Home / Browse projects / Mumbai Suburban, Maharashtra / YELLOW ROSES
YELLOW ROSES
RG-MH-08866 · RERA P51800000712 · Last updated on MahaRERA portal: 8 Feb 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 22 months past the filed date
- Completion date moved by 53 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
YELLOW ROSES is a Residential / Group Housing project by Navkar Infra Projects in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800000712 on 20 Jul 2017. Possession was promised by 31 Dec 2024 and is now 22 months past that date. The completion date has moved by 53 months from the original filing.
At a glance
Project
- NameYELLOW ROSES
- TypeResidential / Group Housing
- Location
- Holy Cross Road
- I C Colony
- Borivali
- Mumbai Suburban
- 400103
- Pincode400103
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800000712
- ReraGenie IDRG-MH-08866
Builder
- NameNavkar Infra Projects
- Entity typePartnership
- PartnersMukesh Nenshi Gala, SAGAR NENSHI GALA
- Other registrations5 more →
- Completed2 of 6
- No longer live3 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on20 Jul 2017
- Promised completion31 Dec 2024
- Revised completionRevised to 31 Dec 2024 (originally 19 Jul 2020)
- Buildings1 building record
- Documents filed119 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| NAVKAR YELLOW ROSES | NA | 13 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 8 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.
NAVKAR YELLOW ROSES: 90% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
Progress on shared amenities15
As on 8 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
Parking filed15
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AMIT PAWAR |
| Engineer | MUTHU KRISHNAN AND ASSOCIATES |
| Chartered Accountant | BRAJESH GOYAL AND ASSOCIATES CHARTERED ACCOUNTANTS |
| Partner | Role in project |
|---|---|
| Navkar Infra Projects | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterBalance FSI consumption with respect to change in the government policy.
Reason as filed by the promoterPANDEMIC COVID 19, non availability of labour and supply of material.
Reason as filed by the promoterWe have already constructed the building as per the approved plan. We have also handed over the soft possession to the society members under the re-development scheme including all prospective purchasers. Since the society name insertion in property card has to be carried out, the completion certificate is kept in abeyance for furnishing updated property card before the competent authority. Thus we request this forum to grant one year extension for making appropriate submission and obtaining OC/CC certificate. The mandatory 51% consent form along with annexure is uploaded for the authority ove
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jun 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 3 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 17 Oct 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 17 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed119
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 119 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM-5 UPTP MAR-24 Yellow Roses.pdf | 8 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM-5 UPTP MAR-24 Yellow Roses.pdf | 7 Feb 2025 |
| Certificates of CA (Form 3)File: FORM-3 UPTO MAR-24 YELLOW ROSES.pdf | 1 Jan 2025 |
| Certificates of CA (Form 3)File: FORM-3 UPTO JUN-24 YELLOW ROSES.pdf | 1 Jan 2025 |
| Certificates of CA (Form 3)File: FORM-3 UPTO SEP-24 YELLOW ROSES.pdf | 1 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 APR-24 TO JUN-24 YELLOW ROSES.pdf | 11 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 JUL-24 TO SEP-24 YELLOW ROSES.pdf | 11 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 APR-24 TO JUN-24 YELLOW ROSES.pdf | 11 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 JUL-24 TO SEP-24 YELLOW ROSES.pdf | 11 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 JAN-24 TO MAR-24 YELLOW ROSES.pdf | 14 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 JAN-24 TO MAR-24 YELLOW ROSES.pdf | 14 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM-2A JAN-24 TO MAR-24 YELLOW ROSES.pdf | 14 Jun 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 UPTO DEC-23 YELLOW ROSES.pdf | 13 Feb 2024 |
| Certificates of CA (Form 3)File: FORM-3 UPTO DEC-23 YELLOW ROSES.pdf | 22 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 UPTO DEC-2023 YELLOW ROSES CHS.pdf | 20 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Yellow Roses 2022-2023.pdf | 10 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: 1 Disclosure of Sold Booked Inventories 30 09 2023.pdf | 9 Nov 2023 |
| Certificates of CA (Form 3)File: FORM 3 as on 31 03 2023_1.pdf | 9 Nov 2023 |
| Certificates of CA (Form 3)File: FORM 3 as on 30 06 2023_1.pdf | 9 Nov 2023 |
| Certificates of CA (Form 3)File: FORM 3 as on 30 09 2023_1.pdf | 9 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 FY 2022-23.pdf | 9 Nov 2023 |
| Declaration in FORM BFile: FORM B AFFIDAVIT CUM DECLARATION_compressed (1).pdf | 7 Nov 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 July- Aug- Sept 2023.pdf | 6 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A YELLOW ROSES 2022-2023.pdf | 6 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 JUL -23 TO SEP-23.pdf | 1 Nov 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 JAN-23 TO MAR-23.pdf | 1 Nov 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 APR-23 TO JUN-23.pdf | 1 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A YELLOW ROSES 2022-2023.pdf | 30 Oct 2023 |
| Building plan approvalFile: DRAWING 1.pdf | 17 Oct 2023 |
| Building Plan Approval (IOD)File: DRAWING 1.pdf | 17 Oct 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC Further.pdf | 17 Oct 2023 |
| Certificates of CA (Form 3)File: FORM-3 UPTO MAR-18.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: FORM-3 UPTO JUN-18.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: FORM-3 UPTO SEP-18.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: FORM-3 UPTO DEC-18.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: FORM-3 UPTO MAR-19.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: FORM-3 UPTO JUN-19.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: FORM-3 UPTO SEP-19.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: FORM-3 UPTO DEC-19.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: FORM-3 UPTO JUN-20.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: FORM-3 UPTO SEP-20.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: FORM-3 UPTO DEC-20.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: FORM-3 UPTO JUN-21.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: FORM-3 UPTO SEP-21.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: FORM-3 UPTO DEC-21.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: FORM-3 UPTO JUN-22.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: FORM-3 UPTO SEP-22.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: FORM-3 UPTO DEC-22.pdf | 13 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 OCT-18 TO DEC-18.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 APR-19 TO JUN-19.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 JUL-19 TO SEP-19.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 OCT-19 TO DEC-19.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 APR-20 TO JUN-20.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 JUL-20 TO SEP-20.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 OCT-20 TO DEC-20.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 APR-21 TO JUN-21.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 JUL-21 TO SEP-21.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 OCT-21 TO DEC-21.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 APR-22 TO JUN-22.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 JUL-22 TO SEP-22.pdf | 12 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 OCT-22 TO DEC-22.pdf | 12 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-I APR-18 TO JUN-18.pdf | 27 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-I JAN-18 TO MAR-18.pdf | 27 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-I JUL-18 TO SEP-18.pdf | 27 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-I OCT-18 TO DEC-18.pdf | 27 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM- I OCT -22 TO DEC-22.pdf | 23 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM I APR-19 TO JUN-19.pdf | 23 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM I APR-20 TO JUNE-20.pdf | 23 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM- I APR-21 TO JUN-21.pdf | 23 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM- I APR-22 TO JUNE -22.pdf | 23 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM- I APR-23 TO JUNE-23.pdf | 23 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM -I JAN -23 TO MAR-23.pdf | 23 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM I JULY-19 TO SEP-19.pdf | 23 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM I JULY-20 TO SEP-20.pdf | 23 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM I JULY-21 TO SEP-21.pdf | 23 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM I OCT-19 TO DEC-19.pdf | 23 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM I OCT-20 TO DEC-20.pdf | 23 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM I OCT-21 TO DEC-21.pdf | 23 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-I JUL-22 TO SEP-22.pdf | 23 Sep 2023 |
| Certificates of CA (Form 3)File: FORM 3 YELLOW ROSES 21-22.pdf | 12 May 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 5 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 119 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep YELLOW ROSES on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near I C Colony6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 296 registered projects within 2 km.
MAYFAIR AANGAN
MAYFAIR HOUSING PRIVATE LIMITED
THE CASTLE
SOLIDAGO REALTY
103 West
M/s. RELCON ZP JE CONSTRUCTION LLP
HAPPY HOME CHSL
SUMUKH INFRA
Romell Ariana
ROMELL REAL ESTATE PRIVATE LIMITED
Kamla Borivali Lucky
Kamla Homes and Lifestyles Private Limited
See every Mumbai Suburban project, with the district possession charts
Builder: Navkar Infra Projects
Navkar Infra Projects has 6 registrations on MahaRERA, including YELLOW ROSES and SAKSHAT NAVKAR. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that YELLOW ROSES shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if YELLOW ROSES is delayed beyond 31 Dec 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of YELLOW ROSES?
The registered promoter entity is Navkar Infra Projects, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in YELLOW ROSES?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for YELLOW ROSES?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at YELLOW ROSES?
The professionals named in the filing: Architect: AMIT PAWAR; Engineer: MUTHU KRISHNAN AND ASSOCIATES; Chartered Accountant: BRAJESH GOYAL AND ASSOCIATES CHARTERED ACCOUNTANTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in YELLOW ROSES?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback