Yashashree
RG-MH-25182 · RERA P51700008388 · Last updated on MahaRERA portal: 9 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 2 cases
- 7 complaints at MahaRERA
- Completion date moved by 60 months
- 1 extension taken
Clear
- No encumbrance on the project land
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Yashashree is a Residential / Group Housing project by TRUPTI BUILDCON LLP in Thane, Maharashtra, registered with MahaRERA as P51700008388 on 18 Aug 2017. Possession is promised by 31 Dec 2028. The completion date has moved by 60 months from the original filing. 7 complaints are on record with the regulator.
At a glance
Project
- NameYashashree
- TypeResidential / Group Housing
- Location
- Navghar Road
- Mulund
- Thane (M Corp.)
- Thane
- 400081
- Pincode400081
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700008388
- ReraGenie IDRG-MH-25182
Builder
- NameTRUPTI BUILDCON LLP
- Entity typeLimited Liability Partnership
- LLPINAAX-2440
- GSTIN27AARFT6649K1Z8
- Managing DirectorFatesh Kishanchand Mirchandani
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on18 Aug 2017
- Promised completion31 Dec 2028
- Revised completionRevised to 31 Dec 2028 (originally 30 Dec 2023)
- Buildings2 building records
- Documents filed38 files
Current status
Figures as on 9 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Yashashree | NA | 25 | 0 | 0 | 0 | 0 |
| Yashashree | NA | 25 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 9 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 10%.
Yashashree37%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 10% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Yashashree37%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 10% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 9 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Yashashree CHS | Kurla | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Yashashree | NA | Rs 13.25 cr | Rs 4.11 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ellora Project Consultants Pvt Ltd |
| Architect | G M Arch Pvt Ltd |
| Engineer | Ellora Consultants PvT Ltd |
| Engineer | Durva Enterprises |
| Chartered Accountant | N N Bagwan and Associates through Nadim Bagwan |
| Partner | Role in project |
|---|---|
| TRUPTI BUILDCON LLP | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to limitation of words, reasons and explanations for delay are attached herewith in the application. Please refer the same.
Litigation declared2
| Case | Court | Status |
|---|---|---|
| SS782/2016/2016 | Mulund Court | Ongoing |
| Commercial Notice of Motion L no 1031 of 2019 IN Commercial Suit L no 339 of 2019/2019 | Bombay High Court | Disposed |
Complaints filed with MahaRERA7
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000056305 | Samrat Malpani | SiroyaFM Constructions Pvt Ltd | 24/09/2018 |
| CC006000000192987 | Abhijit Birjepatil | M/s Siroya FM Constructions pvt ltd | 16/02/2021 |
| CC006000000198350 | Hirengiri D Goswami & Hemina H Goswami | M/s Siroyafm Constructions Private Limited | 24/09/2021 |
| CC006000000198351 | Hirengiri D Goswami & Hemina H Goswami | M/s Siroyafm Constructions Private Limited | 24/09/2021 |
| CC006000000428963 | Navghar Mulund Yashashree CHSL and others | Siroya FM Constructions Pvt. Ltd. | 24/01/2024 |
| CC12502628 | Raju Kumar | SiroyaFM Constructions Pvt Ltdo | 30/07/2025 |
| CC12601496 | Dattatray Parab | SiroyaFM Constructions Pvt Ltdo | 18/03/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 9 Jul 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 9 Jul 2026Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2028
Documents filed38
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Building plan approvalFile: Building Plan 1to3.pdf | 9 Jul 2026 |
| Commencement certificateFile: CC Revalidation Approved of Bldg Yashashree CHS Ltd Mulund.pdf | 9 Jul 2026 |
| Commencement certificateFile: IOA 7 Floor CC_Part1.pdf | 9 Jul 2026 |
| Declaration and undertaking (Annexure A)File: Annexure A Declaration Cum Undertaking 50.pdf | 9 Jul 2026 |
| Commencement certificateFile: CC Validation Mail Copy.pdf | 9 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 30062026.pdf | 9 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 30062026.pdf | 9 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 30062026.pdf | 9 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 30062026.pdf | 9 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 30062026.pdf | 9 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 30062026.pdf | 9 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 30062026.pdf | 9 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 30062026.pdf | 9 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 30062026.pdf | 9 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 30062026.pdf | 9 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 30062026.pdf | 9 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 30062026.pdf | 9 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 30062026.pdf | 9 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 30062026.pdf | 9 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 30062026.pdf | 9 Jul 2026 |
| Details of encumbrancesFile: Termination by Society.pdf | 11 Sep 2021 |
| OtherFile: Termination by Society.pdf | 11 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5)File: Yashashree Form 5.pdf | 21 Sep 2019 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: 219-SOCIETY REGISTERATION CERIFICATE.pdf | 24 Apr 2018 |
| Details of encumbrancesFile: Yashashree encumbrances.pdf | 31 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate - Yashashree.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: New Doc 2017-07-31.pdf | 31 Jul 2017 |
| Building plan approvalFile: IOD SET.pdf | 30 Jul 2017 |
| Layout approvalFile: Bmc plan compressed.pdf | 30 Jul 2017 |
| Copy of the legal title reportFile: Title Report compressed.pdf | 30 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Bmc plan compressed.pdf | 30 Jul 2017 |
| Building Plan Approval (IOD)File: IOD SET.pdf | 30 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Yashashree - CC.pdf | 30 Jul 2017 |
| Declaration in FORM BFile: siroya fm Form B.pdf | 30 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: YASHASHREE CHS Form 1.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: RERA Allotment letter.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: RERA Draft Agreement.pdf | 30 Jul 2017 |
| PAN CardFile: sfm pan card PDF.pdf | 27 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 38 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Yashashree on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mulund7,600+ in Thane
Filed coordinates, straight-line distance. 119 registered projects within 2 km.
Ekvira and Saishakti
Magnaacasa Infrastructures and Realtors Pr
SENROOFS PHASE - III
PIONEER HOUSING
THE ALTEZZA
M/s. VIPL Varasiddhi Infra Project LLP
SUPREMO PHASE I SALVIA D WING
K V BUILDHOME LLP
SUPREMO PHASE II, WING C known as SAKURA
K V BUILDHOME LLP
Aveza Phase 2
Tata Housing Development Company Limited
See every Thane project, with the district possession charts
Builder: TRUPTI BUILDCON LLP
TRUPTI BUILDCON LLP has 1 registration on MahaRERA, including Yashashree. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if Yashashree is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Yashashree?
The registered promoter entity is TRUPTI BUILDCON LLP, a limited liability partnership as per the filing. Its LLPIN AAX-2440 and GSTIN 27AARFT6649K1Z8 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Yashashree?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Yashashree?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Yashashree?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Yashashree?
The professionals named in the filing: Architect: Ellora Project Consultants Pvt Ltd; Architect: G M Arch Pvt Ltd; Engineer: Ellora Consultants PvT Ltd; Engineer: Durva Enterprises; Chartered Accountant: N N Bagwan and Associates through Nadim Bagwan. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Yashashree?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback