Home / Browse projects / Palghar, Maharashtra / HARI RESIDENCY PHASE I

Registered No litigation declared Residential / Group Housing project

HARI RESIDENCY PHASE I

By LOTUS LAKSHMINARAYAN HOMES

RG-MH-50235 · RERA P99000015966 · Last updated on MahaRERA portal: 11 Jul 2025

Source: official MahaRERA filing

Red flags

  • 6 complaints at MahaRERA
  • Completion date moved by 56 months
  • 2 extensions taken
  • Encumbrance declared on the project land

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 56 months from the original
27 of 44Construction stages doneacross 4 buildings; furthest along: Staircases, 95%
176 of 361Units unsoldnot recorded sold or booked
6Complaints at MahaRERAon this registration
Jump to the 73 documents Report an error

HARI RESIDENCY PHASE I is a Residential / Group Housing project by LOTUS LAKSHMINARAYAN HOMES in Palghar, Maharashtra, registered with MahaRERA as P99000015966 on 10 Apr 2018. Possession is promised by 31 Dec 2027. The completion date has moved by 56 months from the original filing. 185 of the 361 units on this registration are recorded sold or booked, and 27 of 44 construction stages are filed complete. 6 complaints are on record with the regulator.

At a glance

Project

  • NameHARI RESIDENCY PHASE I
  • TypeResidential / Group Housing
  • Location
    • VEER SAVARKAR ROAD
    • KOPARI
    • CHANDANSAR
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401305
  • Pincode401305
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000015966
  • ReraGenie IDRG-MH-50235

Builder

  • NameLOTUS LAKSHMINARAYAN HOMES
  • Entity typePartnership
  • PartnersNIKUNJ PRAKASH SHAH, MANOJ JAGANNATH KORE

Key dates

this monthRegisteredApr 2018First promiseApr 2023Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on10 Apr 2018
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Apr 2023)
  • Buildings4 building records
  • Documents filed73 files

Current status

51%185 of 361 units booked
77.5%Work done, per cost certificate

Figures as on 11 Jul 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
HARI RESIDENCY PHASE I BUILDING NO 1 WING ANA161613317150
HARI RESIDENCY PHASE I BUILDING NO 1 WING BNA16169012102
HARI RESIDENCY PHASE I BUILDING NO 1 WING CNA88561167
HARI RESIDENCY PHASE 1 BUILDING NO 2NA7735742

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 11 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

27 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Staircases, at 95%.

HARI RESIDENCY PHASE I BUILDING NO 1 WING A80%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
HARI RESIDENCY PHASE I BUILDING NO 1 WING B35%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure55%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks15%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
HARI RESIDENCY PHASE I BUILDING NO 1 WING C82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
HARI RESIDENCY PHASE 1 BUILDING NO 282%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 11 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes20%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed128

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots128
Closed/Covered3
Open Space125
BuildingClosed/CoveredOpen SpaceTotal
HARI RESIDENCY PHASE I BUILDING NO 1 WING A14849
HARI RESIDENCY PHASE I BUILDING NO 1 WING B13435
HARI RESIDENCY PHASE I BUILDING NO 1 WING C14344

Land and ownership2

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area5,290 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared present
CERSAI search filedYes
Declared on15 Oct 2025
LandownerVillageDistrict
VINOD HARIBHAU JOSHIMumbai CityMumbai City
SUNIL HARIBHAU JOSHIKurlaMumbai Suburban

Approvals and building plan

Sanctioning authorityVVCMC
Permissible FSI10053.42
Proposed, not sanctioned4,778 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVirar east
Estimated costRs 23.99 cr
Cost incurredRs 18.59 cr
Work done77.46%
BuildingWingEstimatedIncurred
HARI RESIDENCY PHASE I BUILDING NO 1 WING ANARs 8.08 crRs 7.76 cr
HARI RESIDENCY PHASE I BUILDING NO 1 WING CNARs 7.92 crRs 7.60 cr
-NARs 3.60 crRs 39.23 lakh
HARI RESIDENCY PHASE I BUILDING NO 1 WING BNARs 2.64 crRs 1.15 cr
HARI RESIDENCY PHASE 1 BUILDING NO 2NARs 1.76 crRs 1.69 cr

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHAPE CONSULTANT
EngineerMUKESH KUMAR
Chartered AccountantASHWIN NAIR
PartnerRole in project
LOTUS LAKSHMINARAYAN HOMES-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000016519Apr 2023 → Apr 2024

Reason as filed by the promoterDue to Covid - 19 Pandemic, unable to complete the construction work by us before deadline declared by us and certificate given by you to us. Hence, we are requesting you to extend its deadline date by one more year that’s 30/04/2024. Please do the needful for the same.

EXT99000019846Apr 2023 → Dec 2027

Reason as filed by the promoterDUE TO SOME UNAVOIDABLE REASONS THE PROJECT COULD NOT BE COMPLETED ON TIME

Complaints filed with MahaRERA6

Case no.ComplainantRespondentFiled
CC006000000591184Dr prashant Ramrao PawarMr Nimish Shah, Lotus Laxminarayan Homes & Partners19/07/2024
CC006000000591212Kunal Vishnu SawantMr Nimish Shah, Lotus Laxminarayan homes & partners18/07/2024
CC006000000591273Pramod Madhukar BhoirMr Nimish Shah, Lotus Laxminarayan Homes & Partners22/07/2024
CC006000000591224Pramod hiraman patilMr Nimish Shah, Lotus Laxminarayan Homes &Partners19/07/2024
CC006000000591214MUKESHKUMAR AMARPAL MISHRAMr. nimesh dilip shah & partenar m/s.lotus lakshmi narayan homes21/07/2024
CC006000000591215sakshi gautam mohiteMr Nimish Shah, Lotus Laxminarayan Homes & Partners22/07/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Mar 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Jun 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jun 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed73

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM 1 mar 25.pdf11 Jul 2025
Form 2File: FORM 2 JAN-MAR 25.pdf11 Jul 2025
Form 3File: FORM 3 MAR 25.pdf11 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD MAR 25.pdf11 Jul 2025
Withdrawal Update Form 1File: FORM 1 mar 25.pdf11 Jul 2025
Withdrawal Update Form 2File: FORM 2 JAN-MAR 25.pdf11 Jul 2025
Withdrawal Update Form 3File: FORM 3 MAR 25.pdf11 Jul 2025
Layout approvalFile: LAYOUT_compressed (6).pdf25 Jun 2024
Building plan approvalFile: MYSCAN_20240624_0007_compressed (1).pdf25 Jun 2024
Building plan approvalFile: MYSCAN_20240624_0008_compressed (1).pdf25 Jun 2024
Building plan approvalFile: MYSCAN_20240624_0009_compressed.pdf25 Jun 2024
Building plan approvalFile: MYSCAN_20240624_0010_compressed.pdf25 Jun 2024
Building plan approvalFile: MYSCAN_20240624_0011_compressed.pdf25 Jun 2024
Building plan approvalFile: MYSCAN_20240624_0012_compressed.pdf25 Jun 2024
Building plan approvalFile: MYSCAN_20240624_0013_compressed (1).pdf25 Jun 2024
Building plan approvalFile: MYSCAN_20240624_0014_compressed.pdf25 Jun 2024
Building plan approvalFile: MYSCAN_20240624_0016_compressed.pdf25 Jun 2024
Copy of Layout Approval (in case of layout)File: LAYOUT_compressed (6).pdf25 Jun 2024
Building Plan Approval (IOD)File: MYSCAN_20240624_0007_compressed (1).pdf25 Jun 2024
Building Plan Approval (IOD)File: MYSCAN_20240624_0008_compressed (1).pdf25 Jun 2024
Building Plan Approval (IOD)File: MYSCAN_20240624_0009_compressed.pdf25 Jun 2024
Building Plan Approval (IOD)File: MYSCAN_20240624_0010_compressed.pdf25 Jun 2024
Building Plan Approval (IOD)File: MYSCAN_20240624_0011_compressed.pdf25 Jun 2024
Building Plan Approval (IOD)File: MYSCAN_20240624_0012_compressed.pdf25 Jun 2024
Building Plan Approval (IOD)File: MYSCAN_20240624_0013_compressed (1).pdf25 Jun 2024
Building Plan Approval (IOD)File: MYSCAN_20240624_0014_compressed.pdf25 Jun 2024
Building Plan Approval (IOD)File: MYSCAN_20240624_0016_compressed.pdf25 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 WITH PERIOD.pdf25 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 period.pdf25 Jun 2024
Certificates of CA (Form 3)File: form 3 with period.pdf25 Jun 2024
Commencement Certificates / NA Order for plotted developmentFile: CC REVISED.pdf19 Jun 2024
Declaration in FORM BFile: FORM B OLD.pdf19 Jun 2024
Declaration in FORM BFile: FORM B EXTENSION.pdf19 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SIGNED.pdf19 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 signed.pdf19 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2a signed.pdf19 Jun 2024
Disclosure of sold/ booked inventoryFile: sold unsold.pdf19 Jun 2024
CERSAI detailsFile: CERSAI.pdf19 Jun 2024
Certificates of CA (Form 3)File: form 3 june 24.pdf19 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTEREST.pdf19 Jun 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK DECLARATION.pdf19 Jun 2024
Declaration about Commencement CertificateFile: FORM D.pdf26 May 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD (2)_compressed.pdf26 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: R4_001.pdf27 Jun 2023
Declaration in FORM BFile: Affidavit cum declaration.pdf24 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf23 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 01-04-19 to 31-03-20.pdf23 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 01-04-20 to 31-03-21.pdf23 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 01-04-21 to 31-03-22.pdf23 Jun 2023
Disclosure of sold/ booked inventoryFile: disclosure of sold flats.pdf23 Jun 2023
Certificates of CA (Form 3)File: Form 3 L L homes_compressed (1).pdf23 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 (01-04-19 to 31-03-20).pdf23 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 (01-04-20 to 31-03-21).pdf23 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 (01-04-21 to 31-03-22).pdf23 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 (01-04-22 to 31-03-23).pdf23 Jun 2023
Building plan approvalFile: 2nd RDP 2021.pdf30 Jul 2021
Building Plan Approval (IOD)File: 2nd RDP 2021.pdf30 Jul 2021
Layout approvalFile: reviced buleprint .pdf30 Oct 2019
Building plan approvalFile: reviced buleprint .pdf30 Oct 2019
Copy of Layout Approval (in case of layout)File: reviced buleprint .pdf30 Oct 2019
Building Plan Approval (IOD)File: reviced buleprint .pdf30 Oct 2019
Commencement Certificates / NA Order for plotted developmentFile: reviced cc.pdf30 Oct 2019
Building plan approvalFile: blueprint (IOD-CC).pdf27 Mar 2018
Layout approvalFile: Layout buleprint.pdf27 Mar 2018
PAN CardFile: pan card llhomes.pdf27 Mar 2018
Copy of the legal title reportFile: title and search.pdf27 Mar 2018
Details of encumbrancesFile: encumbrance decleartion.pdf27 Mar 2018
Copy of Layout Approval (in case of layout)File: Layout buleprint.pdf27 Mar 2018
Building Plan Approval (IOD)File: blueprint (IOD-CC).pdf27 Mar 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement certificate.pdf27 Mar 2018
Declaration in FORM BFile: form B .pdf27 Mar 2018
Certificates of CA (Form 3)File: C A Certificate.pdf27 Mar 2018
Proforma of Allotment letterFile: agreement declaration.pdf27 Mar 2018

How this compares with Palghar

51%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 56 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep HARI RESIDENCY PHASE I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KOPARI, CHANDANSAR3,200+ in Palghar

2 kmHARI RESIDENCY PHASE ICompleted 4Lapsed / revoked 6Other 13Dot size: filed unitsN

Filed coordinates, straight-line distance. 23 registered projects within 2 km.

Builder: LOTUS LAKSHMINARAYAN HOMES

LOTUS LAKSHMINARAYAN HOMES has 1 registration on MahaRERA, including HARI RESIDENCY PHASE I. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if HARI RESIDENCY PHASE I is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of HARI RESIDENCY PHASE I?

The registered promoter entity is LOTUS LAKSHMINARAYAN HOMES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in HARI RESIDENCY PHASE I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against HARI RESIDENCY PHASE I?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for HARI RESIDENCY PHASE I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at HARI RESIDENCY PHASE I?

The professionals named in the filing: Architect: SHAPE CONSULTANT; Engineer: MUKESH KUMAR; Chartered Accountant: ASHWIN NAIR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in HARI RESIDENCY PHASE I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About HARI RESIDENCY PHASE I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save HARI RESIDENCY PHASE I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.