Home / Browse projects / Palghar, Maharashtra / YESHWANT VINAYAK COMPLEX

Completed No litigation declared Residential / Group Housing project

YESHWANT VINAYAK COMPLEX

By SHREE CHINTAMANI DEVELOPERS

RG-MH-51744 · RERA P99000003231 · Last updated on MahaRERA portal: 6 Aug 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 47 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
May 2025Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
12 of 48Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 92 documents Report an error

YESHWANT VINAYAK COMPLEX is a Residential / Group Housing project by SHREE CHINTAMANI DEVELOPERS in Palghar, Maharashtra, registered with MahaRERA as P99000003231 on 5 Aug 2017. The registration is recorded completed; possession was promised by 30 May 2025. The completion date has moved by 47 months from the original filing. 36 of the 48 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.

At a glance

Project

  • NameYESHWANT VINAYAK COMPLEX
  • TypeResidential / Group Housing
  • Location
    • Chandansar
    • Virar East
    • Kopri
    • Vasai
    • Palghar
    • 401305
  • Pincode401305
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000003231
  • ReraGenie IDRG-MH-51744

Builder

  • NameSHREE CHINTAMANI DEVELOPERS
  • Entity typePartnership
  • PartnersJYOTI ARUN VAIDYA, AJIV YESHAWANT PATIL, AMIT BALKRISHNA PATIL
  • Other registrations4 more →
  • Completed3 of 5
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

this monthRegisteredAug 2017First promiseJun 2021Revised toMay 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on5 Aug 2017
  • Promised completion30 May 2025
  • Revised completionRevised to 30 May 2025 (originally 30 Jun 2021)
  • Buildings1 building record
  • Documents filed92 files

Current status

75%36 of 48 units booked

Figures as on 6 Aug 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLDG NO 2, VAKRATUNDNA14748048

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

BLDG NO 2, VAKRATUND: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 6 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed5

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots5
Closed/Covered1
Open Space4

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,793 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
Declared on27 May 2025

Approvals and building plan

Sanctioning authorityVasai-Virar City Municipal Corporation (VVCMC)
Permissible FSI2793.33
Proposed, not sanctioned1,629 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchThakur Arcade above VIVA Super market opp Virar Station Virar west 401303

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANJAY NARANG
ArchitectEN CON
EngineerHARESH PATEL
EngineerSanjay S Narang
Chartered AccountantPALLAVI P BARAPATRE
PartnerRole in project
SHREE CHINTAMANI DEVELOPERS-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000010541Jun 2021 → Dec 2022

Reason as filed by the promoterDue to the present pandemic and frequent lockdown and the shortage of the building materials and the shortage of skilled workers construction of project works largely affected and the project was not completed in time(only 65% work is completed)and we are expecting some more delay in the project completion. So we request to you to extend the project completion date up to 31/12/2022. All necessary documents uploaded for your kind perusal.

EXT99000017048Jun 2021 → Dec 2023

Reason as filed by the promoterWe would like to inform you that due the frequent lockdown and shortage building materials and shortage of skilled workers construction of project works largely affected and project was not able to complete in time and we are expecting some more delay in the project completion. Therefore, we request you to extend the project completion date up to 31/12/2023. We have completed 80-85 % project.

EXT99000019248Jun 2021 → Oct 2024

Reason as filed by the promoterWe would like to inform that the period 2019-22 was not favourable for our real-state sectors due to the covid-19 pandemic, frequent lockdown, shortage of building materials & shortage of skilled workers and construction of our projects were largely affected and the project was not able to complete in time. We expect some more delay in completion of our project. We Have completed 92% work of the project. So we request you to extend the project completion upto 31/10/2024.

EXT99000027673Jun 2021 → May 2025

Reason as filed by the promoterWe would like to inform that the period 2019-2022 was not favorablr for re-estate sector due to Covid-9 pandemic, frequent lockdown, shortage of construction materials and shortage of skilled workers and construction of project work were largely affected and the project was not able to complete in time and we are expecting some more delay in getting the occupancy certificate(OC) from VVCMC. We in the process of getting the Occupancy certificate from the VVCMC.. Therefore, we request you to extend the project completion upto 30/05/2025.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed92

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 92 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2024-2025)File: Form 2A shree chintamani (2).pdf6 Aug 2025
Occupational CertificateFile: Occupancy Certificate sHREE cHINTAMANI.pdf6 Aug 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 chintamani March 2025.pdf18 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Chintamani March 2025.pdf18 Apr 2025
Certificates of CA (Form 3)File: Form-3 June 2024 Chintamani.pdf24 Feb 2025
Certificates of CA (Form 3)File: Form 3 Setember 2024 chintamani_compressed.pdf24 Feb 2025
Certificates of CA (Form 3)File: Form 3 December 2024 chintamani_compressed.pdf24 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 chintamani (2).pdf24 Feb 2025
Declaration in FORM BFile: FORM B Chintamani (2).pdf21 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 September 2024 Chintamani.pdf21 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 December 2024 Chintamani (2).pdf21 Feb 2025
Certificates of CA (Form 3)File: Form 3 March 2024 Chintamani_compressed.pdf21 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 September 2024 Chintamani.pdf21 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 December 2024 Chintamani.pdf21 Feb 2025
Disclosure of sold/ booked inventoryFile: sold booked inventory chintamani.pdf21 Feb 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure Of Interest in other Real Estate Organisations_compressed.pdf21 Feb 2025
Details of encumbrances concerned to FinanceFile: EncumbrancetTo Lega Chintamanil.pdf19 Feb 2025
Declaration about Commencement CertificateFile: Declaration About CC Chintamani.pdf19 Feb 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A Seprate Bank Account Chintamani.pdf19 Feb 2025
Details of encumbrances concerned to LegalFile: EncumbrancetTo Lega Chintamanil.pdf19 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 chintamani (3).pdf12 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 chintamani (3).pdf12 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form-2A Quality Accurance Certificate.pdf11 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1Annexure -A.pdf17 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Annexure -B.pdf17 May 2024
Declaration about Commencement CertificateFile: CC Declaration Chintamani.pdf7 Mar 2024
Declaration in FORM BFile: Form B Chintamani_compressed.pdf7 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Chintamani (2).pdf7 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Chintamani (2).pdf7 Mar 2024
Disclosure of sold/ booked inventoryFile: Sold Inventory Chintamani.pdf7 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 December 2023 CHINTAMANI.pdf12 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Annexure A.pdf17 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Annexure B Form 2 Engineer Certificate.pdf17 Jan 2024
Certificates of CA (Form 3)File: SHREE CHINTAMANI FORM 3.pdf17 Jan 2024
Declaration in FORM BFile: Form B Declaration CHINTAMANI_compressed.pdf5 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2023 CHINTAMANI_compressed.pdf5 Jul 2023
Disclosure of sold/ booked inventoryFile: Sold inventory Chintamani_compressed.pdf5 Jul 2023
Certificates of CA (Form 3)File: Form 3 2023 CHINTAMANI_compressed.pdf4 Jul 2023
Certificates of CA (Form 3)File: Form 3 062023 shree chntamani.pdf1 Jul 2023
Declaration about Commencement CertificateFile: Declaration CC shree chintamani.pdf26 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 shree chintamani_compressed.pdf26 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 shree chintamani_compressed.pdf26 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2021-22_compressed.pdf23 Jan 2023
Proforma of Agreement for saleFile: AFS Shree Chintamani.pdf23 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 chintamani_compressed.pdf20 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2 ENGINEER2023 chintamani.pdf19 Jan 2023
Certificates of CA (Form 3)File: Rera form 3 2023chntamani.pdf19 Jan 2023
Disclosure of sold/ booked inventoryFile: Flats Sold Unsold Inventory.pdf11 May 2022
Disclosure of sold/ booked inventoryFile: sold Inventory chntamani.pdf9 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Form 1 chintamani.pdf7 May 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Enginerr Form 2 chintamani.pdf7 May 2022
Certificates of CA (Form 3)File: Form-3 chintamani.pdf7 May 2022
Certificates of CA (Form 3)File: Form 3 shree chintamani dvlpr.pdf4 Mar 2022
CERSAI detailsFile: CERSAI_Search_Report_200231118533_For_Asset_Based_Search_25_02_2022_13_21_23_830.pdf25 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: shree chintamani architect 1 oct 2021.pdf2 Nov 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: shree chintamani Engineers 2 oct2021.pdf2 Nov 2021
Declaration about Commencement CertificateFile: CC Declaration chintamani.pdf24 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect 1 certificate.pdf24 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate.pdf24 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A FY 2019-20 Chintamani.pdf24 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A FY 2020-21 Chintamani.pdf24 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 1st qrtr June 2021 chitamani.pdf24 Aug 2021
Certificates of CA (Form 3)File: FORM 3 CA AUG 21 chintamani.pdf24 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 2A FY 2019-20 Chintamani.pdf24 Aug 2021
Disclosure of sold/ booked inventoryFile: INVENTORY.pdf21 Aug 2021
Declaration about Commencement CertificateFile: CC.pdf20 Aug 2021
Disclosure of sold/ booked inventoryFile: INVENTORY.pdf20 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form-5_17-18.pdf20 Aug 2021
Declaration about Commencement CertificateFile: CC-1.pdf26 Jul 2021
OtherFile: RERA__ALLOTEE_LETTER.pdf26 Jul 2021
PAN CardFile: pan card.pdf22 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: DOCrera engineer certi.pdf22 Jul 2021
Disclosure of sold/ booked inventoryFile: Customers Booking Inventory.pdf22 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form-5 March 19.pdf22 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form-5 March 20.pdf22 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form-5 31 March 21.pdf22 Jul 2021
Commencement Certificates / NA Order for plotted developmentFile: CC-1.pdf31 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH CERTI.pdf31 Mar 2018
Certificates of CA (Form 3)File: FORM 3 (2).pdf31 Mar 2018
Proforma of Allotment letterFile: AGREEMENT FOR SALE (1).pdf31 Mar 2018

How this compares with Palghar

75%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 47 months
26%of Palghar registrations have lapsed or been cancelledthis one is completed

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep YESHWANT VINAYAK COMPLEX on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Virar East3,200+ in Palghar

2 kmYESHWANT VINAYAK COMPLEXCompleted 52Lapsed / revoked 38Other 75Dot size: filed unitsN

Filed coordinates, straight-line distance. 165 registered projects within 2 km.

Builder: SHREE CHINTAMANI DEVELOPERS

SHREE CHINTAMANI DEVELOPERS has 5 registrations on MahaRERA, including CHINTAMANI RESIDENCY and YESHWANT VINAYAK COMPLEX. Its filings disclose 4 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if YESHWANT VINAYAK COMPLEX is delayed beyond 30 May 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of YESHWANT VINAYAK COMPLEX?

The registered promoter entity is SHREE CHINTAMANI DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in YESHWANT VINAYAK COMPLEX?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for YESHWANT VINAYAK COMPLEX?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at YESHWANT VINAYAK COMPLEX?

The professionals named in the filing: Architect: SANJAY NARANG; Architect: EN CON; Engineer: HARESH PATEL; Engineer: Sanjay S Narang; Chartered Accountant: PALLAVI P BARAPATRE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in YESHWANT VINAYAK COMPLEX?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About YESHWANT VINAYAK COMPLEX. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save YESHWANT VINAYAK COMPLEX to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.