Home / Browse projects / Mumbai Suburban, Maharashtra / Aveza Phase 2
Aveza Phase 2
By Tata Housing Development Company Limited
RG-MH-25416 · RERA P51900007740 · Last updated on MahaRERA portal: 19 Jan 2026
Source: official MahaRERA filing
Red flags
- De-registered
- Possession 10 months past the filed date
- Litigation declared, 2 cases
Clear
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Aveza Phase 2 is a Residential / Group Housing project by Tata Housing Development Company Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51900007740 on 17 Aug 2017. Possession was promised by 30 Dec 2025 and is now 10 months past that date. 0 of the 296 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete.
At a glance
Project
- NameAveza Phase 2
- TypeResidential / Group Housing
- Location
- Navghar Road
- Mulund East
- Opp Navghar Police Station
- MHADA Colony
- Mulund East
- Kurla
- Mumbai Suburban
- 400081
- Pincode400081
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900007740
- ReraGenie IDRG-MH-25416
Builder
- NameTata Housing Development Company Limited
- Entity typeCompany
- CINU45300MH1942PLC003573
- GSTIN27AAACT0191Q1ZY
- Managing DirectorSanjay Bhupender Dutt
- ChairpersonBanmali Surendra Kumar Agrawala
- DirectorsSandhya Shailesh Kudtarkar, Kamlesh Mansukhlal Parekh, Ankur Dalwani, Sudip Mullick
- Other registrations2 more →
- Completed1 of 3
- No longer live2 lapsed, de-registered or revoked
- Declared earlier projects25 →
Key dates
Key facts
Registration and timeline
- StatusDe-registered
- Registered on17 Aug 2017
- Promised completion30 Dec 2025
- Revised completionNone
- Buildings1 building record
- Documents filed137 files
Current status
Figures as on 19 Jan 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Tower D | NA | 65 | 60 | 296 | 0 | 296 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 19 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.
Tower D: 0% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 19 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Richa Realtors | Mumbai City | Mumbai City |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Tower D | NA | Rs 212.91 cr | - |
| - | NA | Rs 34.75 cr | Rs 9.13 lakh |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | KAPADIA ASSOCIATES DESIGN LLP |
| Engineer | UNIVERSAL CONSULTANTS & VALUERS LLP |
| Engineer | MANOJ SHARMA |
| Chartered Accountant | JVB & Co |
| Chartered Accountant | BSR AND CO LLP |
| Partner | Role in project |
|---|---|
| Tata Housing Development Company Limited | - |
Litigation declared2
| Case | Court | Status |
|---|---|---|
| 2051/2015 | Bombay High Court | Reply of the MCGM Respondent At urgent Admission Stage |
| Thane Compliant ULP No 235 of 2016/2016 | Industrial Labour Court | Kept for appearance of the Parties and Next date is Twenty Six April Two Thousand Eighteen |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 28 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed137
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 137 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: avza form 1.pdf | 19 Jan 2026 |
| Withdrawal Update Form 2File: Aveza - Engr Cert Phase 2 Dec 25.pdf | 19 Jan 2026 |
| Withdrawal Update Form 3File: ca form 3.pdf | 19 Jan 2026 |
| Withdrawal Update Form 1File: aveza phase 2 form 1.pdf | 6 Nov 2025 |
| Withdrawal Update Form 2File: aveza phase 2 form 2.pdf | 6 Nov 2025 |
| Withdrawal Update Form 3File: aveza phase 2 form3 sept 25.pdf | 6 Nov 2025 |
| Form 5 (FY 2024-2025)File: aveza phase 2 form new.pdf | 24 Sep 2025 |
| Disclosure of sold/ booked inventoryFile: AVEZA Phase 2.pdf | 15 May 2025 |
| Certificates of CA (Form 3)File: Certificate of CA (Form 3).pdf | 20 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 27 Certificates of Engineer (Form 2)(Mandatory for only ongoing project).pdf | 9 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2 Engineers Certificate on Quality Assurance (Form 2A FY 2024-25).pdf | 9 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 32 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf | 8 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Ph 2 Q3 2 1 2025.pdf | 17 Jan 2025 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate Ph 2 Q3 16 1 2025.pdf | 17 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineering Certificate Ph 2 Q3 3 1 2025.pdf | 17 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Signed Form 1 - Aveza Phase 2.pdf | 27 Nov 2024 |
| Certificates of CA (Form 3)File: Signed - Form 3 - Aveza Phase 2_compressed.pdf | 27 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Cert Form 1 Ph 2 Sept 24.pdf | 20 Oct 2024 |
| Certificates of CA (Form 3)File: Aveza Phase 2 Form 3 Sep24.pdf | 20 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Aveza Form 2 Phase 2 Sept 24.pdf | 20 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Aveza Phase 2.pdf | 7 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Aveza Phase 2.pdf | 7 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20240Arc Certificate.pdf | 19 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_Q1_Eng Cert_Phase 2.pdf | 19 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3_Q1_CA certificate_Phase 2.pdf | 19 Jul 2024 |
| Certificates of CA (Form 3)File: Q4_Form 3_Phase 2_CA certificate.pdf | 18 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Ph 2- Mar 24.pdf | 15 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 eng cert Phase 2- Mar 24.pdf | 15 Apr 2024 |
| Form 2AFile: form 2A Quality Mar 24 - Phase 2.pdf | 15 Apr 2024 |
| Certificates of CA (Form 3)File: Q3_CA Certificate_Phase II.pdf | 16 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q3_Arch Certificate_Phase II.pdf | 11 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Q3_Engg Certificate_Phase II.pdf | 11 Jan 2024 |
| Certificates of CA (Form 3)File: Q2_CA Certificate_Phase II.pdf | 23 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Q2_Engineer Certificate_Phase II.pdf | 11 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q2_Arch Certificate_Phase II.pdf | 9 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Phase-2 RERA Certificate_1_11zon.pdf | 30 Sep 2023 |
| Certificates of CA (Form 3)File: 2023_Q1_Form 3_Phase II_CA certificate.pdf | 17 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2023_Q1_Form 2_Phase II_Eng certificate.pdf | 10 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2023_Q1_Form 1_Phase II_Architect Certificate.pdf | 3 Jul 2023 |
| Certificates of CA (Form 3)File: Form 3 - CA certificate - Aveza Phase 1_Mar-23.pdf | 23 May 2023 |
| Certificates of CA (Form 3)File: Form 3 - CA certificate - Aveza Phase 2_Mar-23.pdf | 23 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Arch Certificate - Aveza Phase 2.pdf | 13 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Eng Certificate - Aveza Phase 2.pdf | 13 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Q3 Eng Cert Dec 22- Aveza Phase 2.pdf | 11 Feb 2023 |
| Certificates of CA (Form 3)File: Q3 FORM 3_Aveza _Phase II - Dec 22.pdf | 11 Feb 2023 |
| Certificates of CA (Form 3)File: Q2 FORM 3_Aveza _Phase II - Sept 22.pdf | 1 Dec 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q2 Form 1 arch cert-Ph 2-Sept 22.pdf | 20 Oct 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q2 Form 1 arch cert-Ph 2-Sept 22.pdf | 20 Oct 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Sept 22- Aveza Phase 2.pdf | 20 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5-Aveza Phase II FY 21-22.pdf | 6 Oct 2022 |
| Certificates of CA (Form 3)File: Q1 FORM 3_Aveza _Phase II - Jun 22.pdf | 6 Sep 2022 |
| Certificates of CA (Form 3)File: Q4 Form 3_Mulund_Phase 2 - Mar-22.pdf | 19 Aug 2022 |
| Certificates of CA (Form 3)File: Q4 Form 3_Mulund_Phase 2 - Mar-22.pdf | 19 Aug 2022 |
| Disclosure of sold/ booked inventoryFile: Q1 Aveza Phase 2.pdf | 19 Jul 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20220711110655.pdf | 12 Jul 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Aveza Ph2 Q3 2021-22.pdf | 7 Apr 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Aveza Ph2 Q4 2021-22.pdf | 7 Apr 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Aveza Ph2 Q3 2021-22.pdf | 6 Apr 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Aveza Ph2 Q4 2021-22.pdf | 6 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: THDC RERA Aveza Phase II 2020-21.PDF | 18 Nov 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arch Cert Q2 Aveza phase 2.pdf | 1 Nov 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arch Cert Q2 Aveza phase 2.pdf | 1 Nov 2021 |
| Disclosure of sold/ booked inventoryFile: Q2 Aveza Phase 2.pdf | 29 Oct 2021 |
| Certificates of CA (Form 3)File: Q2 FORM 3_Aveza _Phase II - Sept 21.pdf | 29 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Aveza Quality Certificate Sept 21 - Phase II.pdf | 9 Oct 2021 |
| Form 2AFile: Aveza Quality Certificate Sept 21 - Phase II.pdf | 9 Oct 2021 |
| Certificates of CA (Form 3)File: FORM 3_Mulund_Phase II - Q1 Jun 21.pdf | 7 Sep 2021 |
| Certificates of CA (Form 3)File: Q4 Form 3 Aveza Ph2 March 2021.pdf | 1 Sep 2021 |
| Disclosure of sold/ booked inventoryFile: Sold Booked Inventory Aveza Ph2 Q1 21-22.pdf | 30 Jul 2021 |
| Disclosure of sold/ booked inventoryFile: Phase 2 Aveza.pdf | 30 Jul 2021 |
| OtherFile: Error in uploading Unit sold booked -THDCL.pdf | 30 Jul 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form A Aveza Ph2 Q1 2021-22.pdf | 16 Jul 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form A Aveza Ph2 Q1 2021-22.pdf | 9 Jul 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Aveza Ph2 Q1 2021-22.pdf | 9 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Aveza Ph2 Q4 2020-21.pdf | 6 Jul 2021 |
| Disclosure of sold/ booked inventoryFile: Aveza ph2 Unit sold April 21.pdf | 27 May 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Q4 Form 2 Aveza Ph2 Jan -March 2021.pdf | 28 Apr 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Q4 Form1 Aveza Ph2 march 2021.pdf | 23 Apr 2021 |
| Certificates of CA (Form 3)File: Q3 Form 3 Aveza Ph2 Oct-Dec 2020-2021.pdf | 6 Feb 2021 |
| Form 2AFile: Q3 Form 2A Aveza Ph2 Dec 2020.pdf | 27 Jan 2021 |
Promoter's earlier projects17
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Amantra PH 1 Tower A A3 | Kalyan Bhiwandi Junction Ranjnoli Village Dist Thane Pin 421302 | 92 | Completed | Dec 2015 | Late, Mar 2016 |
| Amantra PH 1 Tower L B12 | Kalyan Bhiwandi Junction Ranjnoli Village Dist Thane Pin 421302 | 197 | Completed | Nov 2015 | Late, Mar 2016 |
| Amantra PH 1 Tower D A4 | Kalyan Bhiwandi Junction Ranjnoli Village Dist Thane Pin 421302 | 127 | Completed | Nov 2015 | Late, Mar 2016 |
| Amantra PH 1 Tower C A5 | Kalyan Bhiwandi Junction Ranjnoli Village Dist Thane Pin 421302 | 114 | Completed | Nov 2015 | Late, Mar 2016 |
| Amantra PH 1 Tower E B6 | Kalyan Bhiwandi Junction Ranjnoli Village Dist Thane Pin 421302 | 168 | Completed | Sep 2015 | Late, Mar 2016 |
| Amantra PH 1 Tower B A2 | Kalyan Bhiwandi Junction Ranjnoli Village Dist Thane Pin 421302 | 120 | Completed | Sep 2015 | Late, Mar 2016 |
| Inora Park PH II - 3 BHK | Land Survey No 27by2Pand 27by9P Undri Tal Haveli Pune | 104 | Completed | Oct 2014 | Jul 2014 |
| Eden Court, PH III -Centraus Mall | Plot No II G 7 8 Action Area II ew Town Rajarhat Kolkata 700 156 | 38 | Completed | Mar 2014 | Late, May 2014 |
| Eden Court, PH II - T-D,E | Plot No II G 7 8 Action Area II ew Town Rajarhat Kolkata 700 156 | 171 | Completed | Jun 2013 | Late, Sep 2013 |
| Prive Phase II - 25 Villas | Prive Village Lonavala Old Khandala Road opposite Sadhna Kutir Lonavala 410 401 | 25 | Completed | Mar 2013 | Late, Aug 2014 |
| Prive Phase II - 13 Villas | Prive Village Lonavala Old Khandala Road opposite Sadhna Kutir Lonavala 410 401 | 13 | Completed | Mar 2013 | Late, Apr 2015 |
| Inora Park PH I - 2,2 1/2 BHK | Land Survey No 27by2Pand 27by9P Undri Tal Haveli Pune | 141 | Completed | Jan 2013 | Late, Aug 2013 |
| Prive Phase I - 35 Villas | Prive Village Lonavala Old Khandala Road opposite Sadhna Kutir Lonavala 410 401 | 35 | Completed | Mar 2012 | Late, Jun 2013 |
| Eden Court, PH I - T-A,B,C | Plot NoII G7 8 Action Area II New Town Rajarhat Kolkata 700 156 | 348 | Completed | Mar 2012 | Late, Jun 2012 |
| New Haven Boisar 1 and Row House | Chillar Road Betegaon Boisar East Maharashtra 401501 | 1,438 | Completed | Dec 2011 | Late, Mar 2015 |
| Aquila Heights | Sy No 27 HMT HMT Factory Main Road Near HMT School Peenya Plantation Yelahanka Hobli Bengaluru North Taluk Bengaluru 560053 | 108 | Completed | Dec 2011 | Late, Oct 2012 |
| Shubh Griha Boisar I | Chillar Road Betegaon Boisar East Maharashtra 401501 | 1,578 | Completed | Jun 2011 | Late, Dec 2013 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 137 filed documents as one ZIP, foldered, with a manifest
Keep Aveza Phase 2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mulund East, Opp Navghar Police Station, MHADA Colony, Mulund East,6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 165 registered projects within 2 km.
Ekvira and Saishakti
Magnaacasa Infrastructures and Realtors Pr
SENROOFS PHASE - III
PIONEER HOUSING
THE ALTEZZA
M/s. VIPL Varasiddhi Infra Project LLP
SUPREMO PHASE I SALVIA D WING
K V BUILDHOME LLP
SUPREMO PHASE II, WING C known as SAKURA
K V BUILDHOME LLP
SENROOFS PHASE IV, BUILDING NO D1, WING A KNOW
PIONEER HOUSING
See every Mumbai Suburban project, with the district possession charts
Builder: Tata Housing Development Company Limited
TATA HOUSING DEVELOPMENT COMPANY LIMITED has 3 registrations on MahaRERA, including Amantra Phase 2 and Aveza Phase 1. Its filings disclose 25 earlier MahaRERA projects: declares 2 of 25 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that Aveza Phase 2 shows as de-registered on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Aveza Phase 2 is delayed beyond 30 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Aveza Phase 2?
The registered promoter entity is Tata Housing Development Company Limited, a company as per the filing. Its CIN U45300MH1942PLC003573 and GSTIN 27AAACT0191Q1ZY can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Aveza Phase 2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Aveza Phase 2?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Aveza Phase 2?
The professionals named in the filing: Architect: KAPADIA ASSOCIATES DESIGN LLP; Engineer: UNIVERSAL CONSULTANTS & VALUERS LLP; Engineer: MANOJ SHARMA; Chartered Accountant: JVB & Co; Chartered Accountant: BSR AND CO LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Aveza Phase 2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback