HARI RESIDENCY PHASE I
RG-MH-50235 · RERA P99000015966 · Last updated on MahaRERA portal: 11 Jul 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 6 complaints at MahaRERA
- Completion date moved by 56 months
- 2 extensions taken
- Encumbrance declared on the project land
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
HARI RESIDENCY PHASE I is a Residential / Group Housing project by LOTUS LAKSHMINARAYAN HOMES in Palghar, Maharashtra, registered with MahaRERA as P99000015966 on 10 Apr 2018. Possession is promised by 31 Dec 2027. The completion date has moved by 56 months from the original filing. 185 of the 361 units on this registration are recorded sold or booked, and 27 of 44 construction stages are filed complete. 6 complaints are on record with the regulator.
At a glance
Project
- NameHARI RESIDENCY PHASE I
- TypeResidential / Group Housing
- Location
- VEER SAVARKAR ROAD
- KOPARI
- CHANDANSAR
- Vasai-Virar City (M Corp)
- Vasai
- Palghar
- 401305
- Pincode401305
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000015966
- ReraGenie IDRG-MH-50235
Builder
- NameLOTUS LAKSHMINARAYAN HOMES
- Entity typePartnership
- PartnersNIKUNJ PRAKASH SHAH, MANOJ JAGANNATH KORE
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on10 Apr 2018
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 30 Apr 2023)
- Buildings4 building records
- Documents filed73 files
Current status
Figures as on 11 Jul 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| HARI RESIDENCY PHASE I BUILDING NO 1 WING A | NA | 16 | 16 | 133 | 17 | 150 |
| HARI RESIDENCY PHASE I BUILDING NO 1 WING B | NA | 16 | 16 | 90 | 12 | 102 |
| HARI RESIDENCY PHASE I BUILDING NO 1 WING C | NA | 8 | 8 | 56 | 11 | 67 |
| HARI RESIDENCY PHASE 1 BUILDING NO 2 | NA | 7 | 7 | 35 | 7 | 42 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 11 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
27 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Staircases, at 95%.
HARI RESIDENCY PHASE I BUILDING NO 1 WING A80%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 95% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
HARI RESIDENCY PHASE I BUILDING NO 1 WING B35%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 55% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 15% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 20% |
HARI RESIDENCY PHASE I BUILDING NO 1 WING C82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
HARI RESIDENCY PHASE 1 BUILDING NO 282%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 11 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 50% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 50% |
| Storm Water Drains | Yes | 20% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed128
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| HARI RESIDENCY PHASE I BUILDING NO 1 WING A | 1 | 48 | 49 |
| HARI RESIDENCY PHASE I BUILDING NO 1 WING B | 1 | 34 | 35 |
| HARI RESIDENCY PHASE I BUILDING NO 1 WING C | 1 | 43 | 44 |
Land and ownership2
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| VINOD HARIBHAU JOSHI | Mumbai City | Mumbai City |
| SUNIL HARIBHAU JOSHI | Kurla | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| HARI RESIDENCY PHASE I BUILDING NO 1 WING A | NA | Rs 8.08 cr | Rs 7.76 cr |
| HARI RESIDENCY PHASE I BUILDING NO 1 WING C | NA | Rs 7.92 cr | Rs 7.60 cr |
| - | NA | Rs 3.60 cr | Rs 39.23 lakh |
| HARI RESIDENCY PHASE I BUILDING NO 1 WING B | NA | Rs 2.64 cr | Rs 1.15 cr |
| HARI RESIDENCY PHASE 1 BUILDING NO 2 | NA | Rs 1.76 cr | Rs 1.69 cr |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SHAPE CONSULTANT |
| Engineer | MUKESH KUMAR |
| Chartered Accountant | ASHWIN NAIR |
| Partner | Role in project |
|---|---|
| LOTUS LAKSHMINARAYAN HOMES | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to Covid - 19 Pandemic, unable to complete the construction work by us before deadline declared by us and certificate given by you to us. Hence, we are requesting you to extend its deadline date by one more year that’s 30/04/2024. Please do the needful for the same.
Reason as filed by the promoterDUE TO SOME UNAVOIDABLE REASONS THE PROJECT COULD NOT BE COMPLETED ON TIME
Complaints filed with MahaRERA6
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000591184 | Dr prashant Ramrao Pawar | Mr Nimish Shah, Lotus Laxminarayan Homes & Partners | 19/07/2024 |
| CC006000000591212 | Kunal Vishnu Sawant | Mr Nimish Shah, Lotus Laxminarayan homes & partners | 18/07/2024 |
| CC006000000591273 | Pramod Madhukar Bhoir | Mr Nimish Shah, Lotus Laxminarayan Homes & Partners | 22/07/2024 |
| CC006000000591224 | Pramod hiraman patil | Mr Nimish Shah, Lotus Laxminarayan Homes &Partners | 19/07/2024 |
| CC006000000591214 | MUKESHKUMAR AMARPAL MISHRA | Mr. nimesh dilip shah & partenar m/s.lotus lakshmi narayan homes | 21/07/2024 |
| CC006000000591215 | sakshi gautam mohite | Mr Nimish Shah, Lotus Laxminarayan Homes & Partners | 22/07/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Mar 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Jun 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 25 Jun 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 19 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed73
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: FORM 1 mar 25.pdf | 11 Jul 2025 |
| Form 2File: FORM 2 JAN-MAR 25.pdf | 11 Jul 2025 |
| Form 3File: FORM 3 MAR 25.pdf | 11 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: SOLD MAR 25.pdf | 11 Jul 2025 |
| Withdrawal Update Form 1File: FORM 1 mar 25.pdf | 11 Jul 2025 |
| Withdrawal Update Form 2File: FORM 2 JAN-MAR 25.pdf | 11 Jul 2025 |
| Withdrawal Update Form 3File: FORM 3 MAR 25.pdf | 11 Jul 2025 |
| Layout approvalFile: LAYOUT_compressed (6).pdf | 25 Jun 2024 |
| Building plan approvalFile: MYSCAN_20240624_0007_compressed (1).pdf | 25 Jun 2024 |
| Building plan approvalFile: MYSCAN_20240624_0008_compressed (1).pdf | 25 Jun 2024 |
| Building plan approvalFile: MYSCAN_20240624_0009_compressed.pdf | 25 Jun 2024 |
| Building plan approvalFile: MYSCAN_20240624_0010_compressed.pdf | 25 Jun 2024 |
| Building plan approvalFile: MYSCAN_20240624_0011_compressed.pdf | 25 Jun 2024 |
| Building plan approvalFile: MYSCAN_20240624_0012_compressed.pdf | 25 Jun 2024 |
| Building plan approvalFile: MYSCAN_20240624_0013_compressed (1).pdf | 25 Jun 2024 |
| Building plan approvalFile: MYSCAN_20240624_0014_compressed.pdf | 25 Jun 2024 |
| Building plan approvalFile: MYSCAN_20240624_0016_compressed.pdf | 25 Jun 2024 |
| Copy of Layout Approval (in case of layout)File: LAYOUT_compressed (6).pdf | 25 Jun 2024 |
| Building Plan Approval (IOD)File: MYSCAN_20240624_0007_compressed (1).pdf | 25 Jun 2024 |
| Building Plan Approval (IOD)File: MYSCAN_20240624_0008_compressed (1).pdf | 25 Jun 2024 |
| Building Plan Approval (IOD)File: MYSCAN_20240624_0009_compressed.pdf | 25 Jun 2024 |
| Building Plan Approval (IOD)File: MYSCAN_20240624_0010_compressed.pdf | 25 Jun 2024 |
| Building Plan Approval (IOD)File: MYSCAN_20240624_0011_compressed.pdf | 25 Jun 2024 |
| Building Plan Approval (IOD)File: MYSCAN_20240624_0012_compressed.pdf | 25 Jun 2024 |
| Building Plan Approval (IOD)File: MYSCAN_20240624_0013_compressed (1).pdf | 25 Jun 2024 |
| Building Plan Approval (IOD)File: MYSCAN_20240624_0014_compressed.pdf | 25 Jun 2024 |
| Building Plan Approval (IOD)File: MYSCAN_20240624_0016_compressed.pdf | 25 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 WITH PERIOD.pdf | 25 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 period.pdf | 25 Jun 2024 |
| Certificates of CA (Form 3)File: form 3 with period.pdf | 25 Jun 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC REVISED.pdf | 19 Jun 2024 |
| Declaration in FORM BFile: FORM B OLD.pdf | 19 Jun 2024 |
| Declaration in FORM BFile: FORM B EXTENSION.pdf | 19 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SIGNED.pdf | 19 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 signed.pdf | 19 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2a signed.pdf | 19 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: sold unsold.pdf | 19 Jun 2024 |
| CERSAI detailsFile: CERSAI.pdf | 19 Jun 2024 |
