024
Building plan approvalFile: YOOVIE PLAN 3 NO_compressed.pdf28 Dec 2024
Building plan approvalFile: YOOVIE PLAN 4 NO_compressed.pdf28 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH Q 4 JAN TO MARCH 2024.pdf28 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH Q1 APRIL TO JUNE 2024.pdf28 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH Q2 JULY TO SEP 2024.pdf28 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q 3 OCT TO DEC 2023_compressed.pdf28 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q 4 JAN TO MARCH 2024 OK_compressed.pdf28 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 2 Q1 APRIL TO JUNE 2024_compressed.pdf28 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 2 Q2 JULY TO SEP 2024_compressed.pdf28 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q 1 APRIL TO JUNE 2024 OK_compressed.pdf28 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q 2 JULY TO SEP yoohi home _compressed.pdf28 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Q 4 JAN TO MARCH.pdf28 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Q2 JULY TO SEP 2024.pdf28 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Q1 APRIL TO JUNE 2024.pdf28 Dec 2024
Commencement Certificates / NA Order for plotted developmentFile: CC 2019 YOOVIE.pdf28 Dec 2024
Commencement Certificates / NA Order for plotted developmentFile: CC 4-6-2024 YOOVIE.pdf28 Dec 2024
Commencement Certificates / NA Order for plotted developmentFile: CC 29-8-2024 YOOVIE_compressed (1).pdf28 Dec 2024
Building Plan Approval / NA Order for plotted developmentFile: YOOVIE PLAN 1 NO_compressed.pdf28 Dec 2024
Building Plan Approval / NA Order for plotted developmentFile: YOOVIE PLAN 2NO_compressed.pdf28 Dec 2024
Building Plan Approval / NA Order for plotted developmentFile: YOOVIE PLAN 3 NO_compressed.pdf28 Dec 2024
Building Plan Approval / NA Order for plotted developmentFile: YOOVIE PLAN 4 NO_compressed.pdf28 Dec 2024
Disclosure of sold/ booked inventoryFile: SOLD BOOK Q 2 2024 FINAL.pdf28 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A 2023 2024_compressed.pdf28 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form - 5 - apr 23 - mar 24 (2).pdf28 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARC Certificate WPC (1).pdf13 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Eng Certificate_2023_10_25.pdf13 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: q1.pdf13 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: q2.pdf13 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: q3.pdf13 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf29 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARC Certificate WPC.pdf28 Jul 2023
Disclosure of sold/ booked inventoryFile: Document1.pdf28 Jul 2023

How this compares with Pune

24%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 21 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep YOOVIE HOMES on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BANER13,700+ in Pune

2 kmYOOVIE HOMESCompleted 90Lapsed / revoked 35Other 120Dot size: filed unitsN

Filed coordinates, straight-line distance. 245 registered projects within 2 km.

Builder: ROHAN SUBHASH DESHMUKH

ROHAN SUBHASH DESHMUKH has 1 registration on MahaRERA, including YOOVIE HOMES. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if YOOVIE HOMES is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of YOOVIE HOMES?

The registered promoter entity is ROHAN SUBHASH DESHMUKH, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in YOOVIE HOMES?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for YOOVIE HOMES?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at YOOVIE HOMES?

The professionals named in the filing: Architect: SAMEER VALIMBE; Engineer: VISHAL KATE; Chartered Accountant: SUHAS SURESH SATHE; Chartered Accountant: SHEETAL SATHE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in YOOVIE HOMES?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About YOOVIE HOMES. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save YOOVIE HOMES to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.