Home / Browse projects / Pune, Maharashtra / YASHWANT APARTMENT

Completed No litigation declared Residential / Group Housing project

YASHWANT APARTMENT

By M/S SHREERAM BUILDERS

RG-MH-09488 · RERA P52100011553 · Last updated on MahaRERA portal: 20 Jul 2022

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 5 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2017Possession promisedregistration recorded completed
9 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 27 documents Report an error

YASHWANT APARTMENT is a Residential / Group Housing project by M/S SHREERAM BUILDERS in Pune, Maharashtra, registered with MahaRERA as P52100011553 on 31 Aug 2017. The registration is recorded completed; possession was promised by 31 Dec 2017.

At a glance

Project

  • NameYASHWANT APARTMENT
  • TypeResidential / Group Housing
  • Location
    • Parvati
    • Haveli
    • Pune
    • 411009
  • Pincode411009
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100011553
  • ReraGenie IDRG-MH-09488

Builder

  • NameM/S SHREERAM BUILDERS
  • Entity typePartnership
  • GSTIN27AACFS3909E1ZC
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnerNITIN DINKAR KULKARNI
  • Other registrations5 more →
  • Completed5 of 6
  • Declared earlier projects8 →

Key dates

this monthRegisteredAug 2017PromisedDec 2017Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on31 Aug 2017
  • Promised completion31 Dec 2017
  • Revised completionNone
  • Buildings1 building record
  • Documents filed27 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
YASHWANT APARTMENTNA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jul 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

YASHWANT APARTMENT: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 20 Jul 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area557 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI880.09
Proposed, not sanctioned880 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch2044/2045 SAHADRI SADAN SADASHIV PETH TILAK ROAD PURAM CHOWK PUNE 411030

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectM/S Shinde Joshi & Associates
EngineerStrudcom consultants Pvt. Ltd
PartnerRole in project
M/S SHREERAM BUILDERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed27

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of Formation of Legal Entity (Society/Co Op etc.)File: 1 Status of Conveyance.pdf20 Jul 2022
Certificates of CA (Form 5)File: FORM 5 YASHWANT APT.pdf15 Oct 2018
Status of ConveyanceFile: Deed of declaration YASHWANT 1.pdf7 Apr 2018
Status of ConveyanceFile: Deed of declaration YASHWANT 2.pdf7 Apr 2018
Status of ConveyanceFile: Deed of declaration YASHWANT 3.pdf7 Apr 2018
Status of ConveyanceFile: Deed of declaration YASHWANT 4.pdf7 Apr 2018
Status of ConveyanceFile: Yashwant - Deed of Declaration (1).pdf2 Apr 2018
OtherFile: COMPLETION CERTIFICATE.pdf23 Dec 2017
Certificates of Architect (Form 4)File: yaswant0001.pdf20 Dec 2017
Layout approvalFile: 1 (2).pdf31 Jul 2017
Copy of the legal title reportFile: Yashwant Title Report page 1 (13 files merged) (1).pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: 1 (2).pdf31 Jul 2017
Proforma of Allotment letterFile: Yashwant Apartment Agreement Copy.pdf31 Jul 2017
Proforma of Allotment letterFile: Allotment Letter Final.pdf31 Jul 2017
OtherFile: Completion Certificate.pdf31 Jul 2017
Details of encumbrancesFile: FORM B.pdf27 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE Yashwant.pdf27 Jul 2017
Certificates of CA (Form 3)File: CA Certificate Yashwant.pdf27 Jul 2017
Building plan approvalFile: 3.pdf26 Jul 2017
Building plan approvalFile: 1 (2).pdf26 Jul 2017
Building plan approvalFile: 2.pdf26 Jul 2017
Building Plan Approval (IOD)File: 1 (2).pdf26 Jul 2017
Building Plan Approval (IOD)File: 2.pdf26 Jul 2017
Building Plan Approval (IOD)File: 3.pdf26 Jul 2017
Declaration in FORM BFile: FORM B.pdf25 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf25 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf19 Jul 2017

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 delivered on promise1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
YASHWANT APARTMENTPLOT NO 25 CTS NO 1180 Tulshibuagwale Colony Sahakarnagar no 2 Parvati Pune 41100912CompletedDec 2017Aug 2017
Sumeet Co-operative Housing SocietyPLOT NO 8 CTS NO 1384 SR.NO 87 2 2A 3 Sahakarnagar No 2 Parvati Pune 41100919CompletedDec 2017Dec 2017
Anandpuri B Co-operative Housing Society LtdFinal Plot No 68 CTS No 1258 Tulshibagwale Colony Sahakarnagar No 2 Parvati Pune 41100912CompletedAug 2016Jun 2016
Turja ApartmentFinal plot No 16 City Survey No 16 Erandewane Pune 411 00410CompletedDec 2014Dec 2014
Vinayak EnclaveDashabhuja Ganesh Cooperative Housing Society Plot No 117 CTS 1289 Sahakarnagar No 2 Parvati Pune 41100910CompletedApr 2014Late, May 2014

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep YASHWANT APARTMENT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Parvati13,700+ in Pune

2 kmYASHWANT APARTMENTCompleted 22Lapsed / revoked 12Other 1Dot size: filed unitsN

Filed coordinates, straight-line distance. 35 registered projects within 2 km.

Builder: M/S SHREERAM BUILDERS

M/S SHREERAM BUILDERS has 6 registrations on MahaRERA, including YASHWANT APARTMENT and Sumeet Co-operative Housing Society. Its filings disclose 8 earlier MahaRERA projects: declares 7 of 8 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if YASHWANT APARTMENT is delayed beyond 31 Dec 2017?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of YASHWANT APARTMENT?

The registered promoter entity is M/S SHREERAM BUILDERS, a partnership as per the filing. Its GSTIN 27AACFS3909E1ZC can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in YASHWANT APARTMENT?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for YASHWANT APARTMENT?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at YASHWANT APARTMENT?

The professionals named in the filing: Architect: M/S Shinde Joshi & Associates; Engineer: Strudcom consultants Pvt. Ltd. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in YASHWANT APARTMENT?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About YASHWANT APARTMENT. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save YASHWANT APARTMENT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.