Yogashree at Nanded City
By Nanded City Development & Construction Co. Ltd.
RG-MH-13078 · RERA P52100022562 · Last updated on MahaRERA portal: 8 Apr 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 40 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- All 19 completed earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Yogashree at Nanded City is a Residential / Group Housing project by Nanded City Development & Construction Co. Ltd. in Pune, Maharashtra, registered with MahaRERA as P52100022562 on 7 Oct 2019. Possession was promised by 30 Jun 2023 and is now 40 months past that date.
At a glance
Project
- NameYogashree at Nanded City
- TypeResidential / Group Housing
- Location
- Sinhagad Road
- Nanded Phata
- Nanded
- Haveli
- Pune
- 411068
- Pincode411068
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100022562
- ReraGenie IDRG-MH-13078
Builder
- NameNanded City Development & Construction Co. Ltd.
- Entity typeCompany
- GSTIN27AACCN2613H1ZQ
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- Managing DirectorSatish Dattatray Magar
- Other registrations20 more →
- Completed12 of 21
- No longer live4 lapsed, de-registered or revoked
- Declared earlier projects22 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on7 Oct 2019
- Promised completion30 Jun 2023
- Revised completionNone
- Buildings5 building records
- Documents filed29 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A | NA | 22 | 0 | 0 | 0 | 0 |
| B | NA | 22 | 0 | 0 | 0 | 0 |
| C | NA | 22 | 0 | 0 | 0 | 0 |
| D | NA | 22 | 0 | 0 | 0 | 0 |
| E | NA | 22 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 8 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Excavation, at 0%.
A0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
C0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
D0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
E0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities27
As on 8 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
| Play Area with Play Equipments | Yes | 0% |
| Town level restricted facilities like swimming pool tennis courts Gymnasium Skating rink Badminton C | Yes | 100% |
| Town level public assembly facilities like Amphitheatre | Yes | 100% |
| Town level Primary and High Schools ICSE and CBSE Board | Yes | 100% |
| Town level playgrounds excluding school playgrounds | Yes | 0% |
| Town level Gardens and Parks | Yes | 100% |
| Town level exclusive Fire Fighting Station | Yes | 100% |
| Town level community market | Yes | 100% |
| Town level Community Healthcare facilities | Yes | 0% |
| Town level 24 x 7 Centralized security system with CCTV coverage | Yes | 100% |
| Town level Roads Jogging Cycling Tracks Footpaths as per Proposed Land Use Plan | Yes | 86% |
| Prepaid meters for water and electricity | Yes | 0% |
Parking filed5
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| A | 1 | 1 |
| B | 1 | 1 |
| C | 1 | 1 |
| D | 1 | 1 |
| E | 1 | 1 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Arch Prakash Deshmukh |
| Architect | Arch Malay Deshmukh |
| Engineer | Prashant J Kanikdale |
| Engineer | Prashant Kanikdale |
| Chartered Accountant | SDB & Company |
| Chartered Accountant | D R Barve & Company |
| Partner | Role in project |
|---|---|
| Nanded City Development & Construction Co. Ltd. | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 7 Aug 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 7 Aug 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 7 Aug 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 7 Aug 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed29
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - 2024-2025.pdf | 8 Apr 2025 |
| Certificates of CA (Form 3)File: Form 3 - December 2024.pdf | 8 Mar 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Dec 2024.pdf | 8 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Dec 2024.pdf | 6 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Jun 2024.pdf | 6 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Sep 2024.pdf | 6 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - 2022-2023.pdf | 6 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - 2023-2024.pdf | 6 Dec 2024 |
| Certificates of CA (Form 3)File: Form 3 - Jun 2024.pdf | 5 Dec 2024 |
| Certificates of CA (Form 3)File: Form 3 - Sep 2024.pdf | 5 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - 2022-2023.pdf | 5 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - 2023-2024.pdf | 5 Dec 2024 |
| Details of encumbrancesFile: Encumbrance Certificate.pdf | 27 Aug 2019 |
| Declaration in FORM BFile: Affidavit cum Declaration.pdf | 27 Aug 2019 |
| Building plan approvalFile: Building A,B,D 1.pdf | 7 Aug 2019 |
| Building plan approvalFile: Building A,B,D 2.pdf | 7 Aug 2019 |
| Building plan approvalFile: Building C, E 1.pdf | 7 Aug 2019 |
| Building plan approvalFile: Building C, E 2.pdf | 7 Aug 2019 |
| Layout approvalFile: Layout Plan.pdf | 7 Aug 2019 |
| PAN CardFile: PAN Card- NCDCCL.pdf | 7 Aug 2019 |
| Copy of the legal title reportFile: Search Report.pdf | 7 Aug 2019 |
| Copy of Layout Approval (in case of layout)File: Layout Plan.pdf | 7 Aug 2019 |
| Building Plan Approval (IOD)File: Building A,B,D 1.pdf | 7 Aug 2019 |
| Building Plan Approval (IOD)File: Building A,B,D 2.pdf | 7 Aug 2019 |
| Building Plan Approval (IOD)File: Building C, E 1.pdf | 7 Aug 2019 |
| Building Plan Approval (IOD)File: Building C, E 2.pdf | 7 Aug 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 7 Aug 2019 |
| Certificates of CA (Form 3)File: CA Cerificate.pdf | 7 Aug 2019 |
| Proforma of Allotment letterFile: ATS Allotment Letter.pdf | 7 Aug 2019 |
Promoter's earlier projects22
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Aalaap - I at Nanded CityP52100055134 | Nanded Phata, Pune | 936 | Mar 2024 | Ongoing | Dec 2027 | Not due yet |
| Destination Center - IIP52100079788 | Nanded Phata, Pune | 56 | Mar 2025 | Ongoing | Dec 2026 | Not due yet |
| Bahaar at Nanded CityP52100049984 | Nanded Phata, Pune | 608 | Mar 2023 | Ongoing | Dec 2026 | Not due yet |
| Janaranjani - D Phase II at Nanded CityP52100047078 | Nanded Phata, Pune | - | Sep 2022 | Completed | Dec 2025 | Apr 2025 |
| Sur at Nanded CityP52100032686 | Nanded Phata, Pune | - | Jan 2022 | Completed | Aug 2025 | Apr 2025 |
| Rhythm III at Nanded CityP52100028650 | Nanded Phata, Pune | 121 | Mar 2021 | Certificate Signed | Sep 2024 | Feb 2024 |
| Rhythm II at Nanded CityP52100028623 | Nanded Phata, Pune | 87 | Mar 2021 | Certificate Signed | Sep 2024 | Feb 2024 |
| Rhythm I at Nanded CityP52100028606 | Nanded Phata, Pune | 79 | Mar 2021 | Certificate Signed | Sep 2024 | Feb 2024 |
| Kalashree at Nanded CityP52100021483 | Nanded Phata, Pune | - | Jul 2019 | Certificate Signed | May 2023 | Dec 2022 |
| Bageshree at Nanded CityP52100021465 | Nanded Phata, Pune | - | Jul 2019 | Certificate Signed | May 2023 | Dec 2022 |
| Pancham Phase II at Nanded City | Nanded City Sinhagad Road Pune 411068 | 496 | - | Completed | Apr 2021 | Jan 2021 |
| Janaranjani 5B at Nanded City | Nanded City Sinhagad Road Pune 411068 | 540 | - | Completed | Nov 2020 | Jun 2020 |
| Pancham Phase I at Nanded City | Nanded City Sinhagad Road Pune 411068 | 496 | - | Completed | Oct 2019 | Apr 2019 |
| Janaranjani 5A at Nanded City | Nanded City Sinhagad Road Pune 411068 | 540 | - | Completed | Aug 2019 | Aug 2019 |
| Sargam at Nanded City | Nanded City Sinhagad Road Pune 411068 | 1,736 | - | Completed | Mar 2019 | Jul 2018 |
| Madhuvanti at Nanded City | Nanded City Sinhagad Road Pune 411068 | 1,012 | - | Completed | Aug 2016 | Mar 2016 |
| Mangal Bhairav at Nanded City | Nanded City Sinhagad Road Pune 411068 | 1,672 | - | Completed | Dec 2015 | Oct 2015 |
| Sarang at Nanded City | Nanded City Sinhagad Road Pune 411068 | 1,144 | - | Completed | Nov 2015 | Oct 2015 |
| Asawari at Nanded City | Nanded City Sinhagad Road Pune 411068 | 1,936 | - | Completed | Oct 2015 | Aug 2015 |
| Shubhkalyan at Nanded City | Nanded City Sinhagad Road Pune 411068 | 528 | - | Completed | Sep 2015 | Mar 2015 |
| Lalit at Nanded City | Nanded City Sinhagad Road Pune 411068 | 792 | - | Completed | Apr 2015 | Dec 2014 |
| Destination Center I at Nanded City | Nanded City Sinhagad Road Pune 411068 | 272 | - | Completed | Apr 2015 | Mar 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 20 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 29 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Yogashree at Nanded City on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Nanded Phata13,700+ in Pune
Filed coordinates, straight-line distance. 268 registered projects within 2 km.
Aalaap - I at Nanded City
Nanded City Development & Construction Co.
Saajgiri
Nanded City Development & Construction Co.
Bahaar at Nanded City
Nanded City Development & Construction Co.
Melody I at Nanded City
Nanded City Development & Construction Co.
Dhanashree at Nanded City
Nanded City Development & Construction Co.
Rhythm III at Nanded City
Nanded City Development & Construction Co.
Builder: Nanded City Development & Construction Co. Ltd.
Nanded City Development & Construction Co. Ltd. has 21 registrations on MahaRERA, including Sargam at Nanded City and Pancham Phase I at Nanded City. Its filings disclose 22 earlier MahaRERA projects: declares 19 of 19 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Yogashree at Nanded City shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Yogashree at Nanded City is delayed beyond 30 Jun 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Yogashree at Nanded City?
The registered promoter entity is Nanded City Development & Construction Co. Ltd., a company as per the filing. Its GSTIN 27AACCN2613H1ZQ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Yogashree at Nanded City?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Yogashree at Nanded City?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Yogashree at Nanded City?
The professionals named in the filing: Architect: Arch Prakash Deshmukh; Architect: Arch Malay Deshmukh; Engineer: Prashant J Kanikdale; Engineer: Prashant Kanikdale; Chartered Accountant: SDB & Company; Chartered Accountant: D R Barve & Company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Yogashree at Nanded City?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.