Home / Browse projects / Mumbai Suburban, Maharashtra / WORLIWALA CHSL

Completed No litigation declared Residential / Group Housing project

WORLIWALA CHSL

By SHAMIK & SANGHVI DEVELOPERS LLP

RG-MH-52670 · RERA P51800047017 · Last updated on MahaRERA portal: 24 Jan 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 45 documents Report an error

WORLIWALA CHSL is a Residential / Group Housing project by SHAMIK & SANGHVI DEVELOPERS LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800047017 on 26 Sep 2022. The registration is recorded completed; possession was promised by 30 Dec 2025.

At a glance

Project

  • NameWORLIWALA CHSL
  • TypeResidential / Group Housing
  • Location
    • M.G. ROAD
    • VILE PARLE (EAST)
    • Andheri
    • Mumbai Suburban
    • 400057
  • Pincode400057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800047017
  • ReraGenie IDRG-MH-52670

Builder

  • NameSHAMIK & SANGHVI DEVELOPERS LLP
  • Entity typePartnership
  • PartnersKishore Kumar Sukhlal Jain, Ashok Bhurmal Jain

Key dates

this monthRegisteredSep 2022PromisedDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on26 Sep 2022
  • Promised completion30 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed45 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WORLIWALA CHSLNA100000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

WORLIWALA CHSL: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 24 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed39

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots39
Closed/Covered35
Open Space4

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area745 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Worliwala Co-operative housing society LtdAndheriMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI2790.32
Proposed, not sanctioned2,790 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKADAMGIRI COMPLEX, HANUMAN ROAD, VILE PARLE EAST MUMBAI 400057

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPriyank Bhatt
EngineerSURA & Associates
Chartered AccountantCA Abhishek Sewak
PartnerRole in project
SHAMIK & SANGHVI DEVELOPERS LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Aug 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Sep 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Jun 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Jun 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 24 Jan 2025

Documents filed45

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Architect Certificate Completion.pdf24 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate form 3.pdf24 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer certificate FORM 2.pdf24 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCCUPATION_CERTIFICATE.pdf24 Jan 2025
Disclosure of sold/ booked inventoryFile: Inventory list.pdf24 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 CA.pdf24 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH_RERA_CFT_FOR_WORLIWALA.pdf19 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer_certificate.pdf19 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2 A _ 2022 - 23.PDF19 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2 A _ 2023 - 24.PDF19 Jul 2024
Disclosure of sold/ booked inventoryFile: INVENTORY.PDF19 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Certificate.pdf19 Jul 2024
Disclosure of sold/ booked inventoryFile: INVENTORY DISCLOUSRE.PDF22 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 ARCH RERA CFT FOR WORLIWALA .pdf8 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 engineer certificate (1).PDF8 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE Form 3_.pdf8 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 fy2022-23.PDF17 Oct 2023
Building plan approvalFile: FULL IOD FINAL.pdf22 Jun 2023
Building Plan Approval / NA Order for plotted developmentFile: FULL IOD FINAL.pdf22 Jun 2023
Commencement Certificates / NA Order for plotted developmentFile: FUll CC upto 9th floor.pdf22 Jun 2023
Declaration about Commencement CertificateFile: Declaration of FULL CC UPTO 9TH FLOOR.PDF22 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH RERA CFT FOR WORLIWALA .pdf30 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: worliwala ENGINEERING CERT.PDF30 Mar 2023
Details of encumbrances concerned to FinanceFile: ENCUMBRANCES CERTIFICATE TO FINANCE(1).PDF9 Sep 2022
CERSAI detailsFile: UNDERTAKING FOR CRESAI REPORT (1).PDF9 Sep 2022
CERSAI detailsFile: CERSAI_Search_Report_worliwala (No security created) .pdf9 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA FORM 3.pdf9 Sep 2022
Layout approvalFile: IOD AMENDED PLAN UPTO 6TH FLOOR (1).pdf8 Sep 2022
Building plan approvalFile: IOD AMENDED PLAN UPTO 6TH FLOOR (1).pdf8 Sep 2022
Copy of Layout Approval (in case of layout)File: IOD AMENDED PLAN UPTO 6TH FLOOR (1).pdf8 Sep 2022
Building Plan Approval / NA Order for plotted developmentFile: IOD AMENDED PLAN UPTO 6TH FLOOR (1).pdf8 Sep 2022
Building plan approvalFile: IOD LETTER.pdf27 Aug 2022
Layout approvalFile: AMENDED IOD LETTER.pdf27 Aug 2022
PAN CardFile: PAN - Shamik -Sanghavi Developers LLP (3).pdf27 Aug 2022
Copy of the legal title reportFile: Legal Title Report Format A.pdf27 Aug 2022
Details of encumbrances concerned to LegalFile: ENCUMBRANCES CERTIFICATE - Legal.PDF27 Aug 2022
Copy of Layout Approval (in case of layout)File: AMENDED IOD LETTER.pdf27 Aug 2022
Building Plan Approval / NA Order for plotted developmentFile: IOD LETTER.pdf27 Aug 2022
Commencement Certificates / NA Order for plotted developmentFile: FIRST CC RE-ENDORSEMENT.pdf27 Aug 2022
Declaration about Commencement CertificateFile: Declaration for CC -FORMAT D.PDF27 Aug 2022
Declaration in FORM BFile: FORM B AFFIDAVIT CUM DECLARATION_Final.pdf27 Aug 2022
Proforma of Allotment letterFile: Proforma Allotment letter and Agreement for sale.pdf27 Aug 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: SEPERATE BANK DETAILS -FORMAT FINAL.pdf27 Aug 2022
Deviation Report with respect to Allotment letterFile: NO Deviation for allotment Letter.PDF27 Aug 2022
Deviation Report with respect to model copy of AgreementFile: NO Deviation for agreement for sale.PDF27 Aug 2022

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep WORLIWALA CHSL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VILE PARLE (EAST)6,700+ in Mumbai Suburban

2 kmWORLIWALA CHSLCompleted 145Lapsed / revoked 68Other 153Dot size: filed unitsN

Filed coordinates, straight-line distance. 366 registered projects within 2 km.

Builder: SHAMIK & SANGHVI DEVELOPERS LLP

SHAMIK & SANGHVI DEVELOPERS LLP has 1 registration on MahaRERA, including WORLIWALA CHSL. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if WORLIWALA CHSL is delayed beyond 30 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of WORLIWALA CHSL?

The registered promoter entity is SHAMIK & SANGHVI DEVELOPERS LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in WORLIWALA CHSL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for WORLIWALA CHSL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at WORLIWALA CHSL?

The professionals named in the filing: Architect: Priyank Bhatt; Engineer: SURA & Associates; Chartered Accountant: CA Abhishek Sewak. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in WORLIWALA CHSL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About WORLIWALA CHSL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save WORLIWALA CHSL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.