| Certificates of CA (Form 3)File: form 3 june 24.pdf | 19 Jun 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTEREST.pdf | 19 Jun 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK DECLARATION.pdf | 19 Jun 2024 |
| Declaration about Commencement CertificateFile: FORM D.pdf | 26 May 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD (2)_compressed.pdf | 26 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: R4_001.pdf | 27 Jun 2023 |
| Declaration in FORM BFile: Affidavit cum declaration.pdf | 24 Jun 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 23 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 01-04-19 to 31-03-20.pdf | 23 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 01-04-20 to 31-03-21.pdf | 23 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 01-04-21 to 31-03-22.pdf | 23 Jun 2023 |
| Disclosure of sold/ booked inventoryFile: disclosure of sold flats.pdf | 23 Jun 2023 |
| Certificates of CA (Form 3)File: Form 3 L L homes_compressed (1).pdf | 23 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 (01-04-19 to 31-03-20).pdf | 23 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 (01-04-20 to 31-03-21).pdf | 23 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 (01-04-21 to 31-03-22).pdf | 23 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 (01-04-22 to 31-03-23).pdf | 23 Jun 2023 |
| Building plan approvalFile: 2nd RDP 2021.pdf | 30 Jul 2021 |
| Building Plan Approval (IOD)File: 2nd RDP 2021.pdf | 30 Jul 2021 |
| Layout approvalFile: reviced buleprint .pdf | 30 Oct 2019 |
| Building plan approvalFile: reviced buleprint .pdf | 30 Oct 2019 |
| Copy of Layout Approval (in case of layout)File: reviced buleprint .pdf | 30 Oct 2019 |
| Building Plan Approval (IOD)File: reviced buleprint .pdf | 30 Oct 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: reviced cc.pdf | 30 Oct 2019 |
| Building plan approvalFile: blueprint (IOD-CC).pdf | 27 Mar 2018 |
| Layout approvalFile: Layout buleprint.pdf | 27 Mar 2018 |
| PAN CardFile: pan card llhomes.pdf | 27 Mar 2018 |
| Copy of the legal title reportFile: title and search.pdf | 27 Mar 2018 |
| Details of encumbrancesFile: encumbrance decleartion.pdf | 27 Mar 2018 |
| Copy of Layout Approval (in case of layout)File: Layout buleprint.pdf | 27 Mar 2018 |
| Building Plan Approval (IOD)File: blueprint (IOD-CC).pdf | 27 Mar 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement certificate.pdf | 27 Mar 2018 |
| Declaration in FORM BFile: form B .pdf | 27 Mar 2018 |
| Certificates of CA (Form 3)File: C A Certificate.pdf | 27 Mar 2018 |
| Proforma of Allotment letterFile: agreement declaration.pdf | 27 Mar 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 73 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep HARI RESIDENCY PHASE I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KOPARI, CHANDANSAR3,200+ in Palghar
Filed coordinates, straight-line distance. 23 registered projects within 2 km.
AV PEARL BLDG NO.4 WING BCD
AVM BUILDCON LLP
Mrida Innovista Homes
NINE MEGACORP DEVELOPERS LLP
AV PEARL BUILDING NO. 3, C WING
AVM BUILDCON LLP
MJV CORPORATION
VYANKATI CHINNAVISHRWAPAPA SAMAKOTI
AV PEARL BUILDING NO. 3, WING B
SHREE SAI JIVDANI DEVELOPERS LLP
SAI BABA NAGAR
VED GANGA
See every Palghar project, with the district possession charts
Builder: LOTUS LAKSHMINARAYAN HOMES
LOTUS LAKSHMINARAYAN HOMES has 1 registration on MahaRERA, including HARI RESIDENCY PHASE I. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What are my rights if HARI RESIDENCY PHASE I is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of HARI RESIDENCY PHASE I?
The registered promoter entity is LOTUS LAKSHMINARAYAN HOMES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in HARI RESIDENCY PHASE I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against HARI RESIDENCY PHASE I?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for HARI RESIDENCY PHASE I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at HARI RESIDENCY PHASE I?
The professionals named in the filing: Architect: SHAPE CONSULTANT; Engineer: MUKESH KUMAR; Chartered Accountant: ASHWIN NAIR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in HARI RESIDENCY PHASE I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback