Home / Browse projects / YASHVI REGENCY

Registered No litigation declared Others project

YASHVI REGENCY

By AASMA INFRA-CON LLP

RG-MH-28580 · RERA P51900026765 · Last updated on MahaRERA portal: 1 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 38 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Jun 2028Possession promisedmoved 38 months from the original
5 of 11Construction stages donefurthest along: Internal walls, 95%
96 of 105Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 128 documents Report an error

YASHVI REGENCY is a Others project by AASMA INFRA-CON LLP in GRANT ROAD, MUMBAI, 400004, registered with MahaRERA as P51900026765 on 22 Oct 2020. Possession is promised by 30 Jun 2028. The completion date has moved by 38 months from the original filing. 9 of the 105 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameYASHVI REGENCY
  • TypeOthers
  • Location
    • JALBHAI STREET
    • SHAPUR BAUG
    • GRANT ROAD
    • MUMBAI
    • 400004
  • Pincode400004
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900026765
  • ReraGenie IDRG-MH-28580

Builder

  • NameAASMA INFRA-CON LLP
  • Entity typePartnership
  • PartnerMOHAMED MUSTAFA SHAKIL AHMED ANSARI
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredOct 2020First promiseApr 2025Revised toJun 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Oct 2020
  • Promised completion30 Jun 2028
  • Revised completionRevised to 30 Jun 2028 (originally 30 Apr 2025)
  • Buildings1 building record
  • Documents filed128 files

Current status

9%9 of 105 units booked
95.2%Work done, per cost certificate

Figures as on 1 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
YASHVI REGENCYNA21218817105

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 1 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.

YASHVI REGENCY: 83% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 1 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes30%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes70%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area825 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on7 Jul 2025
LandownerVillageDistrict
NAVSRAJAN DEVELOPERSABCD-400001Mumbai City

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI4872.39
Proposed, not sanctioned4,872 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMAHIM BRANCH
Estimated costRs 42.00 cr
Cost incurredRs 40.00 cr
Work done95.24%
BuildingWingEstimatedIncurred
YASHVI REGENCYNARs 42.00 crRs 40.00 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAJ ENTERPRISES
EngineerZAINUDDIN H. TOLE (M/S. SUPCONS CONSULTANTS)
EngineerERAM RASHID SHAIKH
EngineerSHAKEEL AHMED MOHD YUNUS
EngineerARSHAD GHOJARIA
Chartered AccountantS R SIDDIQUI & CO
Chartered AccountantABDUL HALIM SIDDIQUE
PartnerRole in project
AASMA INFRA-CON LLP-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA14082502374Apr 2025 → Apr 2026

Reason as filed by the promoterI, Mr. Mohamed Mustafa Shakil Ahmed Ansari, hereby declare the following with respect to the project “YASHVI REGENCY” bearing registration number P51900026765 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 100% of RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and applying for the Oc

EA20042620672Apr 2025 → Jun 2028

Reason as filed by the promoterDear Sir/Ma’am, I, Mr. Mohamed Mustafa Shakil Ahmed Ansari, hereby declare the following with respect to the project “YASHVI REGENCY” bearing registration number P51900026765 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 100% of RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and app

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Oct 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Oct 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Oct 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Oct 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2028

Documents filed128

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 128 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - Q1.pdf1 Aug 2026
Withdrawal Update Form 2File: Form 2 - Q1.pdf1 Aug 2026
Withdrawal Update Form 3File: Form 3 - Q1.pdf1 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A.pdf21 Apr 2026
Withdrawal Update Form 1File: Form 1 - Q2 25-26.pdf20 Apr 2026
Withdrawal Update Form 1File: Form 1 - Q3 25-26.pdf20 Apr 2026
Withdrawal Update Form 1File: Form 1 Q4 - 25-26.pdf20 Apr 2026
Withdrawal Update Form 1File: Form 1 March 2026 Final.pdf20 Apr 2026
Withdrawal Update Form 2File: Form 2 - Q2 25-26.pdf20 Apr 2026
Withdrawal Update Form 2File: Form 2 - Q3 25-26.pdf20 Apr 2026
Withdrawal Update Form 2File: Form 2 Q4 25-26.pdf20 Apr 2026
Withdrawal Update Form 2File: Form 2 March 2026 Final.pdf20 Apr 2026
Withdrawal Update Form 3File: Form 3 - Q2 25-26.pdf20 Apr 2026
Withdrawal Update Form 3File: Form 3 - Q3 25-26.pdf20 Apr 2026
Withdrawal Update Form 3File: Form 3 Q4 - 25-26.pdf20 Apr 2026
Withdrawal Update Form 3File: Form 3 March 2026 Final.pdf20 Apr 2026
Form 1File: Form 1 December 2020.pdf13 Aug 2025
Form 2File: Form 2 December 2020.pdf13 Aug 2025
Form 3File: Form 3 December 2020.pdf13 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold Unsold December 2020.pdf13 Aug 2025
Form 1File: Form 1 March 2021.pdf13 Aug 2025
Form 2File: Form 2 March 2021.pdf13 Aug 2025
Form 3File: Form 3 March 2021.pdf13 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold Unsold March 2021.pdf13 Aug 2025
Form 1File: Form 1 June 2021.pdf13 Aug 2025
Form 2File: Form 2 June 2021.pdf13 Aug 2025
Form 3File: Form 3 June 2021.pdf13 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold Unsold June 2021.pdf13 Aug 2025
Form 1File: Form 1 September 2021.pdf13 Aug 2025
Form 2File: Form 2 September 2021.pdf13 Aug 2025
Form 3File: Form 3 September 2021.pdf13 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold Unsold September 2021.pdf13 Aug 2025
Form 1File: Form 1 December 2021.pdf13 Aug 2025
Form 2File: Form 2 December 2021.pdf13 Aug 2025
Form 3File: Form 3 December 2021.pdf13 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold Unsold December 2021.pdf13 Aug 2025
Form 1File: Form 1 March 2022.pdf13 Aug 2025
Form 2File: Form 2 March 2022.pdf13 Aug 2025
Form 3File: Form 3 March 2022.pdf13 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold Unsold March 2022.pdf13 Aug 2025
Form 1File: Form 1 June 2022.pdf13 Aug 2025
Form 2File: Form 2 June 2022.pdf13 Aug 2025
Form 3File: Form 3 June 2022.pdf13 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold Unsold June 2022.pdf13 Aug 2025
Form 1File: Form 1 September 2022.pdf13 Aug 2025
Form 2File: Form 2 September 2022.pdf13 Aug 2025
Form 3File: Form 3 September 2022.pdf13 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold Unsold September 2022.pdf13 Aug 2025
Form 1File: Form 1 December 2022.pdf13 Aug 2025
Form 2File: Form 2 December 2022.pdf13 Aug 2025
Form 3File: Form 3 December 2022.pdf13 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold Unsold December 2022.pdf13 Aug 2025
Form 1File: Form 1 March 2023.pdf13 Aug 2025
Form 2File: Form 2 March 2023.pdf13 Aug 2025
Form 3File: Form 3 March 2023.pdf13 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold Unsold March 2023.pdf13 Aug 2025
Form 1File: Form 1 June 2023.pdf13 Aug 2025
Form 2File: Form 2 June 2023.pdf13 Aug 2025
Form 3File: Form 3 June 2023.pdf13 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold Unsold June 2023.pdf13 Aug 2025
Form 1File: Form 1 September 2023.pdf13 Aug 2025
Form 2File: Form 2 September 2023.pdf13 Aug 2025
Form 3File: Form 3 September 2023.pdf13 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold Unsold September 2023.pdf13 Aug 2025
Form 1File: Form 1 December 2023.pdf13 Aug 2025
Form 2File: Form 2 December 2023.pdf13 Aug 2025
Form 3File: Form 3 December 2023.pdf13 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold Unsold December 2023.pdf13 Aug 2025
Form 1File: Form 1 March 2024.pdf13 Aug 2025
Form 2File: Form 2 March 2024.pdf13 Aug 2025
Form 3File: Form 3 March 2024.pdf13 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold Unsold March 2024.pdf13 Aug 2025
Form 1File: Form 1 June 2024.pdf13 Aug 2025
Form 2File: Form 2 June 2024.pdf13 Aug 2025
Form 3File: Form 3 June 2024.pdf13 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold Unsold June 2024.pdf13 Aug 2025
Form 1File: Form 1 September 2024.pdf13 Aug 2025
Form 2File: Form 2 September 2024.pdf13 Aug 2025
Form 3File: Form 3 September 2024.pdf13 Aug 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold Unsold September 2024.pdf13 Aug 2025

Keep YASHVI REGENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near GRANT ROAD, MUMBAI

2 kmYASHVI REGENCYCompleted 13Lapsed / revoked 24Other 33Dot size: filed unitsN

Filed coordinates, straight-line distance. 70 registered projects within 2 km.

Builder: AASMA INFRA-CON LLP

AASMA INFRA-CON LLP has 2 registrations on MahaRERA, including NECKLACE VIEW and YASHVI REGENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record.

Frequently asked questions

What are my rights if YASHVI REGENCY is delayed beyond 30 Jun 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of YASHVI REGENCY?

The registered promoter entity is AASMA INFRA-CON LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in YASHVI REGENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for YASHVI REGENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at YASHVI REGENCY?

The professionals named in the filing: Architect: RAJ ENTERPRISES; Engineer: ZAINUDDIN H. TOLE (M/S. SUPCONS CONSULTANTS); Engineer: ERAM RASHID SHAIKH; Engineer: SHAKEEL AHMED MOHD YUNUS; Engineer: ARSHAD GHOJARIA; Chartered Accountant: S R SIDDIQUI & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in YASHVI REGENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About YASHVI REGENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save YASHVI REGENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